DAILY REPORT ON INTERNSHIP ACTIVITES CARRIED OUT AT

PAN OCEAN OIL CORPORATION (POOC) NIG. LTD. OVADE


OGHAREFE FACILITY
DATE: SATURDAY, 8TH APRIL 2017
PREPARED BY: IMEH, VICTOR OKON
DEPARTMENT OF ELECTRICAL/ELECTRONIC ENGINEERING
AFE BABALOLA UNIVERSITY

PROGRESS:
Liaised with contractor(Abergyl) in carrying out the following:
Sourced for level gauge and level controller from the store house
Mounted level gauge with side glass (LG207A & LG207B) at skid
11(depropranizer skid)
Mounted level gauge with side glass(LG234) at skid 12
Began mounting of level controller at skid 3 (fuel gas scrubber skid)
Familiarization of Gas Processing Plant II (GPP II)
Identification and description of VSHH (Vibration Switch High High)
Identification and description of LSHH (Level Switch High High)
PROBLEMS:
Had issues mounting level controller due to absence of nipple
PLANS:
Proper dimensions should be taken into consideration when purchasing instruments
and proper fittings purchased.