Delayed Activities
Delayed Activities
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
1 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
2 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
3 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
4 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
5 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
6 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
7 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
8 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
9 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
10 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
11 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
12 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
13 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
14 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
15 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
16 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
17 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
18 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
19 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
20 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
21 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
22 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
23 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-01
5-Jan-17
24 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
25 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
26 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
27 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
28 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
29 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
30 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
31 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
32 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
33 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
34 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
35 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
36 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
37 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
38 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
39 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
40 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
41 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
42 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
43 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
44 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
45 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
46 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
47 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-02
12-Jan-17
48 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
49 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
50 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
51 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
52 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
53 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
54 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
55 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
56 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
57 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
58 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
59 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
60 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
61 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
62 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
63 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
64 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
65 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
66 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
67 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
68 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
69 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
70 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
71 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-03
19-Jan-17
72 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
73 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
74 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
75 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
76 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
77 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
78 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
79 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
80 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
81 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
82 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
83 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
84 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
85 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
86 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
87 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
88 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
89 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
90 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
91 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
92 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
93 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
94 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
95 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-04
26-Jan-17
96 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
97 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
98 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
99 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
100 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
101 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
102 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
103 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
104 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
105 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
106 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
107 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
108 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
109 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
110 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
111 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
112 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
113 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
114 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
115 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
116 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
117 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
118 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
119 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-05
2-Feb-17
120 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
121 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
122 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
123 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
124 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
125 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
126 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
127 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
128 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
129 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
130 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
131 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
132 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
133 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
134 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
135 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
136 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
137 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
138 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
139 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
140 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
141 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
142 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
143 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-06
9-Feb-17
144 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.03%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
145 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
146 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
147 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
148 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
149 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
150 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
151 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
152 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
153 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
154 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
155 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
156 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
157 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
158 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
159 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
160 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
161 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
162 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
163 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
164 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
165 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18 0.00%
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18 0.00%
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18 0.00%
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18 0.00%
Ground floor level 23-Sep-17 13-Mar-18 0.00%
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18 0.00%
166 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18 0.00%
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18 0.00%
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18 0.00%
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98% 0.00%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
167 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.03%
Planned Weekly Progress Percentage - Cumulative 0.03%
47,126,293.00 100.00% WK-07
16-Feb-17
168 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.08%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.12%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
169 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
170 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
171 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
172 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
173 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
174 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
175 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
176 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
177 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
178 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
179 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
180 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
181 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
182 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
183 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
184 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
185 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
186 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
187 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
188 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
189 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
190 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
191 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.22%
Planned Weekly Progress Percentage - Cumulative 0.25%
47,126,293.00 100.00% WK-08
23-Feb-17
192 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.02%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.02%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.09%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.14%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
193 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
194 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
195 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
196 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
197 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
198 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
199 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
200 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
201 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
202 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
203 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
204 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
205 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
206 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
207 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
208 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
209 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
210 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
211 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
212 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
213 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
214 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
215 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.29%
Planned Weekly Progress Percentage - Cumulative 0.54%
47,126,293.00 100.00% WK-09
2-Mar-17
216 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.48%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
217 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
218 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
219 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
220 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
221 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
222 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
223 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
224 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
225 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
226 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
227 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
228 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
229 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
230 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
231 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
232 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
233 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
234 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
235 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
236 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
237 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
238 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
239 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.51%
Planned Weekly Progress Percentage - Cumulative 1.05%
47,126,293.00 100.00% WK-10
9-Mar-17
240 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.48%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.08%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
241 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
242 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
243 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
244 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
245 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
246 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
247 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
248 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
249 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
250 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
251 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
252 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
253 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
254 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
255 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
256 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
257 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
258 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
259 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
260 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
261 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
262 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
263 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.59%
Planned Weekly Progress Percentage - Cumulative 1.64%
47,126,293.00 100.00% WK-11
16-Mar-17
264 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.01%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.48%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.12%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.05%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.18%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.03%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.04%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
265 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
266 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
267 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
268 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
269 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
270 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
271 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
272 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
273 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
274 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
275 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
276 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
277 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
278 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
279 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
280 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
281 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
