Professional Documents
Culture Documents
FINAL - TCH Bruhn - Sept. 20 Presentation To DoS - 20170920
FINAL - TCH Bruhn - Sept. 20 Presentation To DoS - 20170920
FINAL - TCH Bruhn - Sept. 20 Presentation To DoS - 20170920
2
Project Development Life Cycle
Conceptual Preliminary Functional Detailed Tender &
Pre-Project Work
Planning Design Design Design Construction
CURRENT PHASE
Data Collection Conceptual Undertake Preliminary Ground Survey Early Works
Needs Development of Design of Design of Tender Drawings Construction
Assessment Multiple Options Shortlisted Shortlisted Activities
Options Option Construction
Problem Multiple Accounts Documents Major Works
Definition Evaluation to Value Analysis Archeological Construction
Shortlist Options Assessment Value Engineering Activities
Road Safety
Risk Assessment Environmental First Nations Archaeological,
Federal Accommodation
Business Case Partnerships Assessments Cultural, and
Geotechnical Property Spiritual
First Nations Cultural Acquisition Monitoring
Consultation Assessment Assessments
First Nations Environmental
Project Liaison First Nations Permitting
Committee Consultation Consultation
Meetings Project Liaison Public Open
Project Liaison House
Community Committee Committee
Engagement Meetings Meetings
Public Open Community Community
House Engagement Engagement
Public Open Public Open
House House
3
Agenda
1. Objectives
2. Status Update
3. Field Work
4. Next Steps
4
Project Objectives
Improve safety and traffic flow along the TCH corridor
Replace the aging R.W. Bruhn Bridge
Improve safety of local road connections at the TCH
Enhance safety for pedestrians along the TCH corridor
5
Status Update
Planning phase resulted in three improvement options presented
at public open house in November 2016
314 online and hard-copy feedback forms collected between November 15, 2016
and January 16, 2017.
5-Lane Bridge had highest level of agreement (65%), following by the 6-Lane
Bridge (35%), and 4-Lane Bridge with Main Street Bridge (32%).
7
5-Lane Bridge Option
8
4-Lane Bridge Option
9
Field Work
10
Next Steps
Conceptual Preliminary Functional Detailed Tender &
Pre-Project Work
Planning Design Design Design Construction
CURRENT PHASE
Data Collection Conceptual Undertake Preliminary Ground Survey Early Works
Needs Development of Design of Design of Tender Drawings Construction
Assessment Multiple Options Shortlisted Shortlisted Activities
Options Option Construction
Problem Multiple Accounts Documents Major Works
Definition Evaluation to Value Analysis Archeological Construction
Shortlist Options Assessment Value Engineering Activities
Road Safety
Risk Assessment Environmental First Nations Archaeological,
Federal Accommodation
Business Case Partnerships Assessments Cultural, and
Geotechnical Property Spiritual
First Nations Cultural Acquisition Monitoring
Consultation Assessment Assessments
First Nations Environmental
Project Liaison First Nations Permitting
Committee Consultation Consultation
Meetings Project Liaison Public Open
Project Liaison House
Community Committee Committee
Engagement Meetings Meetings
Public Open Community Community
House Engagement Engagement
Public Open Public Open
House House
11
Key Contacts
Jennifer Stites, Project Manager
Telephone: (778) 257-7178
Email: jennifer@stitesco.ca
12