Professional Documents
Culture Documents
Poy Razo Glu 2015
Poy Razo Glu 2015
AbstractIn this paper, a novel solution method is proposed for Magnitude of apparent power flow from
the optimal topology control problem in AC framework with N-1 Bus to Bus .
reliability. The resultant new topology of the proposed method Parameters
is guaranteed to yield a better objective function value than the
global solution of the problem with the original topology. In order Number of buses.
to prove our statement, semi-definite programming relaxation Number of branches.
is formulated to find a lower bound to the objective function
value of the problem. The proposed method is favorable for Number of generators.
parallelization to increase the computational efficiency, and the Admittance matrix, defined as
parallel computing flowchart is presented. Computational time of .
the algorithm for IEEE test cases is reported. An in-house power
market simulator is developed to simulate a market environment th element of .
complete with optimal topology control mechanism. Simulations Max apparent power flow capacity of the
held by participating human subjects are analyzed under the sub- transmission line connecting Bus to Bus
titles of the total operating cost, real power losses, and locational .
marginal price (LMP) variance. A simple example is illustrated
Half shunt capacitance of the transmission
to show that the resultant network topology may increase the real
power losses while still providing a lower operating system cost line connecting Bus to Bus .
than that of the original topology. Real power demand at Bus .
Index TermsAC optimal power flow, locational marginal Reactive power demand at Bus .
pricing, optimal topology control, semi-definite programming, Max and min voltage magnitude at Bus .
transmission switching.
Max and min real power capacity of the
generator at Bus .
NOMENCLATURE Max and min reactive power capacity of
the generator at Bus .
Operators
Positive semi-definite.
Indices
Transpose.
Bus indices.
Trace of a matrix.
Branch (transmission line) index with
terminal buses . Sets
Variables Set of all buses, has a cardinality of .
Real power supply from the generator at Set of all buses linked to a generator,
Bus . , has a cardinality of .
Reactive power supply from the generator Set of all transmission line indices, has a
at Bus . cardinality of .
Real part of voltage at Bus . Set of connected bus pairs, has a cardinality
Imaginary part of voltage at Bus . of . If th element in has terminal
Voltage magnitude at Bus , defined as buses , then th element of is
and th element of is
.
I. INTRODUCTION
Manuscript received March 08, 2014; revised June 27, 2014 and October 02,
R
2014; accepted November 24, 2014. This work was supported in part by US
ECENT studies have shown that reconfiguration of the
DoE (under the CERTS initiative). Paper no. TPWRS-00339-2014.
The authors are with the Department of Electrical Engineering, University at existing energy grid, without any physical technological
Buffalo, Buffalo, NY 14260 USA (e-mail: gokturkp@buffalo.edu; hso1@buf- improvement, arises the opportunity to provide a significant
falo.edu).
increase in the overall operational efficiency of the system.
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. One actively studied area is the optimization of transmis-
Digital Object Identifier 10.1109/TPWRS.2014.2379112 sion topologyoften termed, transmission switching. The
0885-8950 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
motivation lying beneath this idea is to reconfigure a power gramming with binary variables on both IEEE 118-bus and
transmission network by switching off transmission lines in RTS-96 system test cases. As of now, all the literature men-
order to result in a new topology, functioning at an econom- tioned in this paper employed a linearized DC OPF model,
ically efficient operational point in terms of total system cost. which does not guarantee a feasible AC dispatch. However,
New operation point still needs to meet all constraints in place Barrows [16]subsequently presented a method to correct DC
by the original system. The idea of purposefully switching model solutions to ensure a feasible but not necessarily op-
lines off is not new, as it has been utilized extensively within timal AC power flow solutions. He also verified that DC OPF
the power industry as a corrective mechanism in response to may underestimate savings from OTC. Additionally, Polturi
network contingencies [1], [2]. However, it had been a common [17]presented the AC OPF formulation for OTC, and took a
belief within industry that the reconfiguration of a transmission brute force approach to solve each problem individually. His
network would induce increased power loss during operation simulations indicate up to 9% savings is possible by topology
when the real power generations are fixed [3]. Contrary to control. Lastly, the AC OPF formulation was considered in
general belief, Bacher [4]proposed switching as a means to [18]by Khanabadi to utilize transmission switching as a con-
minimize system losses by temporarily opening a transmission gestion management tool with respect to voltage security and
line (temporarily taking the line out of operation). N-1 contingency analysis.
In order to realize the most benefit from transmission In order to provide a detailed modeling of the power system,
topology control, Fisher [5]merged optimal topology control we formulated OTC problem within AC framework with an
(OTC) with DC OPF (OPF including linear approximations). additional N-1 contingency criterion constraint. Moreover, we
Linearized DC approximations of the problem were formu- have extended our research by developing in-house electric
lated as a mixed integer linear programming (MIP) and 25% power market simulation software [19]. Our software allows
reduction on the operating system cost was observed for IEEE human subjects to act as market participants in power market
118-bus test case. Promising results were also reported using environment. We are interested in optimal topology control
a similar approach by Hedman in [6]. However, even with mechanism and its possible implementation to a market envi-
the computational benefits provided by DC OPF formulation, ronment. Our main intention is to simulate how people behave
the efficiency of transmission switching algorithms is still in the market with such technological advancement.
insufficient for practical use. Subsequently, several heuristics For the completeness of our study, we bound the objective
for transmission switching were proposed in the following function value of OTC problem by adopting the relaxation of
literature. OPF in the form of semi-definite programming (SDP). Low and
Barrows [7]analyzed the results of optimal transmission Lavaei provided a derivation of SDP relaxation from AC OPF
switching on an RTS-96 network in order to reduce computa- problem in [20]. They reported that SDP relaxation of OPF re-
tional complexity. Ruiz [8]proposed an algorithm to identify turns the global optimal solution for several IEEE test cases.
a promising candidate component for switching, and in some However, Lesieutre examined the limits of SDP in [21]and by
cases was able to achieve a computational time up to four providing an example, he showed that the zero duality gap is
orders of magnitude less than previous algorithms. Ruiz also not always the issue in power system. Lavaei, later, presented
proposed tractable transmission topology control policies to se- the necessary conditions of zero duality gap in radial networks
lect candidate lines and captured 96% potential cost savings in in [22]. In our study, SDP always yields a better or equally
[9]. Fuller [10], however, proposed another heuristic relying on acceptable solution as that of the original OPF. Therefore, in
a line-ranking parameter based on the optimal solution of DC this study, the objective function value of SDP relaxation will
OPF. Cong [11]developed a pre-screening method to identify a be considered only as a lower bound. Using SDP solution as
candidate list for switchable lines hoping to reduce the number a lower bound for AC OPF problem was also considered by
of integer variables in OTC problem. Moreover, transmission Raghunathan [23]while seeking the global optimal solution of
switching was also combined with planning problems in the OPF.
following literature. This research represents the first attempt in related literature
Villumsen [12]used transmission switching in capacity ex- using SDP relaxation as a lower bound in an OTC problem. By
pansion planning by merging a decomposition technique with a providing a lower bound, we are able to select a limited number
stochastic integer-programming problem. Khodaei [13]decom- of candidate lines to be switched off. Moreover, we proved that
posed the capacity expansion planning problem into a master the resulting topology will lead a globally better solution than
and two sub-problems while considering transmission topology the original topology.
as a variable. IEEE 73- and 118-bus test cases were used in the Secondly, to the authors' best knowledge, enabling human
research and their performances indicated that a total cost re- subjects to directly interact within a simulated power market en-
duction between 0.04% and 0.07% was achieved from the sim- vironment complete with optimal topology control mechanism
ulations. that satisfies N-1 contingency criterion is also another first at-
Additionally, N-1 reliability imposed by FERC [14]was tempt in related literature.
studied with optimal topology control under pre-contingency
and post contingency situations. A detailed definition of N-1 II. MOTIVATION
contingency criterion is given in Section V. Hedman [15]ana- A simple 3-bus system example is illustrated in Fig. 1(a).
lyzed N-1 reliable optimal DC OPF solutions with transmission The transmission line connecting Bus 1 and Bus 3 has a max-
switching, where the problem was formulated as linear pro- imum flow limit of 100 MVA and the other lines are infinite
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
POYRAZOGLU AND OH: OPTIMAL TOPOLOGY CONTROL WITH PHYSICAL POWER FLOW CONSTRAINTS 3
(1)
Fig. 1. (a) 3-bus original network. (b) 3-bus network after switching operation.
