WK-01

Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

1 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

2 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

3 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

4 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

5 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

6 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

7 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

8 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

9 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

10 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

11 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

12 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

13 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

14 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

15 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

16 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

17 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

18 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

19 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

20 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

21 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

22 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

23 of 2424
WK-01
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-01
5-Jan-17

24 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

25 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

26 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

27 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

28 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

29 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

30 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

31 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

32 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

33 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

34 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

35 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

36 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

37 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

38 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

39 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

40 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

41 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

42 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

43 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

44 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

45 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

46 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

47 of 2424
WK-02
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-02
12-Jan-17

48 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

49 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

50 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

51 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

52 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

53 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

54 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

55 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

56 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

57 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

58 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

59 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

60 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

61 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

62 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

63 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

64 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

65 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

66 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

67 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

68 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

69 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

70 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

71 of 2424
WK-03
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-03
19-Jan-17

72 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

73 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

74 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

75 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

76 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

77 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

78 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

79 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

80 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

81 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

82 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

83 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

84 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

85 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

86 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

87 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

88 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

89 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

90 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

91 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

92 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

93 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

94 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

95 of 2424
WK-04
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Jan-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-04
26-Jan-17

96 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

97 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

98 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

99 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

100 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

101 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

102 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

103 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

104 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

105 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

106 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

107 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

108 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

109 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

110 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

111 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

112 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

113 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

114 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

115 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

116 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

117 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

118 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

119 of 2424
WK-05
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-05
2-Feb-17

120 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

121 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

122 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

123 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

124 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

125 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

126 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

127 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

128 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

129 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

130 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

131 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

132 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

133 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

134 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

135 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

136 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

137 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

138 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

139 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

140 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

141 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

142 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

143 of 2424
WK-06
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.00%
Planned Weekly Progress Percentage - Cumulative 0.00%
47,126,293.00 100.00% WK-06
9-Feb-17

144 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.03%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

145 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

146 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

147 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

148 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

149 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

150 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

151 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

152 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

153 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

154 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

155 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

156 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

157 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

158 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

159 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

160 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

161 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

162 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

163 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

164 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

165 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18 0.00%
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18 0.00%
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18 0.00%
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18 0.00%
Ground floor level 23-Sep-17 13-Mar-18 0.00%
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18 0.00%

166 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18 0.00%
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18 0.00%
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18 0.00%
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98% 0.00%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

167 of 2424
WK-07
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.03%
Planned Weekly Progress Percentage - Cumulative 0.03%
47,126,293.00 100.00% WK-07
16-Feb-17

168 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.08%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.12%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

169 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

170 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

171 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

172 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

173 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

174 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

175 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

176 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

177 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

178 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

179 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

180 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

181 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

182 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

183 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

184 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

185 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

186 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

187 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

188 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

189 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

190 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

191 of 2424
WK-08
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Feb-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.22%
Planned Weekly Progress Percentage - Cumulative 0.25%
47,126,293.00 100.00% WK-08
23-Feb-17

192 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.02%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.02%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.09%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.14%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

193 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

194 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

195 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

196 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

197 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

198 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

199 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

200 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

201 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

202 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

203 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

204 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

205 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

206 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

207 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

208 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

209 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

210 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

211 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

212 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

213 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

214 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

215 of 2424
WK-09
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.29%
Planned Weekly Progress Percentage - Cumulative 0.54%
47,126,293.00 100.00% WK-09
2-Mar-17

216 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.48%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

217 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

218 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

219 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

220 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

221 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

222 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

223 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

224 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

225 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

226 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

227 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

228 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

229 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

230 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

231 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

232 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

233 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

234 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

235 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

236 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

237 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

238 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

239 of 2424
WK-10
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.51%
Planned Weekly Progress Percentage - Cumulative 1.05%
47,126,293.00 100.00% WK-10
9-Mar-17

240 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.02%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.48%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.08%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

241 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

242 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

243 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

244 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

245 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

246 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

247 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

248 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

249 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

250 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

251 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

252 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

253 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

254 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

255 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

256 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

257 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

258 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

259 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

260 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

261 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

262 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

263 of 2424
WK-11
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.59%
Planned Weekly Progress Percentage - Cumulative 1.64%
47,126,293.00 100.00% WK-11
16-Mar-17

264 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.01%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.48%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.12%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.05%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.18%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.03%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.04%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

265 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

266 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

267 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

268 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

269 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

270 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

271 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

272 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

273 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

274 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

275 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

276 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

277 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

278 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

279 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

280 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

281 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

282 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

283 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

284 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

285 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

286 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

287 of 2424
WK-12
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.90%
Planned Weekly Progress Percentage - Cumulative 2.54%
47,126,293.00 100.00% WK-12
23-Mar-17

288 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.45%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.61%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.07%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

289 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

290 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

291 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

292 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

293 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

294 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

295 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

296 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

297 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

298 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

299 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

300 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

301 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

302 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

303 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

304 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

305 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

306 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

307 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

308 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

309 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

310 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

311 of 2424
WK-13
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Mar-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.54%
Planned Weekly Progress Percentage - Cumulative 4.08%
47,126,293.00 100.00% WK-13
30-Mar-17

312 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 1.29%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.15%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.02%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.22%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

313 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

314 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

315 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

316 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

317 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

318 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

319 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

320 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

321 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

322 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

323 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

324 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

325 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

326 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

327 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

328 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

329 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

330 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

331 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

332 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

333 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

334 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

335 of 2424
WK-14
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 2.10%
Planned Weekly Progress Percentage - Cumulative 6.18%
47,126,293.00 100.00% WK-14
6-Apr-17

336 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.21%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 1.09%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.14%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.29%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.32%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

337 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

338 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

339 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

340 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

341 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

342 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

343 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

344 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

345 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

346 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

347 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

348 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

349 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

350 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

351 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

352 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

353 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

354 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

355 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

356 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

357 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

358 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

359 of 2424
WK-15
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
13-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 2.48%
Planned Weekly Progress Percentage - Cumulative 8.67%
47,126,293.00 100.00% WK-15
13-Apr-17

360 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.07%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.27%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.95%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

361 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

362 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

363 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

364 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

365 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

366 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

367 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

368 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

369 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

370 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

371 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

372 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

373 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

374 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

375 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

376 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

377 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

378 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

379 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

380 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

381 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

382 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

383 of 2424
WK-16
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.72%
Planned Weekly Progress Percentage - Cumulative 10.39%
47,126,293.00 100.00% WK-16
20-Apr-17

384 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.20%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.92%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.13%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

385 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.01%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

386 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

387 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

388 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

389 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

390 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

391 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

392 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

393 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

394 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

395 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

396 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

397 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

398 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

399 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

400 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

401 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

402 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

403 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

404 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

405 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

406 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

407 of 2424
WK-17
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
27-Apr-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.69%
Planned Weekly Progress Percentage - Cumulative 12.08%
47,126,293.00 100.00% WK-17
27-Apr-17

408 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.41%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.05%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.20%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.02%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

409 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.02%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

410 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

411 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

412 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

413 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

414 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

415 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

416 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

417 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

418 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

419 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

420 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

421 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

422 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

423 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

424 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

425 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

426 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

427 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

428 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

429 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

430 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

431 of 2424
WK-18
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
4-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.70%
Planned Weekly Progress Percentage - Cumulative 12.78%
47,126,293.00 100.00% WK-18
4-May-17

432 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.06%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.20%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.13%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.02%

433 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.11%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.02%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

434 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.01%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

435 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

436 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

437 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

438 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

439 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

440 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

441 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

442 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

443 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

444 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

445 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

446 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

447 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

448 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

449 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

450 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

451 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

452 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

453 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

454 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

455 of 2424
WK-19
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
11-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.55%
Planned Weekly Progress Percentage - Cumulative 13.33%
47,126,293.00 100.00% WK-19
11-May-17

456 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

457 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.33%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.01%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

458 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.04%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

459 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

460 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

461 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

462 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

463 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

464 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

465 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

466 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

467 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

468 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

469 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

470 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

471 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

472 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

473 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

474 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

475 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

476 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

477 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

478 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

479 of 2424
WK-20
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
18-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.37%
Planned Weekly Progress Percentage - Cumulative 13.70%
47,126,293.00 100.00% WK-20
18-May-17

480 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

481 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.72%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.01%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.04%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

482 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.04%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

483 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

484 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

485 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

486 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

487 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

488 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

489 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

490 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

491 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

492 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

493 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

494 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

495 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

496 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

497 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

498 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

499 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

500 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

501 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

502 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

503 of 2424
WK-21
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
25-May-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.80%
Planned Weekly Progress Percentage - Cumulative 14.50%
47,126,293.00 100.00% WK-21
25-May-17

504 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

505 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.36%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 1.24%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.02%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.07%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

506 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.01%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.01%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

507 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

508 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

509 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

510 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

511 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

512 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

513 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

514 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

515 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

516 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

517 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

518 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

519 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

520 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

521 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

522 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

523 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

524 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

525 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

526 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

527 of 2424
WK-22
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
1-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.72%
Planned Weekly Progress Percentage - Cumulative 16.22%
47,126,293.00 100.00% WK-22
1-Jun-17

528 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

529 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.13%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.01%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.07%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

530 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.02%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

531 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

532 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

533 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

534 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

535 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

536 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

537 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

538 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

539 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

540 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

541 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

542 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

543 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

544 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

545 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

546 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

547 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

548 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

549 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

550 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

551 of 2424
WK-23
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
8-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.23%
Planned Weekly Progress Percentage - Cumulative 16.45%
47,126,293.00 100.00% WK-23
8-Jun-17

