Professional Documents
Culture Documents
Cost Management Lecture 2 2
Cost Management Lecture 2 2
Planning
Cost Management
Plan Cost Magmt Plan
Planning
Control Cost
Performance
Forecast
Measurements
It focuses to find the less costly way to do the same thing. In Other words, this
technique asks How can we decrease the cost on the project while
maintaining the same scope.
- Analogous Estimation.
- Parametric Estimation.
- Bottom up Estimation.
- Contingency Reserves
- Management Reserves
Basic Parameters
CV = EV - AC
SV = EV - PV
CPI= EV/AC
SPI= EV/PV
CV = +ve (Under Budget) CPI >1 ( Under Budget)
CV = -ve (Over Budget) CPI < 1(Over Budget)
CV = 0 (On Budget) CV = 1 (On Budget)
Actual cost for Project is 57,000$. What is Schedule Performance Index &
Cost Performance index of the Project?
A. 350
B. -75
C. 400
D. -50
BAC= 150,000 USD.06 months after the Project Start, you find our that PV =
40,000 & you have spent an actual cost of 38,000 USD. If CPI = 1.22, then what
will be your earned value cost.
Construct 05 Rooms
Budget for Project = 5,000$
Project Duration = 05 Months
Start $ $ $ $ $ END
1000 1000 1000 1000 1000
M1 M2 M3 M4 M5
Budget = $ 5,000
$
1000
Start END
$
1000
M1 M2 M3 M4 M5
PV = 1,000$ (1 Room)
EV= 1,000$ (1 Room done)
AC= 950$ (What spent)
Budget = $ 5,000
$ $
1000 1000
Start END
$ $
1000 1000
M1 M2 M3 M4 M5
PV = 2,000$ (2 Room)
EV= 2,000$ (2 Room done)
AC= 2,000$ (What spent)
CV=0, SV=0, CPI=1, SPI=1 By: Engr.Faiz Rasul
E: pmp@cmsofficial.com, Ph.: 00966599454518
After Month- 3
Budget = $ 5,000
$ $ $
1000 1000 1000
Start $ 500 END
$ $
1000 1000
M1 M2 M3 M4 M5
PV = 3,000$ (3 Room)
EV= 2,500$ (2.5 Room done)
AC= 2,800$ (What spent)
Estimate To Complete.
Budget = $ 5,000
$ $
$
1000 1000
1000
Start END
$ $
$ 500 $ $
$ 500
1000 1000
$
1000 1000
M1 M2 M3 M4 M5
ETC = BAC EV
Hint* = ( Total Value of work Work Done = Remaining Work)
By: Engr.Faiz Rasul
E: pmp@cmsofficial.com, Ph.: 00966599454518
Now When You have Actual Cost Till Date & You know
Estimate to Complete also, Can you Predict How much
will be the Estimate At compltion of Project?:
Estimate at Completion= EAC = How Much we have spent+ How much more we need to Spend
Budget = $ 5,000
$ $
$
1000 1000
1000
Start END
$ $
$ 500 $ $
$ 500
1000 1000
$
1000 1000
M1 M2 M3 M4 M5
If at initially planned rate then?
EAC = AC + ETC If at Current rate then?
or AC + (BAC-EV) = 2,800 + (5000-2500) = 5,300$ EAC = BAC / CPI= 5000 / 0.89 = 5,617 $
Sample Questions:
On Your Project EV = 3500 , AC= 4000 & PV= 3850. Project Budget at completion
is 20,000 USD. If Cost performance index is expected to be same as it is, then
what is Estimate at completion.
CV = EV- AC
SV= EV-PV
CPI= EV/AC
SPI = EV/PV
ETC= BAC-EV
EAC= AC+ETC , EAC= AC + (BAC-EV), EAC = BAC/CPI
VAC = BAC EAC