Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 15

JaxWorks Small Business Spreadsheet Factory

Since 1996, JaxWorks has offered a suite of Free Excel workbooks and spreadsheets, and associated MS Word, PDF and
HTML documents, that cover a number of financial, accounting and sales functions. These are invaluable small business
tools.

Also included Free are:


- Business plan tools, including spreadsheets and excellent instructions
- Excel functions glossary and guide;
- Free training courses for most Microsoft Office applications. These guides are in PDF format and rival
commercial books.
- Comprehensive list of acronyms, ratios and formulas in customer financial analysis, and financial terms;
- Suite of online calculators, including, breakeven analysis, productivity analysis, business evaluation;
- Altman Z-Score (covering publicly and privately held firms, and small businesses);
- and payroll analysis.

If you are involved in financial analysis at any level, or want to learn more about MS Excel and other applications in the
Office suite this site is invaluable.

Copyright, 2014, Jaxworks, All Rights Reserved.


Belhasa Engineering & Contracting Co LLC
MEP DAILY REPORT

Project Name: Proposed 2B+G+24 storey residential and c Date: 9/19/2017 Project Number: J-215

Location: Al Nahda-1 Dubai REPORT NUMBER: DAY: Tuesday

Weather Report: clear

Temperature:
High o

Low o

MEP Contractor Power Point LLC No. of No. of * Was work delayed for any reason? NO If yes, describe
Men Hours
Power Point Operation Manager 1 8
Power Point MEP Engineers 3 8

* Was stoppage ordered in writing? NO If so, by whom?


HVAC Foreman 0 0
Nos of Worker 0 0

Electrical Foreman 0 0
Nos of Worker 0 0 * Were verbal instructions received: NO If yes, describe

Plumbing/Fire Fighting/Piping Foreman 0 0


Nos of Worker 0 0
Other:
* Has letter confirming verbal instructions been written?
MEP WORKER DETAILS No. of No. of
Men Hours * Have you given any Subcontractor special written or verbal
0 0 instructions? NO If so, describe
0 0
0 0
0 0
0 0 * Were any change orders received or implemented today?
0 0 If yes, describe change order,

0 0
0 0
0 0
0 0
0 0 * Was project delayed because of lack of: NO
0 0 Materials N/A
0 0 Information N/A
Interference N/A
Other Trades N/A
Subcontractors N/A
Other Reasons N/A

* If so, describe

Copyright, 2010, JaxWorks, All Rights Reserved.


Tests/Inspections * Was any Subcontractor scheduled to start or material
due to arrive which did not appear? NO
If so, describe

* Were you required to do Extra Work? NO


Was it authorized?
Should it be backcharged?
Visitors-Names Representing If so, describe

* Vendor Rental Equipment on Site

* Was a safety meeting held today? NO


Topics:

* Were there any lost time accidents recorded today?

Describe day's activities giving quantities, location of work, trades involved, etc.

Remarks:

Name
Signature

Copyright, 2010, JaxWorks, All Rights Reserved.


Superintendent

Copyright, 2014, Jaxworks, All Rights Reserved.

Copyright, 2010, JaxWorks, All Rights Reserved.


If yes, describe

If so, by whom?

If yes, describe

NO

NO

Copyright, 2010, JaxWorks, All Rights Reserved.


NO

Copyright, 2010, JaxWorks, All Rights Reserved.


Copyright, 2010, JaxWorks, All Rights Reserved.
Belhasa Engineering & Contractin
MEP DAILY REPORT

Project Name:

Location: Al Nahda-1 Dubai REPORT NUMBER:

Weather Report: clear

Temperature:
High o

Low o

MEP Contractor Power Point LLC No. of


Men
Power Point Operation Manager 1
Power Point MEP Engineers 3

HVAC Foreman 0
Nos of Worker 0

Electrical Foreman 0
Nos of Worker 0

Plumbing/Fire Fighting/Piping Foreman 0


Nos of Worker 0
Other:

MEP WORKER DETAILS No. of


Men
0
0
0
0
0
0
0
0
0
0
0
0
0

Tests/Inspections

Visitors-Names Representing
Describe day's activities giving quantities, location of work, trades involved, etc.

Remarks:
Copyright, 2014, Jaxworks, All Rights
neering & Contracting Co LLC
MEP DAILY REPORT

Project Number: J-215

REPORT NUMBER: DAY: Tuesday

No. of * Was work delayed for any reason? NO If yes, describe


Hours
8
8

* Was stoppage ordered in writing? NO If so, by whom?


0
0

0
0 * Were verbal instructions received: NO If yes, describe

0
0

* Has letter confirming verbal instructions been written? NO


No. of
Hours * Have you given any Subcontractor special written or verbal
0 instructions? NO If so, describe
0
0
0
0 * Were any change orders received or implemented today? NO
0 If yes, describe change order,

0
0
0
0
0 * Was project delayed because of lack of: NO
0 Materials N/A
0 Information N/A
Interference N/A
Other Trades N/A
Subcontractors N/A
Other Reasons N/A

* If so, describe

* Was any Subcontractor scheduled to start or material


due to arrive which did not appear? NO
If so, describe

* Were you required to do Extra Work? NO


Was it authorized?
Should it be backcharged?
nting If so, describe

* Vendor Rental Equipment on Site


* Was a safety meeting held today? NO
Topics:

* Were there any lost time accidents recorded today? NO


Name
Signature
Superintendent