Annex I of

TPB Paper No. 10304

K-n2017~7
EXTRACT PLAN PREPARED ON 11.7.2017 REFERENCE No.
R/S/K18/20
Annex II of
TPB Paper No. 10304

SCHEDULE OF AMENDMENTS TO THE


APPROVED KOWLOON TONG OUTLINE ZONING PLAN NO. S/K18/19
MADE BY THE TOWN PLANNING BOARD
UNDER THE TOWN PLANNING ORDINANCE (Chapter 131)

I. Amendments to the Matters shown on the Plan

Item A Rezoning of a piece of land near the junction of Lung Cheung Road and Lion
Rock Tunnel Road from Green Belt (GB) to Residential (Group C)11
(R(C)11).

Item B1 Rezoning of a strip of land abutting the northern kerb of Lung Cheung Road
from GB to an area shown as Road.

Item B2 Rezoning of a strip of land abutting the southern kerb of Lung Cheung Road
from GB to an area shown as Road.

II. Amendments to the Notes of the Plan

(a) Revision to the Remarks of the Notes for the R(C) zone to incorporate plot ratio
and building height restrictions for the R(C)11 sub-zone.

(b) Revision to the Remarks of the Notes for the R(C) zone to incorporate R(C)11
sub-zone under the clause for minor relaxation of building height restriction.

Town Planning Board

13 January 2017
Annex III of
TPB Paper No. 10304

List of Representers and Commenter


in respect of Draft Kowloon Tong Outline Zoning Plan No. S/K18/20

Representer Name of Representer


(No. TPB/R/S/K18/20-)
1 Green Sense
2
3
4
5 Mary Mulvihill
6 Winnie Ching
7 (No Name Provided)

Commenter Name of Commenter


(No. TPB/R/S/K18/20-)
C1 Mary Mulvihill
Annex VI of
TPB Paper No. 10304

Summary of Representations and Comment and Government Departments Responses

(1) The grounds of representations and proposals of R1 to R7 and responses are summarized below:
Representations Responses
A. Green Belt Policy
A1. The rezoning does not meet the Town Planning Board Guidelines See paragraphs 6.3.1 and 6.3.5
for Application for Development within Green Belt (GB) of the TPB Paper.
Zone under Section 16 of the Town Planning Ordinance in that
there should be presumption against development in GB zone
and residential development is not suitable use for the GB site.
A2. The Site is close to Lion Rock Country Park and should be See paragraphs 6.3.1 to 6.3.4 of
retained as green belt buffer and retain visual openness of the Site. the TPB Paper.

A3. The Site comprises vegetated woodland and should not be used See paragraphs 6.3.1 to 6.3.4 of
for development of luxury flats. the TPB Paper.
B. Housing Demand and Supply
B1. There is no shortage of land for the development of luxury flats in See paragraph 6.3.6 of the TPB
Hong Kong. Rezoning GB sites for such use will not help to Paper.
address overall housing problem, but will lead to speculation and
escalated property prices. To address the housing problem,
brownfield sites and vacant Government land should be developed
before GB sites.
B2. The Government should also control population growth. See paragraph 6.3.6 of the TPB
Paper.

C. Development Impacts
C1. The Site is close to the Lion Rock Tunnel portal and is not suitable See paragraph 6.3.7 of the TPB
for housing as it will be subject to air and noise pollution. Paper.

C2. The proposed development will generate additional traffic near the See paragraph 6.3.8 of the TPB
Lion Rock Tunnel and will create adverse traffic impacts. Paper.
D. Planning Process
D1. Including the Site in the 2017-18 land sale programme before the See paragraph 6.3.9 of the TPB
completion of the rezoning is a mockery of the town planning Paper.
process.
Representers Proposals Responses
P1. To reject the OZP amendments and to retain the GB zone. See paragraph 6.4.1 of the TPB
1
Paper.
P2. To lower the PR to 0.4 if rezoning of the Site to residential is See paragraphs 6.4.2 and 6.4.3
permitted. of the TPB Paper.