552 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

553 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.23%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.05%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.16%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

554 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.01%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.03%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

555 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

556 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

557 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

558 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

559 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

560 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

561 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

562 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

563 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

564 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

565 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

566 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

567 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

568 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

569 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

570 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

571 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

572 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

573 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

574 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

575 of 2424
WK-24
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
15-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.48%
Planned Weekly Progress Percentage - Cumulative 16.93%
47,126,293.00 100.00% WK-24
15-Jun-17

576 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

577 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.11%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.05%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.03%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.01%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

578 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.03%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.10%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

579 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

580 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.01%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

581 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

582 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

583 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

584 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

585 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

586 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

587 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

588 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

589 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

590 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

591 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

592 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

593 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

594 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

595 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

596 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

597 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

598 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

599 of 2424
WK-25
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
22-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.35%
Planned Weekly Progress Percentage - Cumulative 17.28%
47,126,293.00 100.00% WK-25
22-Jun-17

600 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

601 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.04%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.01%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.02%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.05%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

602 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.10%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.06%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

603 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

604 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.03%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

605 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.01%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

606 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

607 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

608 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

609 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

610 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

611 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

612 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

613 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

614 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

615 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

616 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

617 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

618 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

619 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

620 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

621 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

622 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

623 of 2424
WK-26
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
29-Jun-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.31%
Planned Weekly Progress Percentage - Cumulative 17.59%
47,126,293.00 100.00% WK-26
29-Jun-17

624 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00% 0.00%

625 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.03% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.07% 0.05%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00% 0.16%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00% 0.01%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00% 0.01%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00% 0.00%

626 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.17% 0.06%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00% 0.36%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00% 0.04%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00% 0.02%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00% 0.00%

627 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00% 0.00%

628 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.03% 0.01%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00% 0.01%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00% 0.00%

629 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00% 0.00%

630 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00% 0.00%

631 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00% 0.00%

632 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00% 0.00%

633 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

634 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00% 0.00%

635 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00% 0.00%

636 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.01% 0.01%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.01% 0.01%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00% 0.00%

637 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00% 0.00%
Third floor level 18-Dec-17 30-May-18

638 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00% 0.00%
Third floor level 8-Feb-18 6-Aug-18

639 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00% 0.00%

640 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00% 0.00%

641 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00% 0.00%
Zone 3 28-Nov-17 5-Aug-18

642 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

643 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00% 0.00%

644 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00% 0.00%

645 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00% 0.00%
First floor level 22-Nov-17 15-May-18

646 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00% 0.00%

647 of 2424
WK-27 WK-28
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
6-Jul-17 13-Jul-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.34% 0.76%
Planned Weekly Progress Percentage - Cumulative 17.92% 18.68%
47,126,293.00 100.00% WK-27 WK-28
6-Jul-17 13-Jul-17

648 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00% 0.00%

649 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.05% 0.03%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.02% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00% 0.02%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00% 0.00%

650 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00% 0.09%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00% 0.02%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.12% 0.06%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.04% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.01% 0.01%

651 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00% 0.05%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00% 0.08%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00% 0.00%

652 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.01% 0.01%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00% 0.03%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00% 0.00%

653 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00% 0.00%

654 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00% 0.00%

655 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00% 0.00%

656 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00% 0.00%

657 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

658 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00% 0.00%

659 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00% 0.00%

660 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.01% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.01% 0.01%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00% 0.00%

661 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00% 0.00%
Third floor level 18-Dec-17 30-May-18

662 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00% 0.00%
Third floor level 8-Feb-18 6-Aug-18

663 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00% 0.00%

664 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00% 0.00%

665 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00% 0.00%
Zone 3 28-Nov-17 5-Aug-18

666 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

667 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00% 0.00%

668 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00% 0.00%

669 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00% 0.00%
First floor level 22-Nov-17 15-May-18

670 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00% 0.00%

671 of 2424
WK-29 WK-30
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
20-Jul-17 27-Jul-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.31% 0.43%
Planned Weekly Progress Percentage - Cumulative 18.99% 19.43%
47,126,293.00 100.00% WK-29 WK-30
20-Jul-17 27-Jul-17

672 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

673 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

674 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.10%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.08%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

675 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.13%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.03%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

676 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.03%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.08%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

677 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

678 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

679 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

680 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

681 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

682 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

683 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

684 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

685 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.01%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

686 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

687 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

688 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

689 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

690 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

691 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

692 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

693 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

694 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

695 of 2424
WK-31
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
3-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.50%
Planned Weekly Progress Percentage - Cumulative 19.93%
47,126,293.00 100.00% WK-31
3-Aug-17

696 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

697 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.02%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

698 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.08%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.04%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

699 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.17%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

700 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.09%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.02%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

701 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

702 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

703 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

704 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

705 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

706 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

707 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

708 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.01%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

709 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.01%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

710 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

711 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

712 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

713 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

714 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

715 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

716 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

717 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

718 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

719 of 2424
WK-32
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
10-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.50%
Planned Weekly Progress Percentage - Cumulative 20.43%
47,126,293.00 100.00% WK-32
10-Aug-17

720 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

721 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.01%

722 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.01%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.05%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.02%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

723 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.01%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.08%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.36%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.02%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

724 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.13%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

725 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.05%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.01%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

726 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

727 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

728 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.09%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

729 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

730 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

731 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

732 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.01%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.01%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

733 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.01%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

734 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

735 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

736 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

737 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

738 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

739 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

740 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

741 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

742 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

743 of 2424
WK-33
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
17-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.92%
Planned Weekly Progress Percentage - Cumulative 21.35%
47,126,293.00 100.00% WK-33
17-Aug-17

744 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

745 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

746 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.01%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.03%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

747 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.05%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.01%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.12%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

748 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.09%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.30%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

749 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

750 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

751 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

752 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.10%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

753 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

754 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

755 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

756 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.01%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

757 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.01%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

758 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

759 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

760 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

761 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

762 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

763 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

764 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

765 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

766 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

767 of 2424
WK-34
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
24-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.88%
Planned Weekly Progress Percentage - Cumulative 22.23%
47,126,293.00 100.00% WK-34
24-Aug-17

768 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

769 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

770 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.01%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.04%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.01%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.01%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

771 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.02%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.05%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.08%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.05%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

772 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.10%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.05%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

773 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.02%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

774 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.01%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

775 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

776 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.10%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

777 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

778 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

779 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

780 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.01%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

781 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

782 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

783 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

784 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

785 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

786 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

787 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

788 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.01%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

789 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

790 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

791 of 2424
WK-35
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
31-Aug-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.72%
Planned Weekly Progress Percentage - Cumulative 22.95%
47,126,293.00 100.00% WK-35
31-Aug-17

792 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

793 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

794 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.02%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

795 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.15%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

796 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.08%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.02%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.04%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.02%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

797 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.01%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

798 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

799 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

800 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.10%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

801 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

802 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

803 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

804 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.01%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.01%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.01%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

805 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

806 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

807 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

808 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

809 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

810 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

811 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

812 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

813 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

814 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

815 of 2424
WK-36
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.69%
Planned Weekly Progress Percentage - Cumulative 23.64%
47,126,293.00 100.00% WK-36
7-Sep-17

816 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

817 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

818 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.01%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.01%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.01%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

819 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.17%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

820 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.11%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

821 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

822 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

823 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

824 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.03%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.05%

825 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

826 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

827 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

828 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.03%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

829 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.05%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

830 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.01%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

831 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

832 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

833 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

834 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

835 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

836 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

837 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

838 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

839 of 2424
WK-37
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
14-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 0.76%
Planned Weekly Progress Percentage - Cumulative 24.39%
47,126,293.00 100.00% WK-37
14-Sep-17

840 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

841 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

842 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

843 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.11%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.36%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

844 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.04%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.09%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

845 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

846 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.06%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

847 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

848 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.08%

849 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.02%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

850 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.01%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

851 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

852 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.02%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

853 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.11%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

854 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.01%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

855 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

856 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

857 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.04%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

858 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

859 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

860 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

861 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.00%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.00%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

862 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

863 of 2424
WK-38
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
21-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.24%
Planned Weekly Progress Percentage - Cumulative 25.63%
47,126,293.00 100.00% WK-38
21-Sep-17

864 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

865 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

866 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

867 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.06%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.12%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

868 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.13%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

869 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.09%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.03%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.00%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

870 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

871 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

872 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.03%

873 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.02%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

874 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.01%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

875 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

876 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

877 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.02%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

878 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.01%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

879 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

880 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.01%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

881 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.04%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

882 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

883 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

884 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

885 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

886 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

887 of 2424
WK-39
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
28-Sep-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.07%
Planned Weekly Progress Percentage - Cumulative 26.70%
47,126,293.00 100.00% WK-39
28-Sep-17

888 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

889 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

890 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

891 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.03%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.05%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.10%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.01%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

892 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.02%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.30%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.05%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.03%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

893 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.00%

894 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.01%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

895 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

896 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

897 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.01%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.07%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

898 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.01%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

899 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

900 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.01%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

901 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

902 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.01%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

903 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

904 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.01%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.03%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

905 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.04%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.02%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

906 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

907 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

908 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.00%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

909 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

910 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

911 of 2424
WK-40
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
5-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.48%
Planned Weekly Progress Percentage - Cumulative 28.17%
47,126,293.00 100.00% WK-40
5-Oct-17

912 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

913 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

914 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

915 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.04%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

916 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.10%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.03%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.02%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

917 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.03%

918 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

919 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

920 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

921 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.10%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.01%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

922 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.01%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

923 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

924 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.02%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

925 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

926 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

927 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

928 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.03%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

929 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.01%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.03%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.06%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

930 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.01%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

931 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

932 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

933 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

934 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

935 of 2424
WK-41
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
12-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.20%
Planned Weekly Progress Percentage - Cumulative 29.38%
47,126,293.00 100.00% WK-41
12-Oct-17

936 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

937 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

938 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

939 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.01%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.04%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

940 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.03%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.01%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.04%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.08%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

941 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.03%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

942 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

943 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.00%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.00%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

944 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.00%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

945 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.05%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.02%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.03%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.02%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

946 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.01%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

947 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

948 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.02%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

949 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

950 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

951 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

952 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.01%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.05%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

953 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.03%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.06%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.01%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

954 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.01%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

955 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

956 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

957 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

958 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.02%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.02%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.00%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

959 of 2424
WK-42
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
19-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.29%
Planned Weekly Progress Percentage - Cumulative 30.67%
47,126,293.00 100.00% WK-42
19-Oct-17

960 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

961 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

962 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

963 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.04%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.05%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

964 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.09%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.02%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

965 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.08%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.10%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.06%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.02%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

966 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.00%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

967 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.00%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

968 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.01%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

969 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.11%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.10%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.02%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.02%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.02%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

970 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.03%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

971 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

972 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.01%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.01%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

973 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.00%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

974 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

975 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

976 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.07%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.01%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

977 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.06%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.02%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

978 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.01%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

979 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

980 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.04%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

981 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.00%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

982 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.01%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.07%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.01%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

983 of 2424
WK-43
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
26-Oct-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.59%
Planned Weekly Progress Percentage - Cumulative 32.26%
47,126,293.00 100.00% WK-43
26-Oct-17

984 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

985 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

986 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

987 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.03%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.05%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.03%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

988 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.13%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

989 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.01%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.05%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.03%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.03%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.00%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

990 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.02%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

991 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

992 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

993 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.05%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.10%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.10%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

994 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.06%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.02%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

995 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

996 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

997 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.00%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.00%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.01%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.01%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.01%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.00%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

998 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.11%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.00%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.00%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

999 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

1000 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.02%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.05%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.01%

1001 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.02%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.02%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

1002 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

1003 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.00%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

1004 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

1005 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.03%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

1006 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.00%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

1007 of 2424
WK-44
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
2-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.68%
Planned Weekly Progress Percentage - Cumulative 33.93%
47,126,293.00 100.00% WK-44
2-Nov-17

1008 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

1009 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

1010 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

1011 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.01%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.01%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.02%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.04%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

1012 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.09%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.30%

1013 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.06%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.01%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.00%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

1014 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.00%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.01%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.00%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

1015 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

1016 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

1017 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.10%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.00%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.05%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.01%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.05%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

1018 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.06%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.03%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.00%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

1019 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

1020 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

1021 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

1022 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.11%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

1023 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.01%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

1024 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.04%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.02%

1025 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.01%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.05%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

1026 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

1027 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

1028 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

1029 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.00%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

1030 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.01%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.00%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

1031 of 2424
WK-45
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
9-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 2.00%
Planned Weekly Progress Percentage - Cumulative 35.93%
47,126,293.00 100.00% WK-45
9-Nov-17

1032 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

1033 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

1034 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

1035 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.01%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.02%

1036 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.02%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.05%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

1037 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.10%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.00%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.06%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.00%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.03%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

1038 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.02%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.01%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

1039 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

1040 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

1041 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.03%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.03%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.02%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.00%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.10%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

1042 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.01%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.05%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

1043 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

1044 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.04%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.00%

1045 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

1046 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.00%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

1047 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.01%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

1048 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.02%

1049 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.00%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.07%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.00%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

1050 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.00%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

1051 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

1052 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

1053 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.01%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

1054 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.00%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.01%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

1055 of 2424
WK-46
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
16-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.73%
Planned Weekly Progress Percentage - Cumulative 37.66%
47,126,293.00 100.00% WK-46
16-Nov-17

1056 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

1057 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

1058 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

1059 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

1060 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.02%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.04%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

1061 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.08%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.01%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.01%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.08%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

1062 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.04%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.13%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.01%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.00%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.02%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

1063 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.01%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

1064 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

1065 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.05%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.00%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.01%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.00%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

1066 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.00%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.09%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.00%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

1067 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.00%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

1068 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.01%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.01%

1069 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.00%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

1070 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.01%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

1071 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.01%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.00%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.00%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

1072 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.01%

1073 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.02%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.06%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.05%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

1074 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.00%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.02%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.00%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

1075 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.00%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

1076 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

1077 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.02%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.05%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

1078 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.01%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.01%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

1079 of 2424
WK-47
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
23-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.69%
Planned Weekly Progress Percentage - Cumulative 39.35%
47,126,293.00 100.00% WK-47
23-Nov-17

1080 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

1081 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

1082 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

1083 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

1084 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

1085 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.03%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.00%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.01%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.08%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

1086 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.04%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.06%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.01%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.05%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

1087 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.00%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.00%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

1088 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties 23-May-18 13-Jun-18 80,468.00 0.17% 0.00%
Third floor level 15-Jan-18 4-Aug-18
CFWZ3TF-01 Masonry works 15-Jan-18 17-Apr-18 161,452.00 0.34% 0.00%
CFWZ3TF-02 Waterproofing at wet areas 8-Mar-18 29-Apr-18 2,485.00 0.01% 0.00%
CFWZ3TF-03 Finishes 9-Apr-18 10-Jul-18 446,312.00 0.95% 0.00%
CFWZ3TF-04 Metal works 26-May-18 28-Jun-18 37,089.00 0.08% 0.00%
CFWZ3TF-05 Doors & windows installation 28-May-18 7-Jul-18 241,280.00 0.51% 0.00%
CFWZ3TF-06 Specialties 11-Jul-18 4-Aug-18 64,374.00 0.14% 0.00%
Roof deck level 29-Jul-18 20-Sep-18
CFWZ3RD-01 Masonry works 29-Jul-18 21-Aug-18 10,763.00 0.02% 0.00%
CFWZ3RD-02 Roof Waterproofing 20-Aug-18 26-Aug-18 108,835.00 0.23% 0.00%
CFWZ3RD-03 Finishes 27-Aug-18 20-Sep-18 178,525.00 0.38% 0.00%
CFWZ3RD-04 Metal works 8-Sep-18 18-Sep-18 7,418.00 0.02% 0.00%
CFWZ3RD-06 Doors installation 15-Sep-18 18-Sep-18 60,320.00 0.13% 0.00%
Upperroof deck level 27-Aug-18 5-Sep-18
CFWZ3UD-01 Roof Waterproofing 27-Aug-18 30-Aug-18 12,093.00 0.03% 0.00%
CFWZ3UD-02 Finishes 1-Sep-18 5-Sep-18 44,631.00 0.09% 0.00%
Electrical Works 13-Aug-17 22-May-18 4,863,214.02 10.32%
Zone 1 13-Aug-17 14-Dec-17
Ground floor level 13-Aug-17 12-Nov-17
CEWZ1GF-01 Panel Board 13-Aug-17 10-Sep-17 201,564.00 0.43% 0.00%
CEWZ1GF-02 LV Installation 11-Sep-17 24-Sep-17 77,224.37 0.16% 0.00%

1089 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CEWZ1GF-03 Socket Device 25-Sep-17 11-Oct-17 2,268.89 0.00% 0.00%
CEWZ1GF-04 Special Purpose Socket 27-Sep-17 14-Oct-17 667.32 0.00% 0.00%
CEWZ1GF-05 Switch Device 30-Sep-17 16-Oct-17 1,343.03 0.00% 0.00%
CEWZ1GF-06 Lighting Fixtures 17-Oct-17 30-Oct-17 100,308.00 0.21% 0.00%
CEWZ1GF-07 Emergency Generator System & Save Energy Panel & ATS 19-Oct-17 12-Nov-17 173,023.00 0.37% 0.00%
First floor level 12-Oct-17 28-Nov-17
CEWZ1FF-01 Socket Device 12-Oct-17 29-Oct-17 1,070.23 0.00% 0.00%
CEWZ1FF-02 Special Purpose Socket 15-Oct-17 31-Oct-17 1,067.71 0.00% 0.00%
CEWZ1FF-03 Switch Device 17-Oct-17 2-Nov-17 805.82 0.00% 0.00%
CEWZ1FF-04 Lighting Fixtures 13-Nov-17 28-Nov-17 55,799.00 0.12% 0.03%
Second floor level 22-Aug-17 12-Dec-17
CEWZ1SF-01 Cable Trays 22-Aug-17 14-Sep-17 1,960.00 0.00% 0.00%
CEWZ1SF-02 Panel Board 16-Sep-17 1-Oct-17 24,695.00 0.05% 0.00%
CEWZ1SF-03 LV Installation 2-Oct-17 12-Oct-17 77,224.37 0.16% 0.00%
CEWZ1SF-04 Save Energy Panels 14-Oct-17 24-Oct-17 21,505.00 0.05% 0.00%
CEWZ1SF-05 Socket Device 30-Oct-17 15-Nov-17 2,739.79 0.01% 0.00%
CEWZ1SF-06 Special Purpose Socket 1-Nov-17 18-Nov-17 1,201.17 0.00% 0.00%
CEWZ1SF-07 Switch Device 4-Nov-17 20-Nov-17 1,175.15 0.00% 0.00%
CEWZ1SF-08 Lighting Fixtures 29-Nov-17 12-Dec-17 76,805.00 0.16% 0.03%
Third floor level 17-Sep-17 6-Dec-17
CEWZ1TF-01 Cable Trays 17-Sep-17 9-Oct-17 1,960.00 0.00% 0.00%
CEWZ1TF-02 Panel Board 10-Oct-17 25-Oct-17 19,953.00 0.04% 0.00%
CEWZ1TF-03 LV Installation 26-Oct-17 6-Nov-17 77,224.37 0.16% 0.00%
CEWZ1TF-04 Socket Device 7-Nov-17 21-Nov-17 1,883.60 0.00% 0.00%
CEWZ1TF-05 Save Energy Panels 7-Nov-17 18-Nov-17 17,595.00 0.04% 0.00%
CEWZ1TF-06 Special Purpose Socket 9-Nov-17 23-Nov-17 1,201.17 0.00% 0.00%
CEWZ1TF-07 Switch Device 11-Nov-17 22-Nov-17 839.4 0.00% 0.00%
CEWZ1TF-08 Lighting Fixtures 23-Nov-17 6-Dec-17 39,866.00 0.08% 0.04%
Roof deck level 7-Nov-17 14-Dec-17
CEWZ1RD-01 LV Installation 7-Nov-17 16-Nov-17 72,669.24 0.15% 0.00%
CEWZ1RD-02 Switch Device 18-Nov-17 26-Nov-17 33.58 0.00% 0.00%
CEWZ1RD-03 Disconnect Switches 27-Nov-17 5-Dec-17 18,063.79 0.04% 0.02%
CEWZ1RD-04 Lighting Fixtures 6-Dec-17 14-Dec-17 3,858.00 0.01% 0.00%
Zone 2 11-Sep-17 7-Mar-18
Ground floor level 11-Sep-17 11-Dec-17

