PROJECT PLTM TANGKA

ID Task Name Duration Start Finish Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 Bangunan Bendungan
2 Pintu dan Accecories Weir 26 days Mon 10/30/17 Mon 12/4/17
3 Preparation 3 days Mon 10/30/17 Wed 11/1/17
4 Fabrication 14 days Mon 10/30/17 Thu 11/16/17
5 Finishing 10 days Tue 11/21/17 Mon 12/4/17
6 Pintu dan Accecories Intake 27 days Tue 12/5/17 Wed 1/10/18
7 Preparation 3 days Tue 12/5/17 Thu 12/7/17
8 Fabrication 14 days Fri 12/8/17 Wed 12/27/17
9 Finishing 10 days Thu 12/28/17 Wed 1/10/18
10 Bangunan Sandtrap
11 Pintu dan Accecories Sandtrap 27 days Thu 1/11/18 Fri 2/16/18
12 Preparation 3 days Thu 1/11/18 Mon 1/15/18
13 Fabrication 14 days Tue 1/16/18 Fri 2/2/18
14 Finishing 10 days Mon 2/5/18 Fri 2/16/18
15 Bangunan Headpond
16 Pintu dan Accecories Headpond 65 days Mon 2/19/18 Fri 5/18/18
17 Preparation 3 days Mon 2/19/18 Wed 2/21/18
18 Fabrication 14 days Thu 2/22/18 Tue 3/13/18
19 Finishing 10 days Wed 3/14/18 Tue 3/27/18
20 Trasrack lengkap 38 days Wed 3/28/18 Fri 5/18/18
21 Preparation 3 days Wed 3/28/18 Fri 3/30/18
22 Fabrication 21 days Mon 4/2/18 Mon 4/30/18
23 Finishing 14 days Tue 5/1/18 Fri 5/18/18
24 Pondasi Penstock
25 Pipa Penstock 190 days Mon 9/18/17 Fri 6/8/18
26 Procurement 30 days Mon 9/18/17 Fri 10/27/17
27 Preparation 14 days Mon 9/18/17 Thu 10/5/17
28 Fabrication 100 days Mon 10/30/17 Fri 3/16/18
29 Erection 120 days Mon 11/13/17 Fri 4/27/18
30 NDT Test 120 days Mon 12/4/17 Fri 5/18/18
31 Finishing 120 days Mon 12/25/17 Fri 6/8/18
32 Pipa Pesat Percabangan (Bifurcation) 58 days Fri 3/16/18 Tue 6/5/18

33 Preparation 3 days Fri 3/16/18 Tue 3/20/18


34 Fabrication 30 days Wed 3/21/18 Tue 5/1/18
35 Erection 14 days Sun 4/29/18 Wed 5/16/18
36 NDT Test 12 days Sun 5/6/18 Mon 5/21/18
37 Finishing 10 days Wed 5/23/18 Tue 6/5/18
38 Power House
39 Pintu dan Accecories Tailrace 27 days Mon 5/21/18 Tue 6/26/18
40 Preparation 3 days Mon 5/21/18 Wed 5/23/18
41 Fabrication 14 days Thu 5/24/18 Tue 6/12/18
42 Finishing 10 days Wed 6/13/18 Tue 6/26/18
43 Gambar Bestek
44 Indirect Cost 0 days Sat 8/26/17 Sat 8/26/17 8/26
45 Shop Drawing & Document Cost
46 Transportation
47 Insurance

Task Project Summary Manual Task Start-only Deadline

Project: PLTM TANGKA SCHEDU Split Inactive Task Duration-only Finish-only Progress
Date: Sat 8/26/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone