Time Estimate For Gravel Pack Job
Time Estimate For Gravel Pack Job
Sl. ESTIMATED
ACTIVITY
No TIME (Days)
Casing cleaning trip, Filtration of brine to required cleanliness level for Gravel pack
1 4
job& changeover of well volume to brine
2 RIH with Wireline to Set Up Bridge Plug (SLB) 1
3 TCP trip. Perforation( SLB) 2
Run in lower completion string with FIV, screens, Seal bore packer etc. Set packer.
Rigging up of Gravel pack pumping assembly and testing. Perform Gravel pack job.
4 4
Pull out Lower completion assembly & Rig down Gravel pumping assembly.(HLB
COMPLETIONS and HLB PE TEAM)
5 Carryout space out run and with Completion string (Single by single run in) 2
6 Retrieval of Bore protector from tree along with Jet Wash of Tubing hanger Profile 1
Rig up & R/I upper completion assembly till tubing hanger including Gauges, Chemical
7 Injection mandrels, GLVs & Safety valve. Terminate the cables/lines at the tubing 3
hanger
Make up THRT & SSTT with Tubing hanger. Test SSTT and R/I assembly with the
8 1.5
landing string
Make up Big bore Flow head to the landing string and land and lock tubing hanger to
9 0.5
the subsea tree.
10 Slick line job (sliding sleeve opening) 0.5
11 Change over tubing volume of brine to Diesel 1
12 Slick line job(Sliding sleeve closing) 0.5
13 Set the upper packer. Activate well, clean out and 2
TOTAL 23