1090 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CEWZ2GF-01 Cable Trays 11-Sep-17 5-Oct-17 12,420.00 0.03% 0.00%
CEWZ2GF-02 Panel Board 7-Oct-17 23-Oct-17 5,926.00 0.01% 0.00%
CEWZ2GF-03 LV Installation 24-Oct-17 9-Nov-17 70,391.68 0.15% 0.00%
CEWZ2GF-04 Socket Device 26-Oct-17 8-Nov-17 2,825.40 0.01% 0.00%
CEWZ2GF-05 Special Purpose Socket 29-Oct-17 11-Nov-17 934.25 0.00% 0.00%
CEWZ2GF-06 Switch Device 31-Oct-17 13-Nov-17 1,813.09 0.00% 0.00%
CEWZ2GF-07 Disconnect Switches 14-Nov-17 27-Nov-17 1,354.78 0.00% 0.00%
CEWZ2GF-08 Lighting Fixtures 28-Nov-17 11-Dec-17 63,456.00 0.13% 0.03%
First floor level 7-Oct-17 24-Dec-17
CEWZ2FF-01 Cable Trays 7-Oct-17 28-Oct-17 6,860.00 0.01% 0.00%
CEWZ2FF-02 Panel Board 29-Oct-17 13-Nov-17 30,795.00 0.07% 0.00%
CEWZ2FF-03 LV Installation 14-Nov-17 29-Nov-17 103,114.00 0.22% 0.08%
CEWZ2FF-04 Socket Device 30-Nov-17 9-Dec-17 4,580.58 0.01% 0.00%
CEWZ2FF-05 Save Energy Panels 30-Nov-17 11-Dec-17 27,370.00 0.06% 0.01%
CEWZ2FF-06 Special Purpose Socket 2-Dec-17 11-Dec-17 2,001.96 0.00% 0.00%
CEWZ2FF-07 Switch Device 3-Dec-17 12-Dec-17 2,014.55 0.00% 0.00%
CEWZ2FF-08 Lighting Fixtures 13-Dec-17 24-Dec-17 98,178.00 0.21% 0.00%
Second floor level 13-Dec-17 27-Feb-18
CEWZ2SF-01 Cable Trays 13-Dec-17 3-Jan-18 10,290.00 0.02% 0.00%
CEWZ2SF-02 Panel Board 4-Jan-18 15-Jan-18 50,083.00 0.11% 0.00%
CEWZ2SF-03 LV Installation 16-Jan-18 25-Jan-18 158,897.00 0.34% 0.00%
CEWZ2SF-04 Socket Device 27-Jan-18 4-Feb-18 7,106.32 0.02% 0.00%
CEWZ2SF-05 Save Energy Panels 27-Jan-18 6-Feb-18 44,965.00 0.10% 0.00%
CEWZ2SF-06 Special Purpose Socket 1-Feb-18 11-Feb-18 3,603.52 0.01% 0.00%
CEWZ2SF-07 Switch Device 6-Feb-18 15-Feb-18 3,592.61 0.01% 0.00%
CEWZ2SF-08 Lighting Fixtures 17-Feb-18 27-Feb-18 95,740.00 0.20% 0.00%
Third floor level 4-Jan-18 7-Mar-18
CEWZ2TF-01 Cable Trays 4-Jan-18 22-Jan-18 10,290.00 0.02% 0.00%
CEWZ2TF-02 Panel Board 23-Jan-18 3-Feb-18 48,900.00 0.10% 0.00%
CEWZ2TF-03 LV Installation 4-Feb-18 13-Feb-18 158,897.00 0.34% 0.00%
CEWZ2TF-04 Socket Device 14-Feb-18 22-Feb-18 7,106.32 0.02% 0.00%
CEWZ2TF-05 Save Energy Panels 14-Feb-18 25-Feb-18 44,965.00 0.10% 0.00%
CEWZ2TF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 3,336.60 0.01% 0.00%
CEWZ2TF-07 Switch Device 17-Feb-18 26-Feb-18 3,458.31 0.01% 0.00%
CEWZ2TF-08 Lighting Fixtures 27-Feb-18 7-Mar-18 80,596.00 0.17% 0.00%

1091 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Roof deck level 14-Feb-18 7-Mar-18
CEWZ2RD-01 LV Installation 14-Feb-18 20-Feb-18 207,890.00 0.44% 0.00%
CEWZ2RD-02 Switch Device 21-Feb-18 27-Feb-18 33.58 0.00% 0.00%
CEWZ2RD-03 Disconnect Switches 22-Feb-18 27-Feb-18 48,320.63 0.10% 0.00%
CEWZ2RD-04 Lighting Fixtures 28-Feb-18 7-Mar-18 7,716.00 0.02% 0.00%
Zone 3 7-Oct-17 22-May-18
Ground floor level 7-Oct-17 22-Mar-18
CEWZ3GF-01 Cable Trays 7-Oct-17 27-Nov-17 5,880.00 0.01% 0.00%
CEWZ3GF-02 Panel Board 28-Nov-17 26-Dec-17 47,782.00 0.10% 0.01%
CEWZ3GF-03 LV Installation 27-Dec-17 20-Jan-18 196,121.00 0.42% 0.00%
CEWZ3GF-04 Socket Device 21-Jan-18 7-Feb-18 3,253.50 0.01% 0.00%
CEWZ3GF-05 Special Purpose Socket 1-Feb-18 19-Feb-18 2,669.28 0.01% 0.00%
CEWZ3GF-06 Switch Device 4-Feb-18 20-Feb-18 2,048.12 0.00% 0.00%
CEWZ3GF-07 Disconnect Switches 6-Feb-18 25-Feb-18 4,515.95 0.01% 0.00%
CEWZ3GF-08 Lighting Fixtures 26-Feb-18 22-Mar-18 80,243.00 0.17% 0.00%
First floor level 25-Dec-17 15-Mar-18
CEWZ3FF-01 Cable Trays 25-Dec-17 16-Jan-18 3,920.00 0.01% 0.00%
CEWZ3FF-02 Panel Board 17-Jan-18 30-Jan-18 107,846.00 0.23% 0.00%
CEWZ3FF-03 LV Installation 31-Jan-18 11-Feb-18 108,114.12 0.23% 0.00%
CEWZ3FF-04 Socket Device 12-Feb-18 20-Feb-18 6,378.56 0.01% 0.00%
CEWZ3FF-05 Save Energy Panels 12-Feb-18 22-Feb-18 41,055.00 0.09% 0.00%
CEWZ3FF-06 Special Purpose Socket 15-Feb-18 25-Feb-18 2,535.81 0.01% 0.00%
CEWZ3FF-07 Switch Device 21-Feb-18 1-Mar-18 3,256.85 0.01% 0.00%
CEWZ3FF-08 Lighting Fixtures 3-Mar-18 15-Mar-18 91,949.00 0.20% 0.00%
Second floor level 17-Jan-18 2-Apr-18
CEWZ3SF-01 Cable Trays 17-Jan-18 8-Feb-18 4,214.00 0.01% 0.00%
CEWZ3SF-02 Panel Board 10-Feb-18 22-Feb-18 121,016.00 0.26% 0.00%
CEWZ3SF-03 LV Installation 24-Feb-18 6-Mar-18 357,594.00 0.76% 0.00%
CEWZ3SF-04 Socket Device 7-Mar-18 15-Mar-18 6,292.04 0.01% 0.00%
CEWZ3SF-05 Save Energy Panels 7-Mar-18 18-Mar-18 41,055.00 0.09% 0.00%
CEWZ3SF-06 Special Purpose Socket 10-Mar-18 19-Mar-18 2,535.81 0.01% 0.00%
CEWZ3SF-07 Switch Device 12-Mar-18 20-Mar-18 3,290.43 0.01% 0.00%
CEWZ3SF-08 Lighting Fixtures 21-Mar-18 2-Apr-18 90,809.00 0.19% 0.00%
Third floor level 8-Mar-18 22-May-18
CEWZ3TF-01 Cable Trays 8-Mar-18 31-Mar-18 4,214.00 0.01% 0.00%

1092 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CEWZ3TF-02 Panel Board 1-Apr-18 14-Apr-18 114,860.00 0.24% 0.00%
CEWZ3TF-03 LV Installation 15-Apr-18 25-Apr-18 417,594.00 0.89% 0.00%
CEWZ3TF-04 Socket Device 26-Apr-18 5-May-18 6,464.18 0.01% 0.00%
CEWZ3TF-05 Save Energy Panels 26-Apr-18 7-May-18 44,965.00 0.10% 0.00%
CEWZ3TF-06 Special Purpose Socket 29-Apr-18 8-May-18 2,669.28 0.01% 0.00%
CEWZ3TF-07 Switch Device 1-May-18 9-May-18 3,256.85 0.01% 0.00%
CEWZ3TF-08 Lighting Fixtures 10-May-18 22-May-18 105,097.00 0.22% 0.00%
Roof deck level 26-Apr-18 19-May-18
CEWZ3RD-01 LV Installation 26-Apr-18 1-May-18 259,473.88 0.55% 0.00%
CEWZ3RD-02 Switch Device 2-May-18 10-May-18 33.58 0.00% 0.00%
CEWZ3RD-03 Disconnect Switches 3-May-18 12-May-18 50,578.60 0.11% 0.00%
CEWZ3RD-04 Lighting Fixtures 13-May-18 19-May-18 12,217.00 0.03% 0.00%
Plumbing Works 29-Jun-17 6-Aug-18 2,946,881.00 6.25%
Zone 1 29-Jun-17 22-Feb-18
Ground floor level 29-Jun-17 19-Sep-17
CPWZ1GF-01 Potable water supply piping 29-Jun-17 22-Jul-17 18,000.00 0.04% 0.00%
CPWZ1GF-02 Sewer/ drainage system 1-Jul-17 25-Jul-17 16,403.00 0.03% 0.00%
CPWZ1GF-03 Storm/ Rain water system 3-Jul-17 27-Jul-17 2,532.00 0.01% 0.00%
CPWZ1GF-04 Isolation valves 29-Jul-17 7-Aug-17 2,500.00 0.01% 0.00%
CPWZ1GF-05 Electrical water heater 8-Aug-17 14-Aug-17 6,638.00 0.01% 0.00%
CPWZ1GF-06 LPG System 15-Aug-17 28-Aug-17 10,800.00 0.02% 0.00%
CPWZ1GF-07 Sanitary Fixtures 7-Sep-17 19-Sep-17 25,967.00 0.06% 0.00%
First floor level 26-Jul-17 19-Nov-17
CPWZ1FF-01 Potable water supply piping 26-Jul-17 10-Sep-17 18,069.00 0.04% 0.00%
CPWZ1FF-02 Sewer/ drainage system 31-Jul-17 12-Sep-17 20,000.00 0.04% 0.00%
CPWZ1FF-03 Storm/ Rain water system 5-Aug-17 17-Sep-17 2,000.00 0.00% 0.00%
CPWZ1FF-04 Isolation valves 18-Sep-17 3-Oct-17 2,000.00 0.00% 0.00%
CPWZ1FF-05 Electrical water heater 4-Oct-17 19-Oct-17 20,000.00 0.04% 0.00%
CPWZ1FF-06 Sanitary Fixtures 21-Oct-17 19-Nov-17 75,000.00 0.16% 0.00%
Second floor level 11-Sep-17 17-Jan-18
CPWZ1SF-01 Potable water supply piping 11-Sep-17 29-Oct-17 18,434.00 0.04% 0.00%
CPWZ1SF-02 Sewer/ drainage system 16-Sep-17 29-Oct-17 40,000.00 0.08% 0.00%
CPWZ1SF-03 Storm/ Rain water system 19-Sep-17 1-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-04 Isolation valves 2-Nov-17 18-Nov-17 2,000.00 0.00% 0.00%
CPWZ1SF-05 Electrical water heater 19-Nov-17 4-Dec-17 15,000.00 0.03% 0.01%

1093 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CPWZ1SF-06 LPG System 5-Dec-17 18-Dec-17 8,000.00 0.02% 0.00%
CPWZ1SF-07 Sanitary Fixtures 19-Dec-17 17-Jan-18 100,000.00 0.21% 0.00%
Third floor level 30-Oct-17 22-Feb-18
CPWZ1TF-01 Potable water supply piping 30-Oct-17 17-Dec-17 18,434.00 0.04% 0.01%
CPWZ1TF-02 Sewer/ drainage system 4-Nov-17 17-Dec-17 40,000.00 0.08% 0.01%
CPWZ1TF-03 Storm/ Rain water system 7-Nov-17 20-Dec-17 2,000.00 0.00% 0.00%
CPWZ1TF-04 Isolation valves 21-Dec-17 6-Jan-18 2,000.00 0.00% 0.00%
CPWZ1TF-05 Electrical water heater 28-Dec-17 13-Jan-18 15,000.00 0.03% 0.00%
CPWZ1TF-06 Sanitary Fixtures 24-Jan-18 22-Feb-18 100,000.00 0.21% 0.00%
Roof deck level 21-Dec-17 14-Jan-18
CPWZ1RD-01 Storm/ Rain water system 21-Dec-17 14-Jan-18 5,000.00 0.01% 0.00%
Zone 2 25-Jul-17 30-May-18
Ground floor level 25-Jul-17 23-Sep-17
CPWZ2GF-01 Potable water supply piping 25-Jul-17 16-Aug-17 15,017.00 0.03% 0.00%
CPWZ2GF-02 Sewer/ drainage system 27-Jul-17 21-Aug-17 20,000.00 0.04% 0.00%
CPWZ2GF-03 Storm/ Rain water system 30-Jul-17 23-Aug-17 2,000.00 0.00% 0.00%
CPWZ2GF-04 Isolation valves 24-Aug-17 3-Sep-17 1,500.00 0.00% 0.00%
CPWZ2GF-05 Electrical water heater 4-Sep-17 11-Sep-17 4,000.00 0.01% 0.00%
CPWZ2GF-06 Sanitary Fixtures 12-Sep-17 23-Sep-17 85,085.00 0.18% 0.00%
First floor level 11-Sep-17 15-Jan-18
CPWZ2FF-01 Potable water supply piping 11-Sep-17 1-Nov-17 30,000.00 0.06% 0.00%
CPWZ2FF-02 Sewer/ drainage system 16-Sep-17 31-Oct-17 35,000.00 0.07% 0.00%
CPWZ2FF-03 Storm/ Rain water system 20-Sep-17 5-Nov-17 3,500.00 0.01% 0.00%
CPWZ2FF-04 Isolation valves 6-Nov-17 22-Nov-17 3,000.00 0.01% 0.00%
CPWZ2FF-05 Electrical water heater 23-Nov-17 13-Dec-17 20,000.00 0.04% 0.01%
CPWZ2FF-06 Sanitary Fixtures 14-Dec-17 15-Jan-18 210,000.00 0.45% 0.00%
Second floor level 30-Oct-17 19-Mar-18
CPWZ2SF-01 Potable water supply piping 30-Oct-17 20-Dec-17 55,000.00 0.12% 0.02%
CPWZ2SF-02 Sewer/ drainage system 4-Nov-17 19-Dec-17 75,000.00 0.16% 0.02%
CPWZ2SF-03 Storm/ Rain water system 8-Nov-17 24-Dec-17 5,000.00 0.01% 0.00%
CPWZ2SF-04 Isolation valves 25-Dec-17 10-Jan-18 6,000.00 0.01% 0.00%
CPWZ2SF-05 Electrical water heater 11-Jan-18 31-Jan-18 30,000.00 0.06% 0.00%
CPWZ2SF-06 LPG System 1-Feb-18 14-Feb-18 10,000.00 0.02% 0.00%
CPWZ2SF-07 Sanitary Fixtures 15-Feb-18 19-Mar-18 205,000.00 0.44% 0.00%
Third floor level 18-Dec-17 30-May-18

1094 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CPWZ2TF-01 Potable water supply piping 18-Dec-17 7-Feb-18 55,000.00 0.12% 0.00%
CPWZ2TF-02 Sewer/ drainage system 27-Dec-17 11-Feb-18 75,000.00 0.16% 0.00%
CPWZ2TF-03 Storm/ Rain water system 20-Jan-18 6-Mar-18 5,000.00 0.01% 0.00%
CPWZ2TF-04 Isolation valves 7-Mar-18 24-Mar-18 6,000.00 0.01% 0.00%
CPWZ2TF-05 Electrical water heater 25-Mar-18 14-Apr-18 30,000.00 0.06% 0.00%
CPWZ2TF-06 LPG System 15-Apr-18 28-Apr-18 10,000.00 0.02% 0.00%
CPWZ2TF-07 Sanitary Fixtures 29-Apr-18 30-May-18 205,000.00 0.44% 0.00%
Roof deck level 7-Mar-18 4-Apr-18
CPWZ2RD-01 Storm/ Rain water system 7-Mar-18 4-Apr-18 10,000.00 0.02% 0.00%
Zone 3 7-Sep-17 6-Aug-18
Ground floor level 7-Sep-17 5-Dec-17
CPWZ3GF-01 Potable water supply piping 7-Sep-17 30-Sep-17 11,000.00 0.02% 0.00%
CPWZ3GF-02 Sewer/ drainage system 10-Sep-17 4-Oct-17 25,000.00 0.05% 0.00%
CPWZ3GF-03 Storm/ Rain water system 12-Sep-17 7-Oct-17 3,000.00 0.01% 0.00%
CPWZ3GF-04 Isolation valves 8-Oct-17 17-Oct-17 552 0.00% 0.00%
CPWZ3GF-05 Pumps 28-Oct-17 9-Nov-17 106,950.00 0.23% 0.00%
CPWZ3GF-06 Electrical water heater 11-Nov-17 21-Nov-17 2,000.00 0.00% 0.00%
CPWZ3GF-07 Sanitary Fixtures 22-Nov-17 5-Dec-17 25,000.00 0.05% 0.03%
First floor level 2-Nov-17 3-Apr-18
CPWZ3FF-01 Potable water supply piping 2-Nov-17 24-Dec-17 40,000.00 0.08% 0.01%
CPWZ3FF-02 Sewer/ drainage system 7-Nov-17 25-Dec-17 45,000.00 0.10% 0.01%
CPWZ3FF-03 Storm/ Rain water system 12-Nov-17 30-Dec-17 5,500.00 0.01% 0.00%
CPWZ3FF-04 Isolation valves 31-Dec-17 20-Jan-18 5,000.00 0.01% 0.00%
CPWZ3FF-05 Electrical water heater 21-Jan-18 13-Feb-18 20,000.00 0.04% 0.00%
CPWZ3FF-06 LPG System 14-Feb-18 27-Feb-18 11,000.00 0.02% 0.00%
CPWZ3FF-07 Sanitary Fixtures 28-Feb-18 3-Apr-18 150,000.00 0.32% 0.00%
Second floor level 21-Dec-17 9-May-18
CPWZ3SF-01 Potable water supply piping 21-Dec-17 11-Feb-18 55,000.00 0.12% 0.00%
CPWZ3SF-02 Sewer/ drainage system 24-Dec-17 10-Feb-18 85,000.00 0.18% 0.00%
CPWZ3SF-03 Storm/ Rain water system 26-Dec-17 12-Feb-18 7,000.00 0.01% 0.00%
CPWZ3SF-04 Isolation valves 13-Feb-18 5-Mar-18 7,000.00 0.01% 0.00%
CPWZ3SF-05 Electrical water heater 6-Mar-18 29-Mar-18 30,000.00 0.06% 0.00%
CPWZ3SF-06 LPG System 31-Mar-18 4-Apr-18 11,000.00 0.02% 0.00%
CPWZ3SF-07 Sanitary Fixtures 5-Apr-18 9-May-18 150,000.00 0.32% 0.00%
Third floor level 8-Feb-18 6-Aug-18

1095 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CPWZ3TF-01 Potable water supply piping 8-Feb-18 1-Apr-18 55,000.00 0.12% 0.00%
CPWZ3TF-02 Sewer/ drainage system 19-Mar-18 6-May-18 85,000.00 0.18% 0.00%
CPWZ3TF-03 Storm/ Rain water system 31-Mar-18 17-May-18 7,000.00 0.01% 0.00%
CPWZ3TF-04 Isolation valves 19-May-18 7-Jun-18 7,000.00 0.01% 0.00%
CPWZ3TF-05 Electrical water heater 9-Jun-18 2-Jul-18 30,000.00 0.06% 0.00%
CPWZ3TF-06 LPG System 3-Jul-18 8-Jul-18 14,000.00 0.03% 0.00%
CPWZ3TF-07 Sanitary Fixtures 9-Jul-18 6-Aug-18 150,000.00 0.32% 0.00%
Roof deck level 19-May-18 17-Jun-18
CPWZ3RD-01 Storm/ Rain water system 19-May-18 17-Jun-18 5,000.00 0.01% 0.00%
Fire Alarm System Works 31-Oct-17 10-Jul-18 673,201.57 1.43%
Zone 1 31-Oct-17 15-May-18
Ground floor level 31-Oct-17 18-Dec-17
CFAZ1GF-01 Conduit and boxes installation 31-Oct-17 23-Nov-17 10,870.89 0.02% 0.00%
CFAZ1GF-02 Cable pulling and cable testing 25-Nov-17 7-Dec-17 8,666.17 0.02% 0.01%
CFAZ1GF-03 Detector and equipment installation 9-Dec-17 18-Dec-17 10,500.00 0.02% 0.00%
First floor level 19-Dec-17 6-Feb-18
CFAZ1FF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 9,172.32 0.02% 0.00%
CFAZ1FF-02 Cable pulling and cable testing 13-Jan-18 28-Jan-18 6,879.24 0.01% 0.00%
CFAZ1FF-03 Detector and equipment installation 29-Jan-18 6-Feb-18 10,960.00 0.02% 0.00%
Second floor level 7-Feb-18 27-Mar-18
CFAZ1SF-01 Conduit and boxes installation 7-Feb-18 3-Mar-18 9,851.75 0.02% 0.00%
CFAZ1SF-02 Cable pulling and cable testing 4-Mar-18 17-Mar-18 7,388.81 0.02% 0.00%
CFAZ1SF-03 Detector and equipment installation 18-Mar-18 27-Mar-18 11,595.00 0.02% 0.00%
Third floor level 28-Mar-18 15-May-18
CFAZ1TF-01 Conduit and boxes installation 28-Mar-18 21-Apr-18 7,473.74 0.02% 0.00%
CFAZ1TF-02 Cable pulling and cable testing 22-Apr-18 5-May-18 5,605.30 0.01% 0.00%
CFAZ1TF-03 Detector and equipment installation 6-May-18 15-May-18 9,695.00 0.02% 0.00%
Zone 2 25-Nov-17 14-Jun-18
Ground floor level 25-Nov-17 13-Jan-18
CFAZ2GF-01 Conduit and boxes installation 25-Nov-17 18-Dec-17 22,081.50 0.05% 0.01%
CFAZ2GF-02 Cable pulling and cable testing 19-Dec-17 1-Jan-18 16,561.12 0.04% 0.00%
CFAZ2GF-03 Detector and equipment installation 2-Jan-18 13-Jan-18 20,168.00 0.04% 0.00%
First floor level 14-Jan-18 3-Mar-18
CFAZ2FF-01 Conduit and boxes installation 14-Jan-18 6-Feb-18 23,440.36 0.05% 0.00%
CFAZ2FF-02 Cable pulling and cable testing 7-Feb-18 20-Feb-18 17,580.27 0.04% 0.00%

1096 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFAZ2FF-03 Detector and equipment installation 21-Feb-18 3-Mar-18 21,113.00 0.04% 0.00%
Second floor level 4-Mar-18 21-Apr-18
CFAZ2SF-01 Conduit and boxes installation 4-Mar-18 27-Mar-18 27,856.66 0.06% 0.00%
CFAZ2SF-02 Cable pulling and cable testing 28-Mar-18 10-Apr-18 20,892.50 0.04% 0.00%
CFAZ2SF-03 Detector and equipment installation 11-Apr-18 21-Apr-18 35,401.00 0.08% 0.00%
Third floor level 22-Apr-18 14-Jun-18
CFAZ2TF-01 Conduit and boxes installation 22-Apr-18 15-May-18 27,856.66 0.06% 0.00%
CFAZ2TF-02 Cable pulling and cable testing 16-May-18 31-May-18 20,892.50 0.04% 0.00%
CFAZ2TF-03 Detector and equipment installation 2-Jun-18 14-Jun-18 35,401.00 0.08% 0.00%
Zone 3 19-Dec-17 10-Jul-18
Ground floor level 19-Dec-17 10-Feb-18
CFAZ3GF-01 Conduit and boxes installation 19-Dec-17 11-Jan-18 24,799.22 0.05% 0.00%
CFAZ3GF-02 Cable pulling and cable testing 13-Jan-18 27-Jan-18 18,599.42 0.04% 0.00%
CFAZ3GF-03 Detector and equipment installation 28-Jan-18 10-Feb-18 49,744.00 0.11% 0.00%
First floor level 11-Feb-18 1-Apr-18
CFAZ3FF-01 Conduit and boxes installation 11-Feb-18 6-Mar-18 22,760.93 0.05% 0.00%
CFAZ3FF-02 Cable pulling and cable testing 7-Mar-18 18-Mar-18 18,599.42 0.04% 0.00%
CFAZ3FF-03 Detector and equipment installation 19-Mar-18 1-Apr-18 21,110.00 0.04% 0.00%
Second floor level 2-Apr-18 21-May-18
CFAZ3SF-01 Conduit and boxes installation 2-Apr-18 25-Apr-18 25,478.65 0.05% 0.00%
CFAZ3SF-02 Cable pulling and cable testing 26-Apr-18 7-May-18 19,108.99 0.04% 0.00%
CFAZ3SF-03 Detector and equipment installation 8-May-18 21-May-18 14,958.00 0.03% 0.00%
Third floor level 22-May-18 10-Jul-18
CFAZ3TF-01 Conduit and boxes installation 22-May-18 14-Jun-18 25,818.37 0.05% 0.00%
CFAZ3TF-02 Cable pulling and cable testing 16-Jun-18 26-Jun-18 19,363.78 0.04% 0.00%
CFAZ3TF-03 Detector and equipment installation 27-Jun-18 10-Jul-18 14,958.00 0.03% 0.00%
Low Current / Communication Works 11-Sep-17 5-Aug-18 2,026,475.10 4.30%
Zone 1 11-Sep-17 7-Feb-18
Ground floor level 11-Sep-17 8-Nov-17
CTWZ1GF-01 Telephone System 11-Sep-17 4-Oct-17 24,567.89 0.05% 0.00%
CTWZ1GF-02 Data System 28-Sep-17 15-Oct-17 37,867.56 0.08% 0.00%
CTWZ1GF-03 Public Address & Paging 16-Oct-17 29-Oct-17 65,131.20 0.14% 0.00%
CTWZ1GF-04 CCTV System 26-Oct-17 8-Nov-17 43,232.82 0.09% 0.00%
First floor level 30-Oct-17 1-Jan-18
CTWZ1FF-01 Telephone System 30-Oct-17 21-Nov-17 35,048.00 0.07% 0.00%

1097 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CTWZ1FF-02 Data System 18-Nov-17 4-Dec-17 24,739.69 0.05% 0.02%
CTWZ1FF-03 IPTV System 5-Dec-17 18-Dec-17 4,546.23 0.01% 0.00%
CTWZ1FF-04 CCTV System 19-Dec-17 1-Jan-18 6,872.14 0.01% 0.00%
Second floor level 16-Sep-17 16-Nov-17
CTWZ1SF-01 Telephone System 16-Sep-17 8-Oct-17 55,277.75 0.12% 0.00%
CTWZ1SF-02 Data System 3-Oct-17 19-Oct-17 41,202.00 0.09% 0.00%
CTWZ1SF-03 IPTV System 21-Oct-17 2-Nov-17 4,546.23 0.01% 0.00%
CTWZ1SF-04 CCTV System 4-Nov-17 16-Nov-17 3,436.07 0.01% 0.00%
Third floor level 7-Dec-17 7-Feb-18
CTWZ1TF-01 Telephone System 7-Dec-17 31-Dec-17 12,756.40 0.03% 0.00%
CTWZ1TF-02 Data System 25-Dec-17 10-Jan-18 9,277.38 0.02% 0.00%
CTWZ1TF-03 IPTV System 11-Jan-18 24-Jan-18 5,834.76 0.01% 0.00%
CTWZ1TF-04 CCTV System 25-Jan-18 7-Feb-18 3,436.07 0.01% 0.00%
Zone 2 7-Oct-17 14-May-18
Ground floor level 7-Oct-17 30-Nov-17
CTWZ2GF-01 Telephone System 7-Oct-17 29-Oct-17 95,461.00 0.20% 0.00%
CTWZ2GF-02 Data System 18-Oct-17 5-Nov-17 26,396.09 0.06% 0.00%
CTWZ2GF-03 Public Address & Paging 6-Nov-17 22-Nov-17 84,183.68 0.18% 0.00%
CTWZ2GF-04 CCTV System 18-Nov-17 30-Nov-17 51,541.03 0.11% 0.05%
First floor level 13-Dec-17 10-Feb-18
CTWZ2FF-01 Telephone System 13-Dec-17 6-Jan-18 97,620.00 0.21% 0.00%
CTWZ2FF-02 Data System 25-Dec-17 11-Jan-18 85,712.00 0.18% 0.00%
CTWZ2FF-03 IPTV System 13-Jan-18 29-Jan-18 5,095.73 0.01% 0.00%
CTWZ2FF-04 CCTV System 30-Jan-18 10-Feb-18 10,191.46 0.02% 0.00%
Second floor level 28-Feb-18 2-May-18
CTWZ2SF-01 Telephone System 28-Feb-18 24-Mar-18 109,303.42 0.23% 0.00%
CTWZ2SF-02 Data System 17-Mar-18 3-Apr-18 79,493.40 0.17% 0.00%
CTWZ2SF-03 IPTV System 4-Apr-18 21-Apr-18 5,698.58 0.01% 0.00%
CTWZ2SF-04 CCTV System 22-Apr-18 2-May-18 6,794.31 0.01% 0.00%
Third floor level 8-Mar-18 14-May-18
CTWZ2TF-01 Telephone System 8-Mar-18 1-Apr-18 74,460.99 0.16% 0.00%
CTWZ2TF-02 Data System 22-Mar-18 9-Apr-18 77,880.00 0.17% 0.00%
CTWZ2TF-03 IPTV System 10-Apr-18 26-Apr-18 5,095.73 0.01% 0.00%
CTWZ2TF-04 CCTV System 3-May-18 14-May-18 6,794.31 0.01% 0.00%
Zone 3 28-Nov-17 5-Aug-18

1098 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Ground floor level 28-Nov-17 23-Jan-18
CTWZ3GF-01 Telephone System 28-Nov-17 26-Dec-17 100,461.00 0.21% 0.03%
CTWZ3GF-02 Data System 10-Dec-17 1-Jan-18 65,818.00 0.14% 0.00%
CTWZ3GF-03 Public Address & Paging 27-Dec-17 13-Jan-18 17,835.06 0.04% 0.00%
CTWZ3GF-04 CCTV System 8-Jan-18 23-Jan-18 30,574.38 0.06% 0.00%
First floor level 24-Jan-18 8-Apr-18
CTWZ3FF-01 Telephone System 24-Jan-18 22-Feb-18 97,620.00 0.21% 0.00%
CTWZ3FF-02 Data System 5-Feb-18 28-Feb-18 79,833.11 0.17% 0.00%
CTWZ3FF-03 IPTV System 1-Mar-18 21-Mar-18 5,095.73 0.01% 0.00%
CTWZ3FF-04 CCTV System 22-Mar-18 8-Apr-18 13,588.61 0.03% 0.00%
Second floor level 9-Apr-18 21-Jun-18
CTWZ3SF-01 Telephone System 9-Apr-18 8-May-18 100,369.00 0.21% 0.00%
CTWZ3SF-03 Data System 21-Apr-18 14-May-18 78,813.97 0.17% 0.00%
CTWZ3SF-04 IPTV System 15-May-18 4-Jun-18 5,095.73 0.01% 0.00%
CTWZ3SF-02 CCTV System 5-Jun-18 21-Jun-18 13,588.61 0.03% 0.00%
Third floor level 23-May-18 5-Aug-18
CTWZ3TF-01 Telephone System 23-May-18 21-Jun-18 109,770.53 0.23% 0.00%
CTWZ3TF-02 Data System 4-Jun-18 27-Jun-18 89,833.11 0.19% 0.00%
CTWZ3TF-03 IPTV System 28-Jun-18 18-Jul-18 5,095.73 0.01% 0.00%
CTWZ3TF-04 CCTV System 19-Jul-18 5-Aug-18 13,588.61 0.03% 0.00%
Fire Fighting System Works 1-Oct-17 8-Aug-18 1,776,735.00 3.77%
Zone 1 1-Oct-17 7-Apr-18
Ground floor level 1-Oct-17 1-Jan-18
CFFZ1GF-01 Black steel sch-40 pipes 1-Oct-17 29-Oct-17 11,655.00 0.02% 0.00%
CFFZ1GF-02 Sprinkler heads installation 30-Oct-17 20-Nov-17 2,466.00 0.01% 0.00%
CFFZ1GF-03 FM 200 fire protection system 21-Nov-17 14-Dec-17 53,000.00 0.11% 0.03%
CFFZ1GF-04 Fire hose cabinet 10-Dec-17 26-Dec-17 19,925.00 0.04% 0.00%
CFFZ1GF-05 Fire extinguisher 27-Dec-17 1-Jan-18 39,850.00 0.08% 0.00%
First floor level 21-Nov-17 13-Feb-18
CFFZ1FF-01 Black steel sch-40 pipes 21-Nov-17 19-Dec-17 14,101.00 0.03% 0.01%
CFFZ1FF-02 Sprinkler heads installation 20-Dec-17 15-Jan-18 3,381.00 0.01% 0.00%
CFFZ1FF-03 Fire hose cabinet 16-Jan-18 7-Feb-18 19,387.00 0.04% 0.00%
CFFZ1FF-04 Fire extinguisher 8-Feb-18 13-Feb-18 15,000.00 0.03% 0.00%
Second floor level 20-Dec-17 8-Mar-18
CFFZ1SF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 21,101.00 0.04%

