PROJECT : PROPOSED PENINSULA GARDEN MIDTOWN HOMES - MAHOGANY TOWER

SUBJECT : CONSTRUCTION PROGRAMME-RECOVERY SCHEDULE


DATE OF START : NOVEMBER 3, 2015
DURATION : 23 MONTHS
BALANCE : 3 MONTHS (JULY - 3RD OCT 2017)
REVISION : 002.2

TARGET
PLANNED
ITEM/DESCRIPTION START RECOVERY
FINISH
END DATE

A. Structural Works Balance

A.1 Roof Beams at GL A-D/5-7 6-Jan-17 31-Jan-17 21-Mar-17

A.2 Concrete Gutter at GL A-D/1-6 & saddle tank 24-Jan-17 14-Feb-17 2-Mar-17

A.3 Miscellaneous (Plant Boxes, external,etc) 15-Feb-17 31-Mar-17 31-Aug-17

B. Architectural Works 01-Mar-16 30-Sep-17 30-Sep-17

B.1 Masonry

B.1.a Fabrication of Precast Wall Panel 1-May-16 4-Feb-17 21-Mar-17

B.1.b Installation of Precast Wall Panel(Exteri 22-May-16 28-Feb-17 27-Apr-17

B.1.c Fabrication of CHB 1-Mar-16 15-Feb-17 10-Jun-17

B.1.d CHB laying interior wall(100mm/150m 1-May-16 31-Mar-17 31-Jul-17


21,079,235.36
B.2 Ceiling Finishes_Gypsum works 07-Jul-16 15-Jul-17 15-Aug-17

B.3 Wall Finishes_Gypsum wall 22-Jul-16 15-Jul-17 19-Aug-17

B.4 Waterproofing 01-Jul-16 21-Mar-17 30-Aug-17

B.5 Plastering/ Rubbed Concrete 26-May-16 30-Apr-17 15-Aug-17

B.6 Steel Works

B.6.a Roof/Roof framing 06-Jan-17 28-Feb-17 8-Jul-17

B.6.b Stair & Metal Railing 12-Jul-16 28-Feb-17 4-Aug-17

B.7 Painting Works 07-Jul-16 30-Sep-17 30-Sep-17

B.8 Tiling Works 22-Aug-16 30-Jul-17 09-Sep-17

B.9 Vinyl Tiles 16-Sep-16 30-Jul-17 31-Aug-17

B.10 Wooden Baseboard 20-Aug-16 31-May-17 05-Aug-17

B.11 PVC Doors and Jambs 16-Oct-16 15-May-17 26-Aug-17


H. Owner Supplied Materials

B.12 Aluminum Frames and Glass Windows 01-Jul-16 30-Mar-17

B.12 Wooden Doors & Jambs 22-Jun-16 21-Apr-17 22-Jul-17

B.13 Louvers and Frames 03-Jan-17 30-May-17 22-Jul-17

B.14 Metal Doors and Jambs 01-Dec-16 30-May-17 22-Jul-17

B.15 Door Closers/Locksets 01-Oct-16 15-Aug-17 15-Aug-17

B.16 Ceramic Tiles; Tiling Works 22-Aug-16 30-Jul-17 31-Aug-17

B.17 Toilet Accessories (facial mirror/soap & paper holder) 07-Aug-16 30-Aug-17 30-Aug-17

C. Punchlisting & Cleaning 01-Feb-17 14-Sep-17 03-Oct-17

D. Turn-Over 07-Feb-17 03-Oct-17 03-Oct-17

Projected Accomplishment

Accumulative Projected
Projected Monthly Accomplishment
Manpower Loading

Noted By:

Prepared for Implementation By:


GANY TOWER

701 CALENDAR DAYS


2017
15 16 17 18 19 20 21 22
January February March April May June July August

0.1032

0.0639 0.0639 0.0639 0.0639 0.0639 0.0639 0.0639 0.0639

0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595 0.0595

0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489 0.0489

0.0284 0.0284 0.0284 0.0284 0.0284 0.0284

0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158

0.0683 0.0683 0.0683 0.0683

0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06

0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775 0.1775

0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.1343 0.1343 0.1343 0.1343 0.1343 0.1343

0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066

0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175 0.0175

0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046
0.0215 0.0215 0.0215 0.0215 0.0215 0.0215