(2) The ground of comment C1 that is additional to the grounds of representations in part (1) of the
table and responses is provided below:
Comment in Representations Response
E. Green Belt Policy
The criteria for rezoning GB sites are devegetated, deserted or See paragraphs 6.3.1 to 6.3.4 of
formed and have relatively low value as conservation or buffer zones. the TPB Paper.
The Site does not meet these criteria.

(3) Major Grounds and Proposals of Representations:


Representers Main Grounds
R1 A3, B1, B2, C1, P1
R2 A3, B1, B2, P1
R3 A2, A3, B1, P1
R4 A3, B1, P1
R5 A3, B1, C2, D1, P1
R6 A1, A2, P1, P2
R7 A3, B2, P1

(4) Major Grounds of Comment:


Commenter Related Representation(s) Main Grounds
C1 R1, R3 and R6 B1, D1, E

2
LEGEND

--q AMENDMENT ITEM

sDlsG
uaavu
A REZONING OF A PIECE OF LAND NEAR THE JUNCTION OF
LUNG CHEUNG ROAD AND LION ROCK TUNNEL ROAD
FROM "GREEN BELT" TO "RESIDENTIAL (GROUP C)11"

sD_-
uaav
B1 REZONING OF A STRIP OF LAND ABUTTING
THE NORTHERN KERB OF LUNG CHEUNG ROAD
FROM "GREEN BELT" TO AN AREA SHOWN AS 'ROAD'

sDn-
uaav
B2 REZONING OF A STRIP OF LAND ABUTTING
THE SOUTHERN KERB OF LUNG CHEUNG ROAD
FROM "GREEN BELT" TO AN AREA SHOWN AS 'ROAD'

G/IC(1)

G/IC(6)

R(C)1
R(C)1

G/IC(2)

G/IC(9) G/IC(7)

LOCATION PLAN W
K-n2017~6
JEs-
PLANNING
20

i-pj
// DEPARTMENT
AMENDMENTS INCORPORATED INTO THE DRAFT
EXTRACT PLAN PREPARED ON 2.6.2017
BASED ON OUTLINE ZONING PLAN No. KOWLOON TONG OUTLINE ZONING PLAN No. S/K18/20
S/K18/20 EXHIBITED ON 13.1.2017 REFERENCE No.
PLAN
SCALE 1 : 5 000
METRES 100 0 100 200 METRES
R/S/K18/20 H - 1
ls-
LION ROCK COUNTRY PARK

-z-s
REPRESENTATIONS No. R1 - R7

N
RELATED COMMENT No. C1

--q -z-s

AMENDMENT ITEM B1 REPRESENTATIONS No. R1 - R7

N
RELATED COMMENT No. C1

--q
AMENDMENT ITEM A

G/IC(1)

G/IC(6)

-z-s
REPRESENTATIONS No. R1 - R7

N
RELATED COMMENT No. C1

--q
AMENDMENT ITEM B2

R(C)1
R(C)1

G/IC(2)

G/IC(9) G/IC(7)

-z-a
LOCATION PLAN OF REPRESENTATION SITES
W
K-n2017~6
NEs-pj PLANNING
20
X-z-s- DEPARTMENT
i-pj
CONSIDERATION OF REPRESENTATIONS No. R1-R7
EXTRACT PLAN PREPARED ON 8.6.2017
AND RELATED COMMENT No. C1 TO THE DRAFT
BASED ON OUTLINE ZONING PLAN No.
S/K18/20 EXHIBITED ON 13.1.2017 KOWLOON TONG OUTLINE ZONING PLAN No. S/K18/20
REFERENCE No.
PLAN
SCALE 1 : 5 000
METRES 100 0 100 200 METRES
R/S/K18/20 H - 2
LEGEND

