Professional Documents
Culture Documents
General Inspection Test Plan
General Inspection Test Plan
SUPPLIES.
Receiving materials
- Visual inspection
- Dimensional control
- Documentation review
CIVILWORK / TOPOGRAPHY
Preliminar y topography
- Survey control
Verification of levels
- Survey control
- Check of the phreatic level
- Visual inspection
Compaction of padding in work area
- Proctor Test
Piling
Welding (prefabricated)
Welding (assembly)
COATING / PAINTING
- Visual inspection
- Needle, Surface profile, percentage as per measurement as per specification.
Coating application
- Visual inspection
- MTR verification
- Thickness verification
- HC/PP verification during installation
- Correctness of final installation.
MECHANICAL ASSEMBLY
Installation of equipment
- As ASME PCC1
- Gasket inspection
- Bolting material inspection
- Flange alignments
- Torque tightening.
MECHANICALTESTS
Pressure testing shall include but not be limited to the following equipment and piping system:
- Pump casings
- HP/IP steam s y stem
- HP feed water system
- Fire protection system (test pressure as per NFPA)
- Fuel gas system
- Chemical feed systems
- SCR ammonia system
- All underground piping.
- Condenser air removal system
- Close d cooling water system
- Potable water system
- Makeup water system
- Condensate system
- Demineralised water
Watertight Test
Exhaustive check of pipe in the control of support, free expansion and number of supports
Exhaustive check of pipe insulation in terms of sealing and reinforcing sleeve arrangement of the insulation
on the supports.
CATHODIC PROTECTION
- Verification of sections.
- Check voltage drop by connecting a load on the farthest point of the circuit.
- Identification circuits.
- Identification of the neutral conductor and protective.
- Continuity test of protective conductor and equipotential.
- Insulation resistance between phases and earth.
- Insulation resistance between phases.
- Visual inspection
- Ultrasonic thickness measurement
Installation of instruments
ELECTRICAL TEST
Checklist of :
- General electricity (medium and low voltage)
- Electrical switchboards
- Tray and conduits
- Cable junction boxes
- Low voltage cables
- Lighting
- Sockets and mechanisms.
- Measures of consumption
- Acoustic and vibration measurements
Precommisining- General .
- Preliminary test s which are tests performed prior to rotation or energizing at normal voltage or admission or
normal water or air pressure to the plan t under test.
- Tests on completion which is tests to progressively prove the correct operation of complete auxiliary systems
and of the main plant items..
- Reliability y run
- As per applicable Procedure.
- Start-up mechanic a l, running test, adjustment of turbine inlet guide vane control and interlocking, etc. The
measured data such as pressure , temperature, vibration, adjustable speed range, etc. The measured data such as
pressure, temperature, vibration, adjustable speed range etc. shall be observed and recorded.
- Checking of cooling system and lube oil system.
- Checking of over-speed tripping device s , protection and interlocking system, start-up and shut-down sequence of
auxiliary system .
- Noise and vibration level measurement.
- Manual and automatic synchronization.
- Generator Protection relay testing.
- Checking of loading capability.
- Lead rejection and governor tests.
- Preliminary testing of start-up times.
- Start-up and performance Guarantee tests, bearing in account correction curves, metering, fuel analysis, Instrument
Test Measurement Uncertainly, Performance Tolerances,
- Environmental Performance Guarantee Tests (noise level tests in accordance with ISO 619 0:19 99 and method in
accordance with BS 414 2:10 07)
CONFORM TO WORK
- Documentation Review
Reception of documents
Documentation Review