282 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
283 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
284 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
285 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
286 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
287 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.90%
Planned Weekly Progress Percentage - Cumulative 2.54%
47,126,293.00 100.00% WK-12
23-Mar-17
288 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.45%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.61%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.07%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
289 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
290 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
291 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
292 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
293 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
294 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
295 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
296 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
297 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
298 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
299 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
300 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
301 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
302 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
303 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
304 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
305 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
306 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
307 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
308 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
309 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
310 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
311 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.54%
Planned Weekly Progress Percentage - Cumulative 4.08%
47,126,293.00 100.00% WK-13
30-Mar-17
312 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 1.29%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.15%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.02%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.22%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
313 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
314 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
315 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
316 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
317 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
318 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
319 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
320 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
321 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
322 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
323 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
324 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
325 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
326 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
327 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
328 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
329 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
330 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
331 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
332 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
333 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
334 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
335 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 2.10%
Planned Weekly Progress Percentage - Cumulative 6.18%
47,126,293.00 100.00% WK-14
6-Apr-17
336 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.21%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 1.09%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.14%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.29%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.32%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
337 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
338 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
339 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
340 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
341 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
342 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
343 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
344 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
345 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
346 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
347 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
348 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
349 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
350 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
351 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
352 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
353 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
354 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
355 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
356 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
357 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
358 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
359 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 2.48%
Planned Weekly Progress Percentage - Cumulative 8.67%
47,126,293.00 100.00% WK-15
13-Apr-17
360 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.07%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.27%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.95%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
361 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
362 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
363 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
364 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
365 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
366 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
367 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
368 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
369 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
370 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
371 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
372 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
373 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
374 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
375 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
376 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
377 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
378 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
379 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
380 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
381 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
382 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
383 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.72%
Planned Weekly Progress Percentage - Cumulative 10.39%
47,126,293.00 100.00% WK-16
20-Apr-17
384 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.20%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.92%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.13%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
385 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.01%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
386 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
387 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
388 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
389 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
390 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
391 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
392 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
393 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
394 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
395 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
396 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
397 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
398 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
399 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
400 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
401 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
402 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
403 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
404 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
405 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
406 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
407 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.69%
Planned Weekly Progress Percentage - Cumulative 12.08%
47,126,293.00 100.00% WK-17
27-Apr-17
408 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.05%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.20%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
409 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.02%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
410 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
411 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
412 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
413 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
414 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
415 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
416 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
417 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
418 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
419 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
420 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
421 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
422 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
423 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
424 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
425 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
426 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
427 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
428 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
429 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
430 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
431 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.70%
Planned Weekly Progress Percentage - Cumulative 12.78%
47,126,293.00 100.00% WK-18
4-May-17
432 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.06%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.20%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.13%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.02%
433 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.11%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.02%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
434 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.01%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
435 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
436 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
437 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
438 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
439 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
440 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
441 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
442 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
443 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
444 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
445 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
446 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
447 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
448 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
449 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
450 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
451 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
452 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
453 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
454 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
455 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.55%
Planned Weekly Progress Percentage - Cumulative 13.33%
47,126,293.00 100.00% WK-19
11-May-17
456 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
457 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.33%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.01%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
458 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.04%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
459 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
460 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
461 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
462 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
463 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
464 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
465 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
466 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
467 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
468 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
469 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
470 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
471 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
472 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
473 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
474 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
475 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
476 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
477 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
478 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
479 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.37%
Planned Weekly Progress Percentage - Cumulative 13.70%
47,126,293.00 100.00% WK-20
18-May-17
480 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
481 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.72%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.01%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.04%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
482 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.04%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
483 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
484 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
485 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
486 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
487 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
488 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
489 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
490 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
491 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
492 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
493 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
494 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
495 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
496 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
497 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
498 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
499 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
500 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
501 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
502 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
503 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.80%
Planned Weekly Progress Percentage - Cumulative 14.50%
47,126,293.00 100.00% WK-21
25-May-17
504 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
505 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.36%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 1.24%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.02%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.07%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
506 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.01%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.01%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
507 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
508 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
509 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
510 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
511 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
512 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
513 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
514 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
515 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
516 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
517 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
518 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
519 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
520 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
521 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
522 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
523 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
524 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
525 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
526 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
527 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.72%
Planned Weekly Progress Percentage - Cumulative 16.22%
47,126,293.00 100.00% WK-22
1-Jun-17
528 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
529 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.13%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.01%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.07%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
530 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.02%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
531 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
532 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
533 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
534 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
535 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
536 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
537 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
538 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
539 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
540 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
541 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
542 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
543 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
544 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
545 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
546 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
547 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
548 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
549 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
550 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
551 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.23%
Planned Weekly Progress Percentage - Cumulative 16.45%
47,126,293.00 100.00% WK-23
8-Jun-17
552 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
553 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.23%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.05%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.16%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
554 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.01%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.03%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
555 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
556 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
557 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
558 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
559 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
560 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
561 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
562 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
563 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
564 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
565 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
566 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
567 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
568 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
569 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
570 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
571 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
572 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
573 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
574 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
575 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.48%
Planned Weekly Progress Percentage - Cumulative 16.93%
47,126,293.00 100.00% WK-24
15-Jun-17
576 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
577 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.11%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.05%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.03%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.01%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
578 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.03%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.10%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
579 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
580 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.01%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
581 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
582 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
583 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
584 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
585 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
586 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
587 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
588 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
589 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
590 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
591 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
592 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
593 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
594 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
595 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
596 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
597 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
598 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
599 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.35%
Planned Weekly Progress Percentage - Cumulative 17.28%
47,126,293.00 100.00% WK-25
22-Jun-17
600 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
601 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.04%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.01%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.02%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.05%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
602 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.10%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.06%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
603 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
604 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.03%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
605 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.01%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
606 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
607 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
608 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
609 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
610 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
611 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
612 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
613 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
614 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
615 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
616 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
617 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
618 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
619 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
620 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
621 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
622 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
623 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.31%
Planned Weekly Progress Percentage - Cumulative 17.59%
47,126,293.00 100.00% WK-26
29-Jun-17
624 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00% 0.00%
625 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.03% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.07% 0.05%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00% 0.16%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00% 0.01%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00% 0.01%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00% 0.00%
626 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.17% 0.06%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00% 0.36%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00% 0.04%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00% 0.02%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00% 0.00%
627 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00% 0.00%
628 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.03% 0.01%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00% 0.01%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00% 0.00%
629 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00% 0.00%
630 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00% 0.00%
631 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00% 0.00%
632 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00% 0.00%
633 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
634 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00% 0.00%
635 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00% 0.00%
636 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.01% 0.01%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.01% 0.01%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00% 0.00%
637 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00% 0.00%
Third floor level 18-Dec-17 30-May-18
638 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00% 0.00%
Third floor level 8-Feb-18 6-Aug-18
639 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00% 0.00%
640 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00% 0.00%
641 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00% 0.00%
Zone 3 28-Nov-17 5-Aug-18
642 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
643 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00% 0.00%
644 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00% 0.00%
645 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00% 0.00%
First floor level 22-Nov-17 15-May-18
646 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00% 0.00%
647 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.34% 0.76%
Planned Weekly Progress Percentage - Cumulative 17.92% 18.68%
47,126,293.00 100.00% WK-27 WK-28
6-Jul-17 13-Jul-17
648 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00% 0.00%
649 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.05% 0.03%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.02% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00% 0.02%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00% 0.00%
650 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00% 0.09%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00% 0.02%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.12% 0.06%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.04% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.01% 0.01%
651 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00% 0.05%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00% 0.08%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00% 0.00%
652 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.01% 0.01%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00% 0.03%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00% 0.00%
653 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00% 0.00%
654 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00% 0.00%
655 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00% 0.00%
656 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00% 0.00%
657 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
658 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00% 0.00%
659 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00% 0.00%
660 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.01% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.01% 0.01%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00% 0.00%
661 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00% 0.00%
Third floor level 18-Dec-17 30-May-18
662 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00% 0.00%
Third floor level 8-Feb-18 6-Aug-18
663 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00% 0.00%
664 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00% 0.00%
665 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00% 0.00%
Zone 3 28-Nov-17 5-Aug-18
666 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
667 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00% 0.00%
668 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00% 0.00%
669 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00% 0.00%
First floor level 22-Nov-17 15-May-18
670 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00% 0.00%
671 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.31% 0.43%
Planned Weekly Progress Percentage - Cumulative 18.99% 19.43%
47,126,293.00 100.00% WK-29 WK-30
20-Jul-17 27-Jul-17
672 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
673 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
674 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.10%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.08%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
675 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.13%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.03%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
676 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.03%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.08%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
677 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
678 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
679 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
680 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
681 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
682 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
683 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
684 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
685 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.01%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
686 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
687 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
688 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
689 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
690 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
691 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
692 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
693 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
694 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
695 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.50%
Planned Weekly Progress Percentage - Cumulative 19.93%
47,126,293.00 100.00% WK-31
3-Aug-17
696 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
697 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.02%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
698 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.08%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.04%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
699 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.17%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
700 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.09%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.02%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
701 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
702 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
703 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
704 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
705 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
706 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
707 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
708 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.01%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
709 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.01%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
710 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
711 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
712 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
713 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
714 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
715 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
716 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
717 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
718 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
719 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.50%
Planned Weekly Progress Percentage - Cumulative 20.43%
47,126,293.00 100.00% WK-32
10-Aug-17
720 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
721 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.01%
722 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.01%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.05%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.02%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
723 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.01%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.08%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.36%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.02%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
724 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.13%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
725 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.05%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.01%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
726 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
727 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
728 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.09%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
729 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
730 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
731 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
732 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.01%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.01%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
733 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.01%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
734 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
735 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
736 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
737 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
738 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
739 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
740 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
741 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
742 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
743 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.92%
Planned Weekly Progress Percentage - Cumulative 21.35%
47,126,293.00 100.00% WK-33
17-Aug-17
744 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
745 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
746 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.01%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.03%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
747 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.05%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.01%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.12%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
748 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.09%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.30%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
749 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
750 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
751 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
752 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.10%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
753 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
754 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
755 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
756 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.01%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
757 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
758 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
759 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
760 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
761 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
762 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
763 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
764 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
765 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
766 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
767 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.88%
Planned Weekly Progress Percentage - Cumulative 22.23%
47,126,293.00 100.00% WK-34
24-Aug-17
768 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
769 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
770 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.01%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.04%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.01%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.01%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
771 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.02%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.05%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.08%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.05%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
772 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.10%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.05%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
773 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
774 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.01%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
775 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
776 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.10%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
777 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
778 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
779 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
780 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.01%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
781 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
782 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
783 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
784 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
785 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
786 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
787 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
788 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.01%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
789 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
790 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
791 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.72%
Planned Weekly Progress Percentage - Cumulative 22.95%
47,126,293.00 100.00% WK-35
31-Aug-17
792 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
793 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
794 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.02%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
795 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.15%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
796 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.08%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.02%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.04%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.02%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
797 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.01%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
798 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
799 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
800 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.10%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
801 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
802 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
803 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
804 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.01%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
805 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
806 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
807 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
808 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
809 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
810 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
811 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
812 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
813 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
814 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
815 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.69%
Planned Weekly Progress Percentage - Cumulative 23.64%
47,126,293.00 100.00% WK-36
7-Sep-17
816 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
817 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
818 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.01%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.01%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.01%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
819 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.17%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
820 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.11%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
821 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
822 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
823 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
824 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.03%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.05%
825 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
826 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
827 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
828 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.03%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
829 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.05%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
830 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.01%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
831 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
832 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
833 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
834 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
835 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
836 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
837 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
838 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
839 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.76%
Planned Weekly Progress Percentage - Cumulative 24.39%
47,126,293.00 100.00% WK-37
14-Sep-17
840 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
841 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
842 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
843 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.11%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.36%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
844 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.04%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.09%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
845 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
846 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.06%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
847 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
848 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.08%
849 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.02%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
850 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.01%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
851 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
852 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.02%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
853 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.11%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
854 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.01%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
855 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
856 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
857 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.04%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
858 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
859 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
860 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
861 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
862 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
863 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.24%
Planned Weekly Progress Percentage - Cumulative 25.63%
47,126,293.00 100.00% WK-38
21-Sep-17
864 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
865 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
866 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
867 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.06%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.12%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
868 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.13%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
869 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.09%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.03%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
870 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
871 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
872 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.03%
873 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.02%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
874 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.01%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
875 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
876 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
877 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.02%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
878 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.01%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
879 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
880 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.01%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
881 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.04%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
882 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
883 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
884 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
885 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
886 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
887 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.07%
Planned Weekly Progress Percentage - Cumulative 26.70%
47,126,293.00 100.00% WK-39
28-Sep-17
888 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
889 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
890 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
891 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.03%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.05%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.10%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.01%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
892 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.02%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.30%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.05%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.03%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
893 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%
894 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
895 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
896 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
897 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.01%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.07%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
898 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.01%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
899 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
900 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.01%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
901 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
902 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
903 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
904 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.03%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
905 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.04%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.02%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
906 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
907 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
908 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
909 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
910 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
911 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.48%
Planned Weekly Progress Percentage - Cumulative 28.17%
47,126,293.00 100.00% WK-40
5-Oct-17
912 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
913 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
914 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
915 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.04%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
916 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.10%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.03%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.02%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
917 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.03%
918 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
919 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
920 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
921 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.10%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.01%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
922 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.01%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
923 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
924 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.02%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
925 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
926 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
927 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
928 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.03%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
929 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.01%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.03%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.06%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
930 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.01%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
931 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
932 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
933 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
934 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
935 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.20%
Planned Weekly Progress Percentage - Cumulative 29.38%
47,126,293.00 100.00% WK-41
12-Oct-17
936 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
937 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
938 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
939 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.01%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.04%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
940 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.03%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.01%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.04%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.08%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
941 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
942 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
943 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
944 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
945 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.05%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.02%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.03%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.02%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
946 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.01%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
947 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
948 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.02%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
949 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
950 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
951 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
952 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.01%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.05%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
953 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.03%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.06%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.01%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
954 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.01%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
955 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
956 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
957 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
958 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.02%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
959 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.29%
Planned Weekly Progress Percentage - Cumulative 30.67%
47,126,293.00 100.00% WK-42
19-Oct-17
960 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
961 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
962 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
963 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.04%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.05%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
964 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.09%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.02%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
965 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.02%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
966 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
967 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
968 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.01%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
969 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.11%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.10%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.02%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.02%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.02%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
970 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.03%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
971 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
972 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
973 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
974 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
975 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
976 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.07%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.01%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
977 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.06%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.02%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
978 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.01%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
979 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
980 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
981 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
982 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.01%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.07%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.01%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
983 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.59%
Planned Weekly Progress Percentage - Cumulative 32.26%
47,126,293.00 100.00% WK-43
26-Oct-17
984 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
985 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
986 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
987 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.03%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.05%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.03%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
988 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.13%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
989 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.01%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.05%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.03%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.03%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
990 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.02%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
991 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
992 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
993 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.05%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.10%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.10%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
994 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.06%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.02%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
995 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
996 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
997 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.01%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
998 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.11%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
999 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
1000 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.02%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.05%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.01%
1001 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.02%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.02%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
1002 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
1003 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
1004 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
1005 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.03%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
1006 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
1007 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.68%
Planned Weekly Progress Percentage - Cumulative 33.93%
47,126,293.00 100.00% WK-44
2-Nov-17
1008 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
1009 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
1010 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
1011 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.01%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.01%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.02%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.04%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
1012 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.09%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.30%
1013 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.06%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.01%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
1014 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.01%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
1015 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
1016 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
1017 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.10%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.05%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.01%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.05%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
1018 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.06%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.03%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
1019 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
1020 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
1021 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
1022 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.11%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
1023 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.01%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
1024 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.04%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.02%
1025 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.01%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.05%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
1026 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
1027 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
1028 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
1029 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
1030 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
1031 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 2.00%
Planned Weekly Progress Percentage - Cumulative 35.93%
47,126,293.00 100.00% WK-45
9-Nov-17
1032 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
1033 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
1034 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
1035 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.01%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.02%
1036 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.02%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.05%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
1037 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.10%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.06%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.03%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
1038 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.02%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.01%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
1039 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
1040 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
1041 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.03%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.03%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.02%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.10%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
1042 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.01%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.05%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
1043 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
1044 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%
1045 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
1046 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
1047 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.01%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
1048 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.02%
1049 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.07%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
1050 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
1051 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
1052 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
1053 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.01%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
1054 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.01%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
1055 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.73%
Planned Weekly Progress Percentage - Cumulative 37.66%
47,126,293.00 100.00% WK-46
16-Nov-17
1056 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
1057 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
1058 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
1059 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
1060 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.02%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.04%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
1061 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.08%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.01%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.01%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.08%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
1062 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.04%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.01%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
1063 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
1064 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
1065 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.05%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.01%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
1066 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.09%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
1067 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
1068 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.01%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.01%
1069 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
1070 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.01%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
1071 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.01%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
1072 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.01%
1073 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.02%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.06%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.05%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
1074 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.02%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
1075 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
1076 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
1077 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.02%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
1078 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.01%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.01%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
1079 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.69%
Planned Weekly Progress Percentage - Cumulative 39.35%
47,126,293.00 100.00% WK-47
23-Nov-17
1080 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
1081 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
1082 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
1083 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
1084 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
1085 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.03%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.01%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.08%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
1086 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.04%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.06%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.05%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
1087 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
1088 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%
1089 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.03%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.03%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.04%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.02%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17
1090 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.03%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.08%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.01%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%
1091 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.01%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%
1092 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.01%
1093 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.01%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18
1094 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.03%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18
1095 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.01%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.01%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%
1096 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%
1097 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.02%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.05%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18
1098 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.03%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.03%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.01%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%
1099 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.13%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%
1100 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%
1101 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.02%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.03%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18
1102 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.04%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.01%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%
1103 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.75%
Planned Weekly Progress Percentage - Cumulative 41.10%
47,126,293.00 100.00% WK-48
30-Nov-17
1104 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%
1105 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%
1106 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%
1107 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%
1108 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%
1109 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.01%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.02%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.01%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.08%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%
1110 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.04%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.06%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%
1111 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.03%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.01%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%
1112 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties