Sep20 Two Storey Training Hall and Dormitory
Sep20 Two Storey Training Hall and Dormitory
ACTUAL ACCOMPLISHMENT
20-Sep-17
CONCRETE 191.369 m3
FOOTINGS 126.9
QTY L W THK VOL,M3
C1-F1 9 3 3 0.45 36.45
C1-F1A 3 11 3 0.45 44.55
C2-F1 4 3 3 0.45 16.2
C3-F2 9 2.5 2.5 0.4 22.5
C4 16 1 1 0.45 7.2
COLUMNS 31.536
QTY H L W VOL,M3
C1 12 5.4 0.6 0.5 19.44
C2 4 5.4 0.5 0.4 4.32
C3 9 5.4 0.4 0.4 7.776
RB-1A 1 12 12.6 126 1512 1.4 151.2 176.4 1.579 0.616 347.4072
RB-1B 1 12 18.45 184.5 2214 1.4 221.4 258.3 1.579 0.616 508.7034
FORM WORKS
Securing of Construction
1 Permits, Building permit,
permit to operate, sanitay
& Electrical Permit, Fire
Safety and Occupancy
Permit 1.0 lot 75,000.0 75,000.00
electrical consumptions
2 material testings 1.0 lot 84,000.0 84,000.00
II Site Works 1.0 Lot 4.020% 2.329%
A
a.1 Clearing/Staking/Levelling/
Chipping &
Dismantling/Hauling of
excess materials 1.0 lot 10,000.0 10,000.00 0.40 4,000.00 1.608%
a.2 Temfacil 1.0 lot 35,000.0 35,000.00 0.80 28,000.00 3.216%
a.3 Excavation 1,115.0 cu.m 150.0 167,250.00 650.82 97,623.00 2.346%
a.4 Backfill 866.0 cu.m 280.0 242,480.00 462.32 129,448.48 2.146%
III Structural Steel Works 66,002.4 kgs 26.960% 31,498.11 12.866%
A 25mm dia x 6m RSB 110.0 pcs. 875.0 96,250.00 -
B 20mm dia x 6m RSB 992.0 pcs. 559.0 554,528.00 -
C 16mm dia x 6m RSB 2,310.0 pcs. 357.0 824,670.00 -
D 12mm dia x 6m RSB 1,892.0 pcs. 199.0 376,508.00 -
E 10mm dia x 6m RSB 3,787.0 pcs. 138.0 522,606.00 -
F #16 GI tie wire 825.0 kg 70.0 57,750.00 -
STEEL DECK DURAWEB 1020 @
G 1.2mm thk. Union galvasteel 866.44 lms 715.0 619,504.60 - -
IV Concrete Works 447.0 cu.m 13.230% 191.37 5.664%
A Cement Type 1 4,023.0 bags 210.0 844,830.00
B Albay Sand 245.0 cu.m 600.0 147,000.00
C 3/4 Gravel 447.0 cu.m 900.0 402,300.00
D Ordinary Gravel (Apple size) 39.0 cu.m 650.0 25,350.00
E Concrete canopy 1.0 lot 41,500.0 41,500.00
F Concrete trellis 1.0 lot 17,500.0 17,500.00
G Water Proofing compound (Plexi 27.0 gal 715.0 19,305.00
V Masonry Works 1,458.0 sq.m. 7.210% 167.000 0.826%
A 6" thk CHB 8,275.0 pcs. 14.0 115,850.00
B 4" thk CHB 9,950.0 pcs. 12.0 119,400.00
C Cement Type 1P 1,635.0 bags 210.0 343,350.00
D Albay Sand 131.0 cu.m 600.0 78,600.00
E 12mm dia x6mtrs rsb 638.0 pcs. 199.0 126,962.00
F #16 GI tie wire 43.0 kgs 70.0 3,010.00
G Decorative Stones 28.0 box 1,040.0 29,120.00
XIII. Forms and Scaffoldings 1.0 lot 4.390% 0.37 1.624%
A 1/4" thk x 4x8 marine plywood 70.0 pcs. 450.0 31,500.00
B 1/2" thk x 4x8 marine plywood 140.0 pcs. 850.0 119,000.00
C 2"x3"x12' coco lumber 2,500.0 pcs. 95.0 237,500.00
D GI scaffoldings 1.0 lot 90,000.0 90,000.00
E Assorted CWN 8.0 box 2,400.0 19,200.00
XV Soil Poisoning 1.0 Lot 0.000% - 0.000%
A Soil Poisoning 1.0 lot 35,000.0 35,000.00