a
1 VIEWING POINT OF SITE PHOTO

uu
BOUNDARY FOR IDENTIFICATION PURPOSE ONLY

lsWG
Lion Rock High Level No.2
Primary Service Reservoir

LI
ON R

O CK
B1 ITEM A

ls
TU
ITEM B1 4

NNEL
RO AD

sD 6
Lung Cheung Road
5 H
Playground
R L
UNG ( 2




C FOOTBRIDGE


Pearl Court
HE
UNG
R 3
OAD (SUBJECT TO




Vista Panorama
DETAILED DESIGN)
RHO
ND
DA
R s
Chermain D s
s
s P
P
P
P
Heights Broadcast Drive Peninsula
Garden
AD

Heights
s
s
s
s s
s
s
s
RO

Lung Cheung Road Lung Cheung Road Park 1


Park

s
LL


HI

Dragon
Heights Joy Garden f
Z
Eastland
N

Le Chateau B2
AD
Heights
CO

RO

RD

z

ITEM B2 WATEROO
L Rockford
BEA

CK

s Westland
Mansion
WI

Heights
Manhattan


Court
ALN

Clifford
M Jumbo Mansion
Court E
V

U
RI
Moonbeam Jade Court
Alice Court
w

Terrace Marple
D
s Welcome Court
-

Gardens
q
S

qwD Lung Cheung Court ST


u
Ede Road CA u
u
u
H

D
Playground
BROA Merry Court

FE
SS
ED

EN
[ D
EN
D
R

i
s

M Beacon Hill RO
K

Phoenix Court
IC

AD
RO

Luso School
W
R

Apartments
A

-qx
W

AD

y H
H
H
H
M

M Radio Television
AR

Orion Court Hong Kong Fessenden


CO

Broadcasting House Court



NI

Faber Garden
RO
AD A
A
A
A
Twilight
Court

AERIAL PHOTO W
K-n2017~6 PLANNING
aF`p JEs-pjs
s (B
DEPARTMENT
EXTRACT PLAN PREPARED ON 9.6.2017 AMENDMENTS INCORPORATED INTO THE DRAFT
BASED ON AERIAL PHOTO No. CS60465
KOWLOON TONG OUTLINE ZONING PLAN No. S/K18/20
TAKEN ON 20.6.2015 BY LANDS DEPARTMENT REFERENCE No.
PLAN
(ITEMS A, B1 AND B2)

R/S/K18/20 H - 3
1


Vista
R A
Pearl
B1
Panorama ITEM A
Court ITEM B1

B2
ITEM B2

s D
l LROA
NNE
KTU
ROC
I
LON
s
Lung Cheung Road
Park

OAD
TR
E OO R
L
WA

L
UN
G s
CH
EU
NG
RO
AD

P
VIEW FROM PENINSULA HEIGHTS

2
B2

ITEM B2


A
Vista
Panorama
ITEM A

s
LUNG CHEUNG ROAD

lsGD
VIEW FROM FOOTBRIDGE AT LION ROCK TUNNEL ROAD

uu
BOUNDARY FOR IDENTIFICATION PURPOSE ONLY

a SITE PHOTOS W
2017~67
PLANNING
2016 JEs-pjs
2016~128 (B
DEPARTMENT
PLAN PREPARED ON 7.6.2017 AMENDMENTS INCORPORATED INTO THE DRAFT
BASED ON SITE PHOTOS KOWLOON TONG OUTLINE ZONING PLAN No. S/K18/20
TAKEN ON 1.4.2016 AND 8.12.2016 REFERENCE No.
PLAN
(ITEMS A, B1 AND B2)

