Professional Documents
Culture Documents
Contracts
Contracts
Construction Ltd.
Vs.
Respondent: Tarapore and Co. and another
AIR1996SC2268
In the Supreme Court of India
Hon'ble Judges/Coram:
S.C. Agrawal and G.T. Nanavati, JJ.
FACTS OF THE CASE:
The HSCL awarded a contract to the contractor (Tarapore and co.) for
construction of civil works in its Visakhapatnam Steel Plant and the formal
contract was signed on 25.10.1984.
It was a lumpsum contract for which a deadline was set but the contractor
could not finish work on time and extended the deadline.
On 28.8.1986 some disputes arose and the contractor initiated to solve it
through arbitration and now the dispute was pending before the arbitrators
appointed.
In August, 1988 by mutual agreement the contract work was reduced and the
contract price was fixed at Rs. 4.5 crores.
Again, the deadline was extended due to unfinished work.
Finally, when for the 2nd time the reduced work could not be completed on the
set date, HSCL cancelled the contract on 17.10.1988.
facts continued..
In between 30.1.84 and 8.12.87, fourteen guarantees had been given by Bank of India in
favour of HSCL at the instance of the Contractor for various objects.
The bank guarantee held that:
i. HSCL would be indemnified against any loss or damage caused to or suffered by it
by reason of any breach by the contractor of any term and condition of the contract.
ii. HSCL shall be the sole Judge on the question as to whether the contractor has
committed any breach of the contract and what is the extent of loss or damage.
iii. the decision of HSCL in this behalf shall be treated as final and binding on the bank.
iv. bank has undertaken to pay HSCL on demand any amount payable by the contractor
without any demur and protest, without any reference to the contractor and such
demand by HSCL has to be regarded as conclusive and binding on the bank
notwithstanding any difference between the HSCL and the contractor.
On the day of cancellation of contract HSCL demanded its damages to be paid by the
bank.
PRINCIPLE CREDITOR
DEBTOR (HSCL)
(CONTRACTOR
TARAPORE AND CO.)
SURETY
(BANK OF INDIA)
BEFORE THE HC:
The contractor had approached principle subordinate judge at
Vishakhapatnam contending that since disputes were pending before
the arbitrators HSCL should be restrained from encashing the bank
guarantees but the court on finding that the guarantee was
unconditional refused to grant injuction.
A revision petition was made before HC with the same prayer.
The principle observed by the HC was that unless there is fraud or
special circumstances or equities exist, the beneficiary cannot be
restrained from encashing the letter of credit, even if there are disputes
between the beneficiary and the person at whose instance the letter of
credit was given by the Bank. The same principle is extended in regard
to the performance guarantees or performance bonds executed by the
banks in favour of the beneficiaries.
DECISION OF HC:
The HC searched for special equities or special circumstances.
It considered the position of law with respect to liquidated damages in
our country and relying upon the decision of Union of India v. Raman
Iron Factory "Hence there cannot be any agreement in regard to the
amount that has to be allowed except the upper limit that can be fixed,
in case of breach it held that any term in the agreement that one of the
parties shall be the sole judge to quantify the same has to be held as
invalid.
Therefore the liabilities were to be decided by the arbitrators and
HSCLs contention of being the sole judge was rejected thus
restraining it from encashing the bank guarantee.
ISSUE RAISED IN THE SC:
The petitioner had filed SLP against the Andhra Pradesh high courts
order of injuction where the issue to be decided was: