Proposed Community Center Existing Recreation Center Project Costs
Proposed Community Center Existing Recreation Center Project Costs
Phase 3
Existing Building Footprint: 24,800 sf Proposed Building Footprint: 25,000 sf Community Center Building: $15,960,000
The Recreation Center is an outdated 70-year The proposed Community Center will meet the Community Center Site Work: $575,700
old building that has inadequate spaces for needs of todays community and can evolve to Surface Parking: $466,000
programs, services, and events. Due to its lack meet future needs. The new spaces provide Contingencies: $2,550,255
of ADA compliance and limited parking, it new programming opportunities for community FF&E
(furniture, equipment, technology): $1,012,000
community members. Other challenges 43% larger than the existing facility by having a Soft Costs: $6,948,803
include:
Outdated building infrastructure (mechanical, Operationally and environmentally sustainable Total Phase 3: $27,512,758
plumbing, electrical, and data systems) An indoor/outdoor stage for theatre, music, and
Seismic safety issues events
A facility site and building design that honors Optional (as a part of Phase 3)
the history and heritage of Washington Park and Parking (under building): $6,384,000
Burlingame Contingencies: $957,600
Programming capacity of 300 hours per week
Programming capacity of 510+ hrs. per week Soft Costs: $2,081,344
A new playground in a safer location farther from
Total Optional: $9,422,944
A new outdoor sports court/basketball court
Current technology to meet the needs of the
Burlingame community