The interior-point method solver within MATPOWER [25]is
employed to solve (1). If there exists a feasible solution, the
resulting local optimal solution is guaranteed to be a feasible
in capacity. Suppose generators are located at Bus 1 and Bus solution; however, it should be noted that the global optimal so-
2 and their generation costs are $10/MWh and $20/MWh, re- lution (which is not solved for in MATPOWER) may be dif-
spectively. Furthermore, there are 200 MW, 100 MVar real and ferent than the local optimal. In this study, we're interested to
reactive power demands at Bus 3. Lastly, all three lines are iden- provide an upper and a lower bound for the problem (1) not to
tical and their resistance and reactance are 0.007 and 0.04 find the exact global solution but to find a range for it. Hence,
, respectively. If we solve AC OPF while all 3-transmis- MATPOWER solution will be treated as an upper bound for (1)
sion lines are available, the solution of the problem will be real and relaxed AC OPF problem in the form of SDP is adopted
power generation of 74.7 MW at Generator 1 and 127.1 MW at to provide a lower bound for (1). This approach limits the ex-
Generator 2 with the objective function value of $3289.08. Max- istence of the global solution between upper and lower bound
imum power flow limit on the line connecting Bus 1 and Bus 3 (refer to Section VI for details).
prevents a cheaper generator (Gen1) serving all the loads. How- Reliability and resiliency of the power system are the two
ever, if transmission switching takes place, the decision will be main goals in today's power industry. Such reliability is ex-
made on switching the congested line off. This decision allows pected to be maintained even in a single component failure con-
all demand to be met by the cheapest generator as illustrated dition. In power system operation, typically, all available trans-
in Fig. 1(b). The solution of OPF problem will be real power mission components are utilized. Within industry, component
generation of 206.55 MW at Generator 1 and 0 MW at Gener- failure scenarios are typically referred to contingencies. Con-
ator 2 with the objective function value of $2065.47. An impor- sider a transmission network with N transmission lines. If such
tant analysis can then be made on LMP. LMPs at Buses 1, 2, a system is able to withstand (continue to operate) after the loss
and 3 in the former case with a congested line are $10/MWh, of a single transmission line, the system would be said to have
$20/MWh, and $31.15/MWh, respectively. The main reason of met the N-1 contingency criterion. More specifically, N-1 con-
LMP variance in this system is defined in [24]as the congestion tingency criterion is a common term used to predict a system's
on a transmission line systematically splits LMP at each end operational status after single component within the system fails
of the line. However, LMPs at Buses 1, 2, and 3 in the latter to operate [14].
case after switching operation are $10/MWh, $10.29/MW, and N-1 contingency criterion when applied to AC OPF refers
$10.62/MWh, respectively. This small LMP difference in the to the ability of rescheduling generators immediately after the
latter case is caused by the power loss associated with the line single contingency occurs with no violation of physical con-
resistance. straints, so that the system can move from one stable operation
state to another. In general, a single contingency would be con-
III. AC OPTIMAL POWER FLOW WITH sidered as the loss of a transmission line or a generator; how-
N-1 CONTINGENCY CRITERION ever, the problem of interest in this study is to see the effect of
The objective function of an AC OPF problem is to mini- topology control on reliability. Therefore, hereinafter only the
mize the operating cost of the system, subject to real and reac- loss of transmission line will be considered as a contingency. In
tive power balance equalities, and some inequalities including this sense, each contingency changes the topology of the system.
real and reactive power generation, apparent power flow, and Complete problem formulation of AC OPF with N-1 reliability
voltage reliability limits. AC OPF problem generally be mod- is called super
eled in the form of (1), where the control variable consists
of by1 vectors of real part of voltage and imaginary
part of voltage and the by1 vectors of real and
reactive power injections, then is the set of non-
linear equations represent the real and reactive power balance,
and is the set of equations represent the power flow limits
as nonlinear functions and the variable limits. Lastly, and are
given vectors as parameters.
Mathematical programming in the form of (1) is a nonlinear
programming with a non-convex feasible region; hence the so- ..
lution methods of the problem are beyond the scope of this .
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
POYRAZOGLU AND OH: OPTIMAL TOPOLOGY CONTROL WITH PHYSICAL POWER FLOW CONSTRAINTS 5
TABLE I
COMPUTATIONAL TIME FOR PARALLEL ALGORITHM
(3e)
(3f)
(3g)
(3h)
POYRAZOGLU AND OH: OPTIMAL TOPOLOGY CONTROL WITH PHYSICAL POWER FLOW CONSTRAINTS 7
A. Simulation Tool
An electric power market simulator can be used as an excel-
lent teaching tool to give students the opportunity to learn the
fundamentals of power economics while participating in several
market simulation experiments. Developed simulators in other
studies may be found in [29][33]. Here, we are interested in op-
timal topology control mechanism and its possible implemen- Fig. 5. Operating costs for 25 trading periods.
tation to a market environment. Our main intention is to sim-
ulate how people behave in the market with the technological
advancement. An electric power market simulation software,
complete with an OTC mechanism was developed and human
subjects, students of graduate and undergraduate level, took the
role of a person responsible of trading in a generator company.
Interested readers are referred to [34]for more detail; however,
for the completeness of this study, we will describe the simula-
tion tool briefly.
Participated students are informed in advance that the sim-
ulated power market is advanced with optimal topology con-
trol mechanism. In order to provide a realistic market environ-
ment to be competitive and confidential, participants can only
see their own dispatch amount and economic data. Human sub-
Fig. 6. Real power losses for 25 trading periods of an experiment.
jects should decide their offers for a trading period based on a
forecasted load and their own cost data. Their main objective is
to achieve high profit in each trading period. costly than the original network but also satisfies the N-1 con-
The following discussions on the total operating cost of tingency constraint. Proposed OTC algorithm found a topology
the system, real power losses, and locational marginal prices that leads 5% cost reduction within 22nd trading period, and
(LMPs) are based on an experiment held by human subjects for 10% within the 16th trading period.
25 trading periods.
C. Real Power Losses
B. Total Operating Cost
Fig. 6 shows the real power losses in MW with respect to
The objective of an OTC problem is to minimize the total 25 trading periods. In general, proposed OTC algorithm returns
operating cost of the system by considering the transmission a solution with lower power losses than the original topology
network as a variable in optimization problem. Although this solution. However, one interesting instance deserving careful
approach may decrease the operating cost of the system by attention is the 5th trading period in Fig. 6. During this period
switching operation, the resulted topology may not satisfy the the operating cost of the system after OTC with N-1 contingency
same N-1 contingency criterion as the original topology. is less than the cost of the original topology, yet higher power
Real and reactive power load parameters and cost functions of loss was observed as opposed to our expectation. Hence, our
generators are different in each trading period given in Fig. 5 and observation is that even though the operating cost of the system
they may be found online via [19]. For each trading period, the is reduced after transmission switching operation, real power
total operating cost of the system is given in Fig. 5. In order losses do not necessarily decrease.
to better illustrate our N-1 contingency criterion, we also in-
cluded the case when not considering N-1 contingency condi- D. Locational Marginal Price Variance
tion in Fig. 5 labeled as w/o N-1. Due to the similarity of The price of electricity at a particular bus is determined by
the solutions gathered with and without N-1 contingency crite- what is known as the LMP. LMP is well defined for ACOPF
rion, we believe it to be unnecessary to plot the results of no N-1 problem modeled in the form of (1). It is defined by the dual vari-
contingency condition throughout the remainder of the paper. able pertaining to the real power balance constraint. However,
The 5th trading period, as magnified in Fig. 5, illustrates how OTC problem is indeed a mixed integer nonlinear programming
the results differ with and without N-1 contingency condition. (MINLP) so that the dual variables are not well defined. Here,
Although there exists a topology with a better solution, due to we would like to note that, our intention in this section is not to
no satisfaction of N-1 contingency constraint, our proposed al- compare the dual variables of two problems. Instead, we simply
gorithm finds another topology that is still guaranteed to be less want to compare well-defined LMP in two different topologies.
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
REFERENCES
[1] H. Glavitsch, State of the art review switching as means of control in
the power system, Int. J. Elect. Power Energy Syst., vol. 7, no. 2, pp.
92100, Apr. 1985.
Fig. 8. Locational marginal price at Bus 6 for 25 trading periods. [2] J. G. Rolim and L. J. B. Machado, A study of the use of corrective
switching in transmission systems, IEEE Trans. Power Syst., vol. 14,
no. 1, pp. 336341, Feb. 1999.
[3] K. Hedman, Flexible transmission in the smart grid, Ph.D. disserta-
Fig. 7 shows the LMP at Bus 20 in IEEE 30-bus system for 25 tion, Univ. California, Berkeley, CA, USA, 2010.
trading periods. LMP within the 16th trading period under the [4] R. Bacher and H. Glavitsch, Loss reduction by network switching,
original network is $555.93/MWh. After the application of the IEEE Trans. Power Syst., vol. 3, no. 2, pp. 447454, May 1988.
