HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/HDL
From :I Gede Andi Dipayadnya
Date / Time :16 May 2012
To : Agus D.L
CC : Mr. Sentot H./ Mr. Sri Widadi

I. HSE Matters

ALWAYS REMINDER ALL OF THE CREW ABOUT ZERO TOLERANCE CAMPIGN

II. Work In progress and Today Activities


Item. 12146C
Replacement several corroded section of fire water line at Gas Compressor
area
Status:
- Sheet 2 of 7, completed.
- Sheet 4 of 7, completed.
- Sheet 5 of 7, completed.
- Sheet 6 of 7, completed.
- Sheet 7 of 7, completed.
Remaining:
- Sheet 1 of 7 :
a. Scaffolding job
b. Fire water line around V-8190, already replaced.
c. Replace remaining corroded fire water line, as per drawing.
- Sheet 3 of 7:
a. Scaffolding job
b. Replace corroded section FW line

III. Main Events on the Period.

Item. 12276C
Replace corroded FW line and 4 #150 gate valve at Train 1
Status:
Completed
Item. 12425/C
Removing 8 #600 blind flange and 8 #600 ball valve at API area
Status:
Completed

Item. 12340H
Assist CPA/INS for internal inspection and internal repair at V-46320, HR
cluster
Status:
Completed
IV. High Priority Job to be done in forthcoming days
Item. 12117/H
Re-installation of F-7700 at HV cluster
Item. 12298/H
Install scaffolding to assist PIM on 12 LP line HV to CPA
Item. 12308/H
Install scaffolding to assist PIM on 10 LP line HGA to CPA
Item. 11874/C
Repair 4 piping to T-5090, CERMAT #302502
V. Pending Job and to be solved

NIL

VI. Miscellaneous Items

- Contractors team under PT. Meindo, Foreman: Afrizal


- MOP . will be valid until .

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( Agus DL )