INSPECTION CHECKLIST - BOREPILING WORK Q

Form Ref. : KI/FORM/QC/BP/01

PROJECT : SENAYAN SQUARE OFFICE TOWER 3 DATE :

SUB-CONTRACTOR :

PILE NO.

CRITERIA / Acceptable
NO. ITEMS TO BE CHECKED REMARKS
CH'K METHOD YES NO DATE

1 Pre-Installation
a) Peg position Theodolite
b) Bore location 6m from new casted pile Record Sign : ( STS )
c) Collection pit Visual
d) Rebar cage Dwg
e) Concrete cover ; 75mm Measure Sign : ( KI )

2 Bore piling
a) Casing position Offset line Actual :
b) Kelly bar verticality Spirit Level
c) Toe Level ; RL -30m Measure Actual : Time :
d) Base cleaning min.30min after Record Time :

e) Rebar Installation Measure Cage 1 : 12m : Lapping 1 : mm

Cage 2 : 12m : Lapping 2 : mm

Cage 3 :

f) Tremie pipe
- Cleanliness Visual
- Top level Measure Actual :
- Tremie total length Record Actual :
- Toe depth max.200mm above toe Calculate Actual :
g) Bore hole water level
min. 2m above ground water level Measure Water level : 3m
Bore hole water level :

Sign : Sign :

3 Concreting G30N
a) Concrete Slump ; 18 + 2 Slump test Actual :
b) Time Time Start : Finish :
c) Top level ; min.1 x above cut off level Measure Actual :
d) Concrete Volume Record Dwg : Actual
Differences % :

4 OTHER COMMENT IF ANY ;