R/S/K18/20 H - 4a
3




Vista
Panorama R
R
R
R




A
Pearl
Beverley ITEM A
Court
Heights

LU
N
G
C
H
EU
N
G
RO
AD

lsGD
VIEW FROM FOOTBRIDGE AT LION ROCK TUNNEL ROAD


The Palace
4
A
ITEM A

lsWG
VIEW FROM LION ROCK HIGH LEVEL No. 2 PRIMARY SERVICE RESERVOIR

uu
BOUNDARY FOR IDENTIFICATION PURPOSE ONLY

a SITE PHOTOS W
2017~67
PLANNING
2016~ JEs-pjs
2016~321 (
DEPARTMENT
PLAN PREPARED ON 7.6.2017 AMENDMENTS INCORPORATED INTO THE DRAFT
BASED ON SITE PHOTOS KOWLOON TONG OUTLINE ZONING PLAN No. S/K18/20
TAKEN ON 8.12.2016 AND 21.3.2016 REFERENCE No.
PLAN
(ITEM A)

R/S/K18/20 H - 4b
R
R
R
R
Pearl
5 Court

B1
ITEM B1

s
LUNG CHEUNG ROAD

sDFu
VIEW FROM THE EXISTING ROAD ACCESS AT LUNG CHEUNG ROAD EASTBOUND

B1
ITEM B1 The Palace

L s
UN
GC
HE
UN
GR
OA
D

sDFu
VIEW FROM THE EXISTING ROAD ACCESS AT LUNG CHEUNG ROAD EASTBOUND

uu
BOUNDARY FOR IDENTIFICATION PURPOSE ONLY

a SITE PHOTOS W
PLANNING
2017~67 JEs-pjs
2016~12 (
DEPARTMENT
PLAN PREPARED ON 7.6.2017 AMENDMENTS INCORPORATED INTO THE DRAFT
BASED ON SITE PHOTOS KOWLOON TONG OUTLINE ZONING PLAN No. S/K18/20
TAKEN ON 8.12.2016 REFERENCE No.
PLAN
(ITEM B1)

