Professional Documents
Culture Documents
Ceig Rules
Ceig Rules
1) The Scrutiny reports pertains to the drawing covering the items of Electrical
Installation intended for the present proposal only.
2) The scrutiny reports takes into account of the present trends and practicas
followed in conformity with the statutory Provisions of Indian Electricity
Rules 1956 Bureau Of Indian Standerds in force on the date of scrutiny report.
In the event of any amendment/Modification/Insertion of new rules,they
should be completed with not with standing the scrutiny report issued.Revised
drawings as per the modified rules/new rules inserted should be submitted
suo-motto by the consumer and freshscrutiny report should be obtained
suspersiding the previous one.
8) Clearances stipulated under R51(1) of IER 1956 should be provided for the
switch board,for enebling convenient and safe working to the operating
personnal.
10) When independent (stand by) source of supply using generators set etc., is
proposed positive arrengement should be made to prsent paralling of such
such source of supply either amoung them or with the suppliers source of
supply under and circumstances.
12) ELCB should be provided at the source and itself for the circuits feeding
socket outlets intended for the utilization of portable/hand hold equipements.
13) Suitable starting current limiting devices should be provided for the
Equipments when their starting current is likely to affect the other circuits by
causing excesive voltage drop.
14) Fault level at various locations should be arrived at and the adequacy at fault
Clearing devices at the respective location should always be ensured.
15) The relays and fault clearing device should be co-ordinator for affording
Discriminative protection to the circuits right from the HV panel upto the
MV panel different circuits and loads.
17) The installation works should be carried ouit in accordance with Indian
Electricity rule Indian standard specifications and as per the general and
Specific condition & remarks stipulated in the scrutiny report.
19) The service of mobile laboratory available in this deprtment may be utilised
for the purpose of high voltage equipments and precommissioning tests.
20) Any other canditions that may be imposed on an inspction at a late date.
21) The size of cable proposed for raising main UPS input panel to 60KVA UPS.
UPS output panel etc.,should be adequate for working level.
22) On the primary and secondary side of each upo either B/F of MCCB sholud
be provided for protection.
23) In the tap off box feeding form raising main each circuits,suitable for should
be provided.
24) All the wiring above the false ceiling should be enclosed in metal conduit
pipe.
26) The clearancess for SSB shold be maintained as per Rule 51(1) (c) of IER
1956.
28) The 11/2 pvc pipe lines from the oil collectoin pits of 1600KVA
Transformer to the oil soak pit should be replaced with 150mm dia hume
pipe lines.
29) HT Indoor area: Necessary ceiling level ventilators and windows should be
provided at the above room for adequate ventilation.
30) At the main MV panels the incomming & outgoing feeders are
identified.The name of the feeders the runes and size of the cable etc.,should
be marked permantly on the front side.
31) Generator synchronising panel: The passage to a width at not less than
750mm clear to a height at not less than 1.8 meters should be provided on
the both side of the above panel.
4
32) MV DG set panel the hinged doors should be replaced by bolted doors to
maintain adequate rear side clearance.
33) The relays Including O/C , E/F & differential relays should be installed of
the synchronizing panels connected to the Tripping circuits.
34) The opening around the vertical raising mains at the floor crossings should
be sealed with non-inflammable materials.
35) Adequate size of cable should be provided between RMG unit and HT VCB.
37) The circuit for common area lighting should also be directly taken from main
switch gear panel.
38) Oil soak pit of requisite capacity should be provided for the 2 nos 1600KVA
transformer it the aggregate oil capacity exceeds 2000 Liters.
39) The wall separatly the transformer should be either 355mm thick brick wall
or 230mm thick RCC.
40) The approach distance between the tranformer & their secondary control
should be restricted to 15 meters by providing a door opening in HT panel
room.
42) Number of lighting conductor down conductor for the lighting protection of
the building should be carried out as per IS 2039.
43) Fire alarm,smoke detctors sholud be provided all the locations and
emergency lights shuold be provided in common areas power room etc.,
45) DC series motor is starting Torque high.so starting current may be 300
Amps.
46) If the voltage exceeds 250v, all the DB and main switches should be
proveded with danger board.
47) Total load in the circuit should not exceed more than 800watts and number
of points should not more than 10 points.
49) For lighting load the fuse wire should not exceed 5Amps capacity and power
it is 10Amps.
50) The minimun size of the conductor in sub circuits should not be less
than1/1.12mm(0.96mm2) in case of copper wores 1/1/40mm(1.5mm2) in
case if Aluminum wires.
51) All the boards should be connected fixed at a height of 1.5 meters.
52) The height of all the incandescent lamps shall be 2.5 meters from the floor
level and that of ceiling fan shall 2.75 meters.
53) In industrial fittings where high wattage lamps are emplyyed.The height may
be 6-7 meters.
56) The overhead lines should be minmum 6 meter between overhead line and
ground IER-77
58) The overhead line building cross must be 2.349 meter clearance from
Building height. IER-79
61) The load on a particular circuit shall not exced 800watts or 10 poits in case
of lighting and 2 points or 2000w in case of power of 15A sokets.
63) Mechanical interlock shall be provided for the switches in the MV panel
such a manner that only one switch can switehed on of a time.
64) Mechanical interlock shall be provided for the Generator be incomming and
bus coupler in such a manner that two feeders can be switched on at a time.
65) All MV equipments shall be earthed with suitable size of copper flat/wire as
per earthing table.
66) Clearance between earth electrode and the wall shall be maintened as not
less than 1425mm and between the two earth electrodes shall be maintained
as not less than 3050mm.
67) All electrical equipments shall be provied with a starter where ever necessary
and a isolator as near as possible.
69) Suitable rating of HRU fuse shall be provided in all SSBs outgoing as per
backup HRC fuse table.
70) Working load on any feeder shall be limited to the current carring capacity of
the cable and that of the control switch gear.
71) Switch borards and distribution boards shall be erected with a front clearance
of 1000mm
7
72) Model diagram of all control panels and motor control center (MCC) wiring
diagram shall be submitted to CEIG office as soon as we receive the same
from the supplier of machinary.
76) Do not allow visitors and unautorised persons to touch or handle elecrical
apparatus or come with in the danger zone HV appratus.
a) Site plan
b) Electrical sub station layout
c) SLD
d) Rasing main
e) Electrical layout flor plan