0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033

0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038 0.00038

0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336 0.0336

0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039

0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.02
1.27

1.17

1.17

1.17

1.10

1.10

1.05

1.05

0.93

0.93

0.93

0.88

0.72

0.72

0.70

0.70

0.81

0.78

0.79

0.71

0.71

0.71

0.53

0.53

0.42

0.42

0.42

0.42

0.42

0.42

0.42

0.42

0.42

0.42
74.12

75.28

76.45

77.62

78.72

79.82

80.87

81.92

82.84

83.77

84.69

85.57

86.29

87.01

87.72

88.42

89.24

90.02

90.81

91.52

92.23

92.94

93.47

94.00

93.89

94.31

94.73

95.15

95.57

95.99

96.40

96.82

97.24

97.66
77.62% 81.92% 86.29% 89.24% 92.23% 94.31% 95.99% 97.66%
185.0 248.0 248.0 248.0 223.0 223.0 215.0 215.0
January February March April May June July August
2017
C:\Users\USER\Downloads\[RECOVERY TARGET SCHEDULE WITH MANPOWER LOADING_07.29.17 (1).xlsx]Target recovery SChed+MP
Summary Bar Punchlisting/clearing

Installation Bar/ Turn-Over


Activity Bar
Projected completiion

Critical Activities

Adjusted Sched
23 24
September October

0.1775 0.1775 0.1775 0.1775 0.1775


98.08 0.42

ecovery SChed+MP
98.50 0.42

98.92 0.42

180.0
99.76%
99.34 0.42

September
99.76 0.42

100.0 0.24

100.0 0.00

248
100.0 0.00

100%
100.000
October
100 0.00
PROJECT: PGMH-MAHOGANY TOWER
SUBJECT: TARGET RECOVERY SCHEDULE & MANPOWER REQUIREMENT
DATE: JULY 29, 2017
ADDITIONAL MP
TARGET PRESENT TOTAL MP REQUIRED
START DATE DURATION NEED TO MEET
COMPLETION MANPOWER TARGET COMPLETION TO MEET SCHEDULE
ITEM/DESCRIPTON
A. Masonry Plastering (exterior)
1. Cadag's Group
Rear GL 7-10 / 16th-Gutter 31-Jul-17 5-Aug-17 5 8 8
2. Atoy's Group
Rear GL 1-6 / 10th - Gutter 31-Jul-17 12-Aug-17 12 10 10
B. Waterproofing
1. T&B
-13th flr 31-Jul-17 1-Aug-17 1 2
-14th flr 1-Aug-17 6-Aug-17 5 2
-15th flr 7-Aug-17 12-Aug-17 5 2
4 6
-16th flr 13-Aug-17 18-Aug-17 5 2
-17th flr 19-Aug-17 24-Aug-17 5 2
-18th flr 25-Aug-17 30-Aug-17 5 2
2. Balcony
9th flr - 10th flr 31-Jul-17 5-Aug-17 5 2
11th flr - 12th flr 6-Aug-17 11-Aug-17 5 2
13th flr - 14th flr 12-Aug-17 17-Aug-17 5 2 2 4
15th flr - 16th flr 18-Aug-17 23-Aug-17 5 2
17th flr - 18th flr 23-Aug-17 28-Aug-17 5 2
C. Tiling Works
1. T&B
-12th flr 31-Jul-17 3-Aug-17 3 5
-13th flr 4-Aug-17 9-Aug-17 5 5
-14th flr 10-Aug-17 15-Aug-17 5 5
-15th flr 16-Aug-17 20-Aug-17 4 5
3 8
-16th flr 20-Aug-17 25-Aug-17 5 5
-17th flr 26-Aug-17 31-Aug-17 5 5
-18th flr 1-Sep-17 4-Sep-17 3 5
-Ground flr 5-Sep-17 10-Sep-17 5 5
2. Hallway
-14th flr 31-Jul-17 2-Aug-17 2 3
-15th flr 3-Aug-17 8-Aug-17 5 3
-16th flr 9-Aug-17 14-Aug-17 5 3
2 5
-17th flr 15-Aug-17 20-Aug-17 5 3
-18th flr 21-Aug-17 26-Aug-17 5 3
-Ground flr 27-Aug-17 1-Sep-17 5 3
2. Stair 1
-13th flr 3-Aug-17 5-Aug-17 2 2
-14th flr 9-Aug-17 11-Aug-17 2 2
-15th flr 15-Aug-17 17-Aug-17 2 2
1 3
-16th flr 21-Aug-17 23-Aug-17 2 2
-17th flr 27-Aug-17 29-Aug-17 2 2
-18th flr 30-Aug-17 1-Sep-17 2 2
3. Balcony
9th -10th flr 7-Aug-17 10-Aug-17 3 2
11th -12th flr 11-Aug-17 15-Aug-17 4 2
13th -14th flr 16-Aug-17 20-Aug-17 4 2 2 4
15th -16th flr 21-Aug-17 25-Aug-17 4 2
17th -18th flr 26-Aug-17 31-Aug-17 5 2
D. Drywall/Ceiling
1. Drywall
-17th flr 31-Jul-17 15-Aug-17 15 3 2 5
-18th flr 9-Aug-17 19-Aug-17 10 6 1 7
2. Ceiling
-11th-12th flr 31-Jul-17 15-Aug-17 15 4 2 6
-13th-16th flr 31-Jul-17 15-Aug-17 15 3 5 8
-17th flr 31-Jul-17 15-Aug-17 15 3 3 6
-18th flr 3-Aug-17 12-Aug-17 9 6 0 6
TOTAL 86

C:\Users\USER\Downloads\[RECOVERY TARGET SCHEDULE WITH MANPOWER LOADING_07.29.17 (1).xlsx]Target recovery SChed+MP


Target
Item/Description Start Duration Present MP
Completion
A. Drywall & ceiling works balances

A.1 Dry wall


18th floor 8/9/2017 8/19/2017 10 6
17th floor 7/31/2017 8/15/2017 15 3

A.2 Ceiling
18th floor 8/3/2017 8/12/2017 9 6
17th floor 7/31/2017 8/15/2017 15 3
13th-16th floor 7/31/2017 8/15/2017 15 3
11th-12th floor 7/31/2017 8/15/2017 15 4
Option 1 (additional MP) Option 2 (additional OT)
MP to
MP to meet target Add'l MP OT to provide to meet target compare Findings
completion needed completion

7 1 2 6 possible
5 2 4 3 possible

6 0
6 3 4 4 not possible, therefore HODIAH must provid
8 5 4 6 not possible, therefore UNITED must provide
6 2 4 4 possible
therefore HODIAH must provide additional MP
therefore UNITED must provide additional MP
DRYWALL FRAME
33
A B C D E F G H I J K L M N O P Q R MP P Area remaining
2nd
3rd
4th
5th
6th SKY
7th GAR
8th DEN
9th 2 2.44
10th
11th
12th
13th
14th SKY
15th GAR
16th DEN
17th 4 1.626 229.6
18th 6 525

Accomplishment: _Previous
_This period
_Combined/Altered/Bare

DRYWALL BOARD-UP
33
A B C D E F G H I J K L M N O P Q R MP P Area remaining
2nd
3rd
4th
5th
6th SKY
7th GAR
8th DEN
9th N.A 2
10th
11th
2

12th
13th
14th SKY
15th GAR
16th DEN
17th 3 459.2
18th 525

Accomplishment: _Previous
_This period
_Combined/Altered/Bare
CEILING FRAME
3 2 3 11
A B C D E F G H
LEVEL/UNIT

19.18 2nd
3rd
4th
5th
6th
SKY GARDEN
7th
8th
9th
10th
11th
12th
13th
14th
SKY GARDEN
15th
16th
17th
18th

_ Bedroom area Accomplishment: _Previous


_ Kitchen area _This period
_ T&B area _Combined/Alt

CEILING BOARD-UP
3 2 3 11
Area remaining A B C D E F G H
LEVEL/UNIT

19.18 2nd
3rd
4th
5th
6th
SKY GARDEN
7th
8th
9th
10th
11th
12th
13th
14th
SKY GARDEN
15th
321.44 16th
524.8 17th
18th

_ Bedroom area Accomplishment:


_ Kitchen area
_ T&B area
H I J K L M N O P Q R HALLWAY
1 2 3 4

_Previous
_This period
_Combined/Altered/Bare

H I J K L M N O P Q R HALLWAY
1 2 3 4
_Previous
_This period
_Combined/Altered/Bare
HALLWAY P MP Acc. m2 Area remaining p=mh/a
5 6 7 8 9 0

12.6
17.36 13.1 7.86
20.78 2.72
4.94 120.6
1.1474469 2 235.644
105.78
44 163.64
3.1578947 3 20.64 321.56 192.936
0.969697 6 356.24 213.744
107.72

HALLWAY P MP Acc. m2 Area remaining p=mh/a


5 6 7 8 9 0
52.4
52.216
9.38 78.14 60.076
10.4 46.76 h= 38.77928
1.6934801 3 2.22 160.04
313.936 549.58
55 193.56
3.24 384.48
3 455.24 182.096 375.032 h= 25.40867
6 455.24 182.096 395.84 h= 7.996768
80.24
PROJECT: PGMH-MAHOGANY TOWER
SUBJECT: TARGET SCHEDULE & MANPOWER
DATE: JULY 29, 2017

TARGET PRESENT
ITEM/DESCRIPTON START DATE COMPLETION DURATION MANPOWER
B. Masonry (exterior)
1. Cadag's Group
Rear GL 7-10 / 16th-Gutter 31-Jul-17 5-Aug-17 5 8
2. Atoy's Group
Rear GL 1-6 / 10th - Gutter 31-Jul-17 12-Aug-17 12 10
C. Waterproofing
1. T&B
-13th flr 31-Jul-17 1-Aug-17 1 2
-14th flr 1-Aug-17 6-Aug-17 5 2
-15th flr 7-Aug-17 12-Aug-17 5 2
-16th flr 13-Aug-17 18-Aug-17 5 2
-17th flr 19-Aug-17 24-Aug-17 5 2
-18th flr 25-Aug-17 30-Aug-17 5 2
2. Balcony
9th flr - 10th flr 31-Jul-17 5-Aug-17 5 2
11th flr - 12th flr 6-Aug-17 11-Aug-17 5 2
13th flr - 14th flr 12-Aug-17 17-Aug-17 5 2
15th flr - 16th flr 18-Aug-17 23-Aug-17 5 2
17th flr - 18th flr 23-Aug-17 28-Aug-17 5 2
F. Tiling Works
1. T&B
-12th flr 31-Jul-17 3-Aug-17 3 5
-13th flr 4-Aug-17 9-Aug-17 5 5
-14th flr 10-Aug-17 15-Aug-17 5 5
-15th flr 16-Aug-17 20-Aug-17 4 5
-16th flr 20-Aug-17 25-Aug-17 5 5
-17th flr 26-Aug-17 31-Aug-17 5 5
-18th flr 1-Sep-17 4-Sep-17 3 5
-Ground flr 5-Sep-17 10-Sep-17 5 5
2. Hallway
-14th flr 31-Jul-17 2-Aug-17 2 3
-15th flr 3-Aug-17 8-Aug-17 5 3
-16th flr 9-Aug-17 14-Aug-17 5 3
-17th flr 15-Aug-17 20-Aug-17 5 3
-18th flr 21-Aug-17 26-Aug-17 5 3
-Ground flr 27-Aug-17 1-Sep-17 5 3
2. Stair 1
-13th flr 3-Aug-17 5-Aug-17 2 2
-14th flr 9-Aug-17 11-Aug-17 2 2
-15th flr 15-Aug-17 17-Aug-17 2 2
-16th flr 21-Aug-17 23-Aug-17 2 2
-17th flr 27-Aug-17 29-Aug-17 2 2
-18th flr 30-Aug-17 1-Sep-17 2 2
3. Balcony
9th -10th flr 7-Aug-17 10-Aug-17 3 2
11th -12th flr 11-Aug-17 15-Aug-17 4 2
13th -14th flr 16-Aug-17 20-Aug-17 4 2
15th -16th flr 21-Aug-17 25-Aug-17 4 2
17th -18th flr 26-Aug-17 31-Aug-17 5 2
ADD'L MANPOWER
NEEDED TO MEET TARGET
COMPLETION