[5] E. B. Fisher, R. P. O'Neill, and M. C. Ferris, Optimal transmission
proposed algorithm, the LMP at Bus 20 becomes $64.38/MWh. switching, IEEE Trans. Power Syst., vol. 23, no. 3, pp. 13461355,
This bus is chosen on purpose to highlight the maximum change Aug. 2008.
of LMP observed within our experiments at 88.42%. [6] K. Hedman, R. P. O'Neill, E. B. Fisher, and S. S. Oren, Co-opti-
mization of generation unit commitment and transmission switching
Change on LMP to an opposite direction was also observed with N-1 reliability, IEEE Trans. Power Syst., vol. 25, no. 2, pp.
after transmission switching operation. Fig. 8 shows LMP at 10521063, May 2010.
Bus 6 in IEEE 30-bus system and it is higher after the decision [7] C. Barrows and S. Blumsack, Transmission switching in the RTS-96
test system, IEEE Trans. Power Syst., vol. 27, no. 2, pp. 11341135,
of switching made in several trading periods when compared to May 2011.
the LMP with the original network. [8] P. A. Ruiz, J. M. Foster, A. Rudkevich, and M. C. Caramanis, On fast
Analysis of our experimental results on LMP variance transmission topology control heuristics, in Proc. 2011 IEEE Power
and Energy Soc. General Meeting, San Diego, CA, USA, Jul. 2011.
showed that optimal topology control could not guarantee an [9] P. A. Ruiz, J. M. Foster, A. Rudkevich, and M. C. Caramanis,
increase or a decrease on LMP at any bus. Tractable transmission topology control using sensitivity analysis,
IEEE Trans. Power Syst., vol. 27, no. 3, pp. 15501559, Aug. 2012.
[10] J. D. Fuller, R. Ramasra, and A. Cha, Fast heuristics for transmis-
VII. CONCLUSION sion-line switching, IEEE Trans. Power Syst., vol. 27, no. 3, pp.
Our studies on optimal topology control problem with phys- 13771386, Aug. 2012.
[11] L. Cong, W. Jianhui, and J. Ostrowski, Heuristic prescreening switch-
ical power flow constraints and N-1 reliability have exposed in- able branches in optimal transmission switching, IEEE Trans. Power
teresting results. Such a method has proved to be theoretically, Syst., vol. 27, no. 4, pp. 22892290, Nov. 2012.
quite beneficial by resulting in increased operational efficiency [12] J. C. Villumsen and A. B. Philpott, Investment in electricity networks
with transmission switching, Eur. J. Oper. Res., vol. 222, no. 2, pp.
of the electric power grid. Taking control of the transmission 377385, Oct. 2012.
topology is a promising option to reduce the total operating cost [13] A. Khodaei, M. Shahidehpour, and S. Kamalinia, Transmission
of the system. The potential usefulness of such a methodology switching in expansion planning, IEEE Trans. Power Syst., vol. 25,
no. 3, pp. 17221733, Aug. 2010.
motivated us to develop an electric power market simulation [14] U. S. Federal Energy Regulatory Commission, Mandatory Reliability
software package that allows human subjects to take on the role Standards for the Bulk-Power System, Order no. 693, 72 FR 16416,
of a utility generation facility and to participate in experiments Apr. 4, 2007.
[15] K. Hedman, R. O'Neill, E. Fisher, and S. Oren, Optimal transmission
with a power market simulator. The underlying structure of the switching with contingency analysis, in Proc. 2010 IEEE Power and
market is an economic dispatch model completed with a single Energy Soc. General Meeting, Minneapolis, MN, USA, July 2010.
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
POYRAZOGLU AND OH: OPTIMAL TOPOLOGY CONTROL WITH PHYSICAL POWER FLOW CONSTRAINTS 9
[16] C. Barrows, S. Blumsack, and P. Hines, Correcting optimal transmis- [30] R. Ethier, R. D. Zimmerman, T. Mount, W. Schulze, and R. J. Thomas,
sion switching for AC power flows, in Proc. 2014 47th Hawaii Int. Auction design for competitive electricity markets, in Proc. Hawaii
Conf. System Sciences, Waikoloa, HI, USA, 2014, pp. 23742379. Int. Conf. System Sciences, Maui, HI, USA, Jan. 710, 1997.
[17] T. Polturi and K. W. Hedman, Impacts of topology control on the [31] J. Bernard, R. Ethier, T. Mount, W. Schulze, R. D. Zimmerman, D.
AC OPF, in Proc. IEEE PES General Meeting, San Diego, CA, USA, Gan, C. Murillo-Snchez, R. J. Thomas, and R. Schuler, Markets for
2012. electric power: Experimental results for alternative auction institu-
[18] M. Khanabadi, H. Ghasemi, and M. Doostizadeh, Optimal transmis- tions, in Proc. Hawaii Int. Conf. System Sciences, Kona, HI, USA,
sion switching considering voltage security and N-1 contingency anal- Jan. 69, 1998.
ysis, IEEE Trans. Power Syst., vol. 28, no. 1, pp. 542550, Feb. 2012. [32] J. Bushnell and S. Borenstein, Energy economics and policy: Courses
[19] BEST Group at University at Buffalo Electrical Engineering Depart- and training, in Proc. PSERC Future Grid InitiativeAnnu. Meeting,
ment Website [Online]. Available: http://www.eng.buffalo.edu/Re- May 2013.
search/BEST [33] Q. C. Trinh, M. Saguan, and L. Meeus, Experience with electricity
[20] J. Lavaei and S. H. Low, Zero duality gap in optimal power flow market test suite: Students versus computational agents, IEEE Trans.
problem, IEEE Trans. Power Syst., vol. 27, no. 1, pp. 92107, Feb. Power Syst., vol. 28, no. 1, pp. 112120, Feb. 2012.
2011. [34] G. Poyrazoglu and H. Oh, Electric power market experiments with
[21] B. C. Lesieutre, D. K. Molzahn, A. R. Borden, and C. L. DeMarco, Ex- optimal topology control, in Proc. 2015 48th Hawaii Int. Conf. System
amining the limits of the application of semidefinite programming to Sciences, Kauai, HI, USA, Jan. 58, 2015.
power flow problems, in Proc. 2011 49th Annu. Allerton Conf. Com-
munication, Control, and Computing, 2011, pp. 14921499.
[22] J. Lavaei, D. Tse, and B. Zhang, Geometry of power flows on trees, Gokturk Poyrazoglu (S14) received the M.S. de-
in Proc. 2012 IEEE PES General Meeting, San Diego, CA, USA, Jul. gree in electrical engineering (energy systems) from
2012. the State University of New York at Buffalo (UB),
[23] A. Gopalakrishnan, A. U. Raghunathan, D. Nikovski, and L. T. Biegler, Buffalo, NY, USA, in 2013. He is currently pursuing
Global optimization of optimal power flow using a branch & bound the Ph.D. degree at UB.
algorithm, in Proc. 2012 50th Annu. Allerton Conf. Communication, His interests include network reconfiguration
Control, and Computing, 2012, pp. 609616. algorithms and large scale optimization in applica-
[24] H. Oh, Aggregation of buses for a network reduction, IEEE Trans. tions to power systems. Currently, he is working on
Power Syst., vol. 27, no. 2, pp. 705712, May 2012. developing an efficient semi-definite programming
[25] R. D. Zimmerman, C. E. Murillo-Snchez, and R. J. Thomas, MAT- solver for power systems problems. Before graduate
POWER's extensible optimal power flow architecture, in Proc. 2009 school, he worked in St. Petersburg, Russia and
IEEE Power and Energy Soc. General Meeting, Jul. 2630, 2009, pp. Istanbul, Turkey as a design engineer on power distribution system for 3 years.
17.
[26] X. Bai, H. Wei, K. Fujisawa, and Y. Wang, Semidefinite programming
for optimal power flow problems, Int. J. Elect. Power Energy Syst.,
vol. 30, no. 67, pp. 383392, 2008, Elsevier.
[27] D. K. Molzahn, J. T. Holzer, B. C. Lesieutre, and C. L. DeMarco, HyungSeon Oh (M07) received the Ph.D. degree
Implementation of a large-scale optimal power flow solver based on in electrical and computer engineering from Cornell
semidefinite programming, IEEE Trans. Power Syst., vol. 28, no. 4, University, Ithaca, NY, USA, in 2005.
pp. 39873998, Nov. 2013. He is an Assistant Professor at the State University
[28] J. Lfberg, YALMIP: A toolbox for modeling and optimization in of New York at Buffalo, Buffalo, NY, USA. Before
MATLAB, in Proc. CACSD Conf., Taipei, Taiwan, 2004. the appointment, he was a staff engineer at the Na-
[29] R. D. Zimmerman, R. J. Thomas, D. Gan, and C. Murillo-Snchez, An tional Renewable Energy Laboratory. His research
internet-based platform for testing generation scheduling auctions, in interests include: energy systems economics, power
Proc. Hawaii Int. Conf. System Sciences, Kona, HI, USA, Jan. 69, system planning, smart grid, storage, computer sim-
1998. ulation, and nonlinear dynamics.