Cycle time (C/T)

The period required to complete one cycle of an operation, or complete a function, job, or task
from start to finish. The table below contains cycle time of ready mix concrete production
No Activity Time
1 Loading cement to cement transfer 80,5 sec
2 Blowing cement in silo 91 sec
3 Pumping water to tank 3,5 sec
4 Pumping Admix. In tank 3,5 sec
5 Aggregate available 61 sec
6 Loading aggregate to conveyor 61,5 sec
7 Loading aggregate to mixer 630 sec
8 Weighing and mixing 690 sec
9 Filling of truck 36 sec

Changeover Time (C/O)


The period required to prepare person, machine, or system of an production of ready mix
concrete. The table below contains changeover time of ready mix concrete production.

No Activity Time
1 Loading cement to cement transfer 11 sec
2 Blowing cement in silo 0 sec
3 Pumping water to tank 0 sec
4 Pumping Admix. In tank 0 sec
5 Aggregate available 0 sec
6 Loading aggregate to conveyor 0 sec
7 Loading aggregate to mixer 0 sec
8 Weighing and mixing 0 sec
9 Filling of truck 12 sec

Current Value Stream Map


There are three important things in creating current value stream map, which is customer data,
supplier data, and business process. Customer PT. Varia Usaha Beton are contractors, where
the contractor releases an order (spesification) to batch to the supplying process (the batch
plant) and receives product as a result (Figure 3).