R/S/K18/20 H - 4c
[
1 {
VIEWING POINT
EXISTING VIEW


Lion Rock


The Palace


WATERLOO ROAD

X
PHOTOMONTAGE


Lion Rock


The Palace
PROPOSED
BUILDING

LOCATION PLAN

[
l
TUNNEL
LI

One Beacon
ON ROC

Hill
s

UNGR
ROAD

E D. Tin Ma
CH
K

Court
G


s
N


LU

s
-

qM Hong Kong The Palace
CORNWAL
LS Baptist
T
.
Hospital pX

p Junction Road
JU Park
N
C h
TI
O
F N Morse
Park
RO AD
W ATERLOO

WATERLOO ROAD
ROAD
NE
LLI
RAI

Es
Kowloon
EAST

1 Tsai Park
S
YAU YAT E
TSUEN KOWLOON TONG

X PHOTOMONTAGE W
K-n2017~6
PLANNING

D- DEPARTMENT

EXTRACT PLAN PREPARED ON 5.6.2017 VIEW FROM FOOTBRIDGE


BASED ON SITE PHOTO TAKEN ON 8.4.2016 AT WATERLOO ROAD NEAR RUTLAND QUADRANT
REFERENCE No.
PLAN

R/S/K18/20 H - 5a
[
VIEWING POINT
2 {
EXISTING VIEW


The Palace

I
Fu Keung Court

pX
Junction Road Park

X
PHOTOMONTAGE


The Palace


PROPOSED
BUILDING
I
Fu Keung Court LOCATION PLAN

[
l
TUNNEL
LI

One Beacon
ON ROC

Hill
s

UNGR
ROAD

E D. Tin Ma
CH
K

Court
G


s
N


LU

s
-

qM Hong Kong The Palace
CORNWAL
LS Baptist
T
.
Hospital pX

p Junction Road
JU Park
N
C h
TI
O Morse
F 2 N
Park
RO AD
W ATERLOO

pX
ROAD
NE

Junction Road Park


LLI
RAI

Es
Kowloon
EAST

Tsai Park
S
YAU YAT E
TSUEN KOWLOON TONG

X PHOTOMONTAGE W
K-n2017~6
PLANNING

pXD DEPARTMENT

EXTRACT PLAN PREPARED ON 5.6.2017 VIEW FROM JUNCTION ROAD PARK


BASED ON SITE PHOTO TAKEN ON 8.4.2016
REFERENCE No.
PLAN

R/S/K18/20 H - 5b
[
VIEWING POINT
3 {

EXISTING VIEW
Tin Ma Court

The Palace

P
Peninsula
Heights


s

LU
N
G
C
H
EU
N
G
RO
AD

X

The Palace PHOTOMONTAGE
Tin Ma Court


PROPOSED
BUILDING
P
Peninsula
Heights

LOCATION PLAN

[
l

TUNNEL
LI

One Beacon
ON ROC
s

Hill
s

UNGR
ROAD

E D. 3 Tin Ma
CH
K

Court
G


LU

s
N


LU

s
-
N

qM Hong Kong The Palace


CORNWAL
LS Baptist
T
.
C

Hospital pX

H

p Junction Road
JU
EU

Park
N
C h
TI
N

O Morse
F N
G

Park
RO AD
W ATERLOO
RO

ROAD
NE
AD

LLI
RAI

Es
Kowloon
EAST

Tsai Park
S
YAU YAT E
TSUEN KOWLOON TONG

X PHOTOMONTAGE W
K-n2017~6
PLANNING

sD DEPARTMENT

EXTRACT PLAN PREPARED ON 5.6.2017 VIEW FROM FOOTBRIDGE AT LUNG CHEUNG ROAD
BASED ON SITE PHOTO TAKEN ON 8.4.2016
REFERENCE No.
PLAN

R/S/K18/20 H - 5c
T
ON
GCH
U
NGT
ON
G

LI
116.9 K
W
UNKW
A
IKO
W
LO
O
N

ON
L


CUL
L

RO C
CUL 103.2

CUL
117.5

K TUN
10
0

ACCESS ROAD FOR

NEL
V In
CUL
106.0 SERVICE RESERVOIR Toll
88.3

sp
118.3
118.0
117.2
$8 103.1

RO A
L
104.0
110.9

Ht
K-TS9

Ht 4.

4.6
87.7

D
0
CUTLI

Tu
m
6
1

n
m

Ar
ea
117.5

En
NE A-

d

V In
WIDTH 7.3m

sp
SITE BOUNDARY
L
A

Ht
4.6

ls
PR 104.1
L 86.2
OP

m
OS
ED CUL SUBJECT SITE 93.5

DE 103.9
CE


LE

Tun Area Sta

Tr
D G
Cat
RA

50
TI

Mg
ON

km/h
Proh
1,

L/
T
LA

2,
/
70

50
NE

LI
km
R 20m

/h PROPOSED VEHICULAR

5
(

km/h
ON
70

S
m) ACCESS

T
L
Tun KL L

RO C
83.1
84.7

RLC
87.8
Sha Tin Kwun Tong
95.7 70 87.0
via Lion Rock Tunnel

K T
Sha Tin (via Tate's Cairn Tunnel) BUSES Wong Tai Sin
km
/h M EDIU M A N D HEAVY
?

0
GO O DS VEHICLES
, ? ?? ? ? ? ?) 101.4

0
70 KEEP LEFT
L m ? ? ? ? Kwun Tong
R8

1
km
/h

UNN
EXIT

12 1 7 7 PH

m
35
K/KC/LunC-G50A L 7 Hong Kong (E)

K-TS229 (?)

EL R
K-TS229
96.3

R
DI
20 8 E 10B
ad
0L
9 Sharp Devi
Ro PROPOSED PROVISION OF
70
Sharp Devi K/KC/LioRT-03A

O AD
km
EXISTING SIGN GANTRY PROPOSED PEDESTRIAN LIFT AND STAIRCASE AT Sharp Devi
/h
WIDTH 3m D Sharp Devi EXISTING FOOTPATH CONNECTION
TO BE RELOCATED ACCESS VIA FOOTBRIDGE LUNG CHEUNG ROAD FOOTPATH Sharp Devi

H
CUL TO BROADCAST DRIVE GARDEN
L
ad
24R
/h w
D G Proh 50
km
Ro S
l
o
L
LUNG
D
L
95.2 CHE
UNG MERG m/h
85.9 70 km/h
/ 24R

PRO ROA ING D 50 k

POS L D I
ST

El
ED 95.3
ANCE L
(
1

evated
ACC 70m) 84.2
EXISTING SIGN GANTRY ELERA 80.3
R TI
ON L
TO BE RELOCATED
s 70 km/h

[
Pearl Court TAPE L 91.1
L L
R (
1

Road
Bl 50m) 87.7
oc 93.3
k L
A
LUNG CHEUNG ROAD
Bl H
oc H
kB 24R

D G Proh

T un
109.2
106.0
H 28
K-TS374 88.3
L

Area
e 1
Lan
Busa
St
Sham Shui Po & Kwai Chung 9 ea
CUL 2 Ar

End
1 n
WIDTH 3.5m Tu

ROAD
? ? Sha Tin EXIT

12 n
e
a
PROPOSED DOUBLE 104.1 7 7 7
1
s
L
90
B
u
L End L
LENGTH BUS LAY-BY K/KC/LunC-G12A d
CUTLI

n Sha Tin
E via Lion Rock Tunnel
K-TS734 Ht 4.6m / D G Proh /

Dn
101.0 107.0
PROPOSED Cat 1, 2, 5 89.0

LO O
26m L

1:8
? ? ? ?

m
98.4

k
SEGREGATION BY EXIT

0
12 1

Dn
NE A-

L
CUL CHEVRON
CULROAD Please g
ive way

ER
50 km/h K/KC/LunC-G05A

1:8
to buses
26 MARKINGS Kwun Tong
m

WAT
Sha Tin (via Tate's Cairn Tunnel)

EUNG ROAD 98.3 K-TS374


, ? ?? ? ? ? ?)

EXISTING STAIRCASE s
7
A

100
7 7
E
LAN

L
TO BE MODIFIED K/KC/LunC-G08A LAN
E
GET
IN 10A

90
101.0 IN
PROPOSED Lung Cheung Road Park

1 00
GET Sharp
L
90


89.2 Devil

99.2 80
PROPOSED DOUBLE BUS LANE Sharp
s P


DI Devil
30 L
0L LENGTHLung
BUSCheung
LAY-BYRoad Park
E

PROPOSED CLOSURE OF EXISTING FOOTPATH 83.7


L L Sharp
ALONG LUNG CHEUNG ROAD82SLIP ROAD WITH
LU
NG L PROPOSED FOOTBRIDGE
ALTERNATIVE PEDESTRIAN ROUTE READILY
Devil


Sharp
CONNECTION TO LUNG CHEUNG
CH
EU ROAD PARK AT +97-98mPD AVAILABLE VIA LUNG CHEUNG ROADFP PARK
Devil

F
NG

FP
RO CUL
98.7
LEGEND:
AD L
SITE ACCESS
95.7 78.0
20
L L 1
77.7
SITE BOUNDARY

x P
l sD 83.8 PROPOSED ROAD ALIGNMENT/
bal
B
d
kett L
PEDESTRIAN FACILITIES
Basour
R
e
d
C Lung Cheung Road Playground u
c
e
S
p
91.6
Tu
EFFECTIVE WIDTH ON ALL PROPOSED FOOTBRIDGES
n
Ar
84.3
88.1
L ea
St
a
AND STAIRS TO BE 2.0m (TOTAL WIDTH 3.0m)

-- SITE PLAN
W
B PLANNING DEPARTMENT
K-n2017~
PROPOSED TRANSPORT RELATED PROVISIONS
EXTRACT PLAN PREPARED ON 5.6.2017

REFERENCE No.
PLAN
SCALE 1 : 1 000

20 0 20 40 60 80
METRES METRES R/S/K18/20 H - 6