CONSTRUCTION SCHEDULE OF THE PERIMETER FENCE (GANTT CHART)

NUMBER OF DAYS
CONSTRUCTION ACTIVITIES CONTRACT AMT. WEIGHT %
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 100
A DELIVERY OF MATERIALS 12,000.00 3.07 90
ACTIVITY CODE

B EXCAVATION OF FOOTING 18,000.00 4.61


80
C EXCAVATION OF WALL FOOTING 8,600.00 2.20
70
D REBAR WORKS AND FORMWORKS 72,668.00 18.62
60
E CONCRETE POURING 52,440.56 13.44
F CONCRETE CURING 1.35 50
5,250.00
G MASONRY WORKS 98,000.00 25.11 40
H LOT FILLING 50,000.00 12.81 PROJECTED ACCOMPLISHMENT S-CURVE 30
I INSTALLATION OF GATE 20,000.00 5.12 20
J ELECTRICAL WORKS 13,500.00 3.46 10
K PLASTERING 39,813.00 10.20 0
TOTAL AMOUNT 390,271.56 100 3.84 % 6.88 % 12.99 % 25.66 % 42.28 % 62.13 % 81.21 % 93.88 % 100 %