Number:AFISR/MEP/E/022
Inspection Points
Inspection and Test Specification
Item No. Activity Description Frequency Acceptance Criteria Verifying Document / Report
Activity Reference SUB-CON CONT ITL ENGINEER
1 Material Approval
A33 Quality
Before site Standards and
Approved Material Submittal
1.1 11KV MV SWITCHGEAR PANEL Submit to the Engineer execution of the ENGINEER Approval Control,170.005 R R - R/A
Form
activity Standard and
Regulation
2 Drawing Submittal
Part A, A31
Before site
Provision,Content Approved Shop Drawings
2.1 H.V. Schematic Diagram Submit to the Engineer execution of the Workmanlike. ENGINEER Approval R R -- R/A
and use of Submittal Form
activity
Documents
3 Method Statement
Page 1 of 2
ITP Reference
Number:AFISR/MEP/E/022
Inspection Points
Inspection and Test Specification
Item No. Activity Description Frequency Acceptance Criteria Verifying Document / Report
Activity Reference SUB-CON CONT ITL ENGINEER
5 Installation
Comments if any:
Page 2 of 2