1099 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFFZ1SF-02 Sprinkler heads installation 18-Jan-18 10-Feb-18 1,500.00 0.00% 0.00%
CFFZ1SF-03 Fire hose cabinet 11-Feb-18 3-Mar-18 17,803.00 0.04% 0.00%
CFFZ1SF-04 Fire extinguisher 4-Mar-18 8-Mar-18 10,000.00 0.02% 0.00%
Third floor level 18-Jan-18 7-Apr-18
CFFZ1TF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 21,101.00 0.04% 0.00%
CFFZ1TF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 1,500.00 0.00% 0.00%
CFFZ1TF-03 Fire hose cabinet 12-Mar-18 1-Apr-18 17,803.00 0.04% 0.00%
CFFZ1TF-04 Fire extinguisher 2-Apr-18 7-Apr-18 10,000.00 0.02% 0.00%
Zone 2 6-Nov-17 8-May-18
Ground floor level 6-Nov-17 18-Jan-18
CFFZ2GF-01 Black steel sch-40 pipes 6-Nov-17 4-Dec-17 19,101.00 0.04% 0.01%
CFFZ2GF-02 Sprinkler heads installation 5-Dec-17 25-Dec-17 7,500.00 0.02% 0.00%
CFFZ2GF-03 Fire hose cabinet 27-Dec-17 13-Jan-18 22,223.00 0.05% 0.00%
CFFZ2GF-04 Fire extinguisher 14-Jan-18 18-Jan-18 36,873.00 0.08% 0.00%
First floor level 20-Dec-17 11-Mar-18
CFFZ2FF-01 Black steel sch-40 pipes 20-Dec-17 17-Jan-18 27,101.00 0.06% 0.00%
CFFZ2FF-02 Sprinkler heads installation 18-Jan-18 12-Feb-18 6,000.00 0.01% 0.00%
CFFZ2FF-03 Fire hose cabinet 13-Feb-18 5-Mar-18 17,803.00 0.04% 0.00%
CFFZ2FF-04 Fire extinguisher 6-Mar-18 11-Mar-18 35,000.00 0.07% 0.00%
Second floor level 18-Jan-18 9-Apr-18
CFFZ2SF-01 Black steel sch-40 pipes 18-Jan-18 15-Feb-18 39,101.00 0.08% 0.00%
CFFZ2SF-02 Sprinkler heads installation 17-Feb-18 11-Mar-18 6,000.00 0.01% 0.00%
CFFZ2SF-03 Fire hose cabinet 12-Mar-18 3-Apr-18 17,803.00 0.04% 0.00%
CFFZ2SF-04 Fire extinguisher 4-Apr-18 9-Apr-18 10,000.00 0.02% 0.00%
Third floor level 17-Feb-18 8-May-18
CFFZ2TF-01 Black steel sch-40 pipes 17-Feb-18 17-Mar-18 39,101.00 0.08% 0.00%
CFFZ2TF-02 Sprinkler heads installation 18-Mar-18 9-Apr-18 6,000.00 0.01% 0.00%
CFFZ2TF-03 Fire hose cabinet 10-Apr-18 2-May-18 22,803.00 0.05% 0.00%
CFFZ2TF-04 Fire extinguisher 3-May-18 8-May-18 10,000.00 0.02% 0.00%
Zone 3 26-Nov-17 8-Aug-18
Ground floor level 26-Nov-17 26-Apr-18
CFFZ3GF-01 Main fire pump 26-Nov-17 30-Dec-17 365,700.00 0.78% 0.13%
CFFZ3GF-02 Feed water tank 31-Dec-17 16-Jan-18 49,450.00 0.10% 0.00%
CFFZ3GF-03 Black steel sch-40 pipes 17-Jan-18 14-Feb-18 19,101.00 0.04% 0.00%
CFFZ3GF-04 Sprinkler heads installation 25-Jan-18 18-Feb-18 6,500.00 0.01% 0.00%

1100 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CFFZ3GF-05 FM 200 fire protection system 19-Feb-18 13-Mar-18 80,000.00 0.17% 0.00%
CFFZ3GF-06 Fire hose cabinet 14-Mar-18 3-Apr-18 32,539.00 0.07% 0.00%
CFFZ3GF-07 Fire extinguisher 4-Apr-18 9-Apr-18 70,000.00 0.15% 0.00%
CFFZ3GF-08 Condensate pipes 10-Apr-18 26-Apr-18 11,250.00 0.02% 0.00%
First floor level 15-Feb-18 23-May-18
CFFZ3FF-01 Black steel sch-40 pipes 15-Feb-18 24-Mar-18 27,101.00 0.06% 0.00%
CFFZ3FF-02 Sprinkler heads installation 19-Feb-18 27-Mar-18 4,000.00 0.01% 0.00%
CFFZ3FF-03 FM 200 fire protection system 15-Mar-18 18-Apr-18 40,000.00 0.08% 0.00%
CFFZ3FF-04 Fire hose cabinet 19-Apr-18 13-May-18 55,304.00 0.12% 0.00%
CFFZ3FF-05 Fire extinguisher 25-Apr-18 30-Apr-18 20,000.00 0.04% 0.00%
CFFZ3FF-06 Condensate pipes 1-May-18 23-May-18 25,000.00 0.05% 0.00%
Second floor level 25-Mar-18 21-Jun-18
CFFZ3SF-01 Black steel sch-40 pipes 25-Mar-18 30-Apr-18 39,101.00 0.08% 0.00%
CFFZ3SF-02 Sprinkler heads installation 28-Mar-18 3-May-18 5,000.00 0.01% 0.00%
CFFZ3SF-03 FM 200 fire protection system 22-Apr-18 26-May-18 40,000.00 0.08% 0.00%
CFFZ3SF-04 Fire hose cabinet 27-May-18 19-Jun-18 55,303.00 0.12% 0.00%
CFFZ3SF-05 Fire extinguisher 2-Jun-18 6-Jun-18 20,000.00 0.04% 0.00%
CFFZ3SF-06 Condensate pipes 2-Jun-18 21-Jun-18 25,000.00 0.05% 0.00%
Third floor level 1-May-18 8-Aug-18
CFFZ3TF-01 Black steel sch-40 pipes 1-May-18 10-Jun-18 39,101.00 0.08% 0.00%
CFFZ3TF-02 Sprinkler heads installation 5-May-18 13-Jun-18 5,000.00 0.01% 0.00%
CFFZ3TF-03 FM 200 fire protection system 24-May-18 27-Jun-18 40,000.00 0.08% 0.00%
CFFZ3TF-04 Fire hose cabinet 28-Jun-18 23-Jul-18 55,303.00 0.12% 0.00%
CFFZ3TF-05 Fire extinguisher 3-Jul-18 8-Jul-18 20,000.00 0.04% 0.00%
CFFZ3TF-06 Condensate pipes 15-Jul-18 8-Aug-18 25,000.00 0.05% 0.00%
Mechanical (HVAC) Works 30-Aug-17 7-Aug-18 5,389,457.00 11.44%
Zone 1 30-Aug-17 28-Jul-18
Ground floor level 30-Aug-17 18-Feb-18
CMWZ1GF-01 HVAC Equipments 30-Aug-17 26-Oct-17 148,699.00 0.32% 0.00%
CMWZ1GF-02 Ventilation Equipment/ Exhaust Fans 28-Oct-17 21-Dec-17 4,207.00 0.01% 0.00%
CMWZ1GF-03 Diffusers, Grilles, Duct works & other outlets 23-Dec-17 18-Feb-18 194,364.00 0.41% 0.00%
First floor level 7-Oct-17 10-May-18
CMWZ1FF-01 HVAC Equipments 7-Oct-17 17-Dec-17 74,349.00 0.16% 0.02%
CMWZ1FF-02 Ventilation Equipment/ Exhaust Fans 23-Dec-17 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1FF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 10-May-18 97,182.00 0.21% 0.00%

1101 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Second floor level 15-Nov-17 26-Apr-18
CMWZ1SF-01 HVAC Equipments 15-Nov-17 31-Dec-17 74,349.00 0.16% 0.02%
CMWZ1SF-02 Ventilation Equipment/ Exhaust Fans 1-Jan-18 27-Feb-18 2,104.00 0.00% 0.00%
CMWZ1SF-03 Diffusers, Grilles, Duct works & other outlets 28-Feb-18 26-Apr-18 97,182.00 0.21% 0.00%
Third floor level 25-Dec-17 3-Jul-18
CMWZ1TF-01 HVAC Equipments 25-Dec-17 25-Feb-18 74,349.00 0.16% 0.00%
CMWZ1TF-02 Ventilation Equipment/ Exhaust Fans 28-Feb-18 24-Apr-18 2,104.00 0.00% 0.00%
CMWZ1TF-03 Diffusers, Grilles, Duct works & other outlets 28-Apr-18 3-Jul-18 97,182.00 0.21% 0.00%
Roof deck level 4-Jul-18 28-Jul-18
CMWZ1RD-01 Air Cooled Condensing units 4-Jul-18 28-Jul-18 784 0.00% 0.00%
Zone 2 23-Sep-17 7-Aug-18
Ground floor level 23-Sep-17 15-Apr-18
CMWZ2GF-01 HVAC Equipments 23-Sep-17 6-Dec-17 231,608.00 0.49% 0.05%
CMWZ2GF-02 Ventilation Equipment/ Exhaust Fans 20-Nov-17 30-Jan-18 9,999.00 0.02% 0.00%
CMWZ2GF-03 Diffusers, Grilles, Duct works & other outlets 31-Jan-18 15-Apr-18 498,853.00 1.06% 0.00%
First floor level 30-Oct-17 21-May-18
CMWZ2FF-01 HVAC Equipments 30-Oct-17 7-Jan-18 193,007.00 0.41% 0.04%
CMWZ2FF-02 Ventilation Equipment/ Exhaust Fans 8-Jan-18 12-Mar-18 8,333.00 0.02% 0.00%
CMWZ2FF-03 Diffusers, Grilles, Duct works & other outlets 13-Mar-18 21-May-18 415,711.00 0.88% 0.00%
Second floor level 9-Dec-17 20-May-18
CMWZ2SF-01 HVAC Equipments 9-Dec-17 4-Feb-18 193,007.00 0.41% 0.00%
CMWZ2SF-02 Ventilation Equipment/ Exhaust Fans 5-Feb-18 28-Mar-18 8,333.00 0.02% 0.00%
CMWZ2SF-03 Diffusers, Grilles, Duct works & other outlets 24-Mar-18 20-May-18 415,711.00 0.88% 0.00%
Third floor level 17-Jan-18 24-Jul-18
CMWZ2TF-01 HVAC Equipments 17-Jan-18 27-Mar-18 154,405.00 0.33% 0.00%
CMWZ2TF-02 Ventilation Equipment/ Exhaust Fans 17-Mar-18 15-May-18 6,666.00 0.01% 0.00%
CMWZ2TF-03 Diffusers, Grilles, Duct works & other outlets 21-May-18 24-Jul-18 332,569.00 0.71% 0.00%
Roof deck level 11-Jul-18 7-Aug-18
CMWZ2RD-01