1
1

2
T&B TILING WORKS TOTAL AREA
WALL FLOOR WALL FLOOR DONE % wt Acc GF 128.44
100% 128.864 48.976 177.84 100.0% 2F 177.84
100% 128.864 48.976 177.84 100.0% 3F 177.84
100% 128.864 48.976 177.84 100.0% 4F 177.84
100% 40.00 128.86 128.864 48.976 177.84 100.0% 5F 177.84
100% 43.46 114.30 114.295 43.456 157.75 100.0% 6F 157.751
100% 43.46 114.30 114.295 43.456 157.75 100.0% 7F 157.751
100% 43.46 114.30 114.295 43.456 157.75 100.0% 8F 157.751
100% 48.98 128.86 128.864 48.976 177.84 100.0% 9F 177.84
100% 48.98 128.86 128.864 48.976 177.84 100.0% 10F 177.84
100% 48.98 128.86 128.864 48.976 177.84 100.0% 11F 177.84
45% 66.61 13.32 128.864 48.976 79.97 45.0% 12F 177.84
122.205 46.26 13F 168.465
115.546 43.543 14F 159.089
9.88 95.568 35.394 15F 130.962
128.44 115.546 43.543 16F 159.089
108.886 40.827 17F 149.713
128.864 48.976 18F 177.84
TOTAL AREA 2,969.57
BALANCE AREA 1,171.46
BALANCE
128.44 PRESENT MANPOWER FOR T&B: 5
0.00 ADD'L MANPOWER NEEDED: 3
0.00
0.00 12F 15F
0.00 Area 97.87 Area completed Area 130.96 Area completed
0.00 Man 8 Required MP Man 8 Required MP
0.00 Hour 27.83 at 10hr/day Hour 37.24 at 10hr/day
0.00 Parameter 2.28 mh/sqm Parameter 2.28 mh/sqm
0.00
0.00
0.00 13F 16F
97.87 Area 168.47 Area completed Area 159.09 Area completed
168.47 Man 8 Required MP Man 8 Required MP
159.09 Hour 47.91 at 10hr/day Hour 45.24 at 10hr/day
130.96 Parameter 2.28 mh/sqm Parameter 2.28 mh/sqm
159.09
149.71 14F 17F
177.84 Area 159.09 Area completed Area 149.71 Area completed
1,171.46 Man 8 Required MP Man 8 Required MP
m Hour 45.24 at 10hr/day Hour 42.57 at 10hr/day
Parameter 2.28 mh/sqm Parameter 2.28 mh/sqm
18F
Area completed Area 177.84 Area completed
Required MP Man 8 Required MP
at 10hr/day Hour 50.57 at 10hr/day
Parameter 2.28 mh/sqm

GF
Area completed Area 128.44 Area completed
Required MP Man 8 Required MP
at 10hr/day Hour 36.53 at 10hr/day
Parameter 2.28 mh/sqm

Area completed
Required MP
at 10hr/day
HALLWAY/LOBBY
TILING WORKS TOTAL AREA BALANCE
DONE % wt Acc GF 120.00 120.00 PRESENT MANPOWER FOR HALLWAY: 3
112.80 98.8% 2F 114.122 1.32 ADD'L MANPOWER NEEDED: 2
112.80 98.8% 3F 114.122 1.32
112.80 98.8% 4F 114.122 1.32 14F
112.80 98.8% 5F 114.122 1.32 Area 42.05 Area completed
112.80 98.8% 6F 114.122 1.32 Man 5 Required MP
112.80 98.8% 7F 114.122 1.32 Hour 14.89 at 10hr/day
112.80 98.8% 8F 114.122 1.32 Parameter 1.77 mh/sqm
112.80 98.8% 9F 114.122 1.32
112.80 98.8% 10F 114.122 1.32
112.80 98.8% 11F 114.122 1.32 15F
112.80 98.8% 12F 114.122 1.32 Area 114.12 Area completed
112.80 98.8% 13F 114.122 1.32 Man 5 Required MP
72.07 63.2% 14F 114.122 42.05 Hour 40.40 at 10hr/day
15F 114.122 114.12 Parameter 1.77 mh/sqm
16F 114.122 114.12
17F 114.122 114.12 16F
18F 114.122 114.12 Area 114.12 Area completed
TOTAL AREA 2,060.07 634.43 Man 5 Required MP
BALANCE AREA 634.43 m Hour 40.40 at 10hr/day
Parameter 1.77 mh/sqm
17F
Area 114.12 Area completed
Man 5 Required MP
Hour 40.40 at 10hr/day
Parameter 1.77 mh/sqm

18F
Area 114.12 Area completed
Man 5 Required MP
Hour 40.40 at 10hr/day
Parameter 1.77 mh/sqm

GF
Area 120.00 Area completed
Man 5 Required MP
Hour 42.48 at 10hr/day
Parameter 1.77 mh/sqm
BALCONY TILING WORKS TOTAL AREA BALANCE
DONE % wt Acc GF 0.00 0.00 PRESENT MANPOWER FOR BALCONY: 2
26.45 100.0% 2F 26.45 0.00 ADD'L MANPOWER NEEDED: 2
23.68 89.5% 3F 26.45 2.77
26.45 100.0% 4F 26.45 0.00 9F
24.33 92.0% 5F 26.45 2.12 Area 13.28 Area completed
19.43 87.5% 6F 22.2 2.78 Man 4 Required MP
19.43 87.5% 7F 22.2 2.78 Hour 9.42 at 10hr/day
19.29 86.9% 8F 22.2 2.91 Parameter 2.84 mh/sqm
13.17 49.8% 9F 26.45 13.28
5.94 22.4% 10F 26.45 20.51
0.00 0.0% 11F 26.45 26.45 10F
12F 26.45 26.45 Area 20.51 Area completed
13F 26.45 26.45 Man 4 Required MP
14F 24.325 24.33 Hour 14.55 at 10hr/day
15F 24.325 24.33 Parameter 2.84 mh/sqm
16F 24.325 24.33
17F 26.45 26.45 11F
18F 26.45 26.45 Area 26.45 Area completed
TOTAL AREA 430.53 252.38 Man 4 Required MP
BALANCE AREA 252.38 m Hour 18.76 at 10hr/day
Parameter 2.84 mh/sqm
12F 15F
Area 26.45 Area completed Area 24.33 Area completed
Man 4 Required MP Man 4 Required MP
Hour 18.76 at 10hr/day Hour 17.25 at 10hr/day
Parameter 2.84 mh/sqm Parameter 2.84 mh/sqm Parameter

13F 16F
Area 26.45 Area completed Area 24.33 Area completed
Man 4 Required MP Man 4 Required MP
Hour 18.76 at 10hr/day Hour 17.25 at 10hr/day
Parameter 2.84 mh/sqm Parameter 2.84 mh/sqm

14F 17F
Area 24.33 Area completed Area 26.45 Area completed
Man 4 Required MP Man 4 Required MP
Hour 17.25 at 10hr/day Hour 18.76 at 10hr/day
Parameter 2.84 mh/sqm Parameter 2.84 mh/sqm
18F
Area 26.45 Area completed
Man 4 Required MP
Hour 18.76 at 10hr/day
Parameter 2.84 mh/sqm
STAIR 1&2 TILING WORKS TOTAL AREA BALANCE
DONE ST2 % wt Acc GF - - PRESENT MANPOWER FOR T&B: 2
12.96 50.0% 2F 25.9256 12.96 ADD'L MANPOWER NEEDED: 1
12.96 50.0% 3F 25.9256 12.96
12.96 50.0% 4F 25.9256 12.96 13F
12.96 50.0% 5F 25.9256 12.96 Area 12.96 Area completed
12.96 50.0% 6F 25.9256 12.96 Man 3 Required MP
12.96 50.0% 7F 25.9256 12.96 Hour 16.00 at 10hr/day
12.96 50.0% 8F 25.9256 12.96 Parameter 3.70 mh/sqm
12.96 50.0% 9F 25.9256 12.96
12.96 50.0% 10F 25.9256 12.96 14F
12.96 50.0% 11F 25.9256 12.96 Area 12.96 Area completed
12.96 50.0% 12F 25.9256 12.96 Man 3 Required MP
13F 25.9256 25.93 Hour 16.00 at 10hr/day
14F 25.9256 25.93 Parameter 3.70 mh/sqm
15F 25.9256 25.93
16F 25.9256 25.93 15F
17F 25.9256 25.93 Area 12.96 Area completed
18F 25.9256 25.93 Man 3 Required MP
142.59 TOTAL AREA 440.74 298.14 Hour 16.00 at 10hr/day
BALANCE AREA 298.14 m Parameter 3.70 mh/sqm
ER FOR T&B: 2

16F
Area completed Area 12.96 Area completed
Required MP Man 3 Required MP
at 10hr/day Hour 16.00 at 10hr/day
Parameter 3.70 mh/sqm

17F
Area completed Area 12.96 Area completed
Required MP Man 3 Required MP
at 10hr/day Hour 16.00 at 10hr/day
Parameter 3.70 mh/sqm

18F
Area completed Area 12.96 Area completed
Required MP Man 3 Required MP
at 10hr/day Hour 16.00 at 10hr/day
Parameter 3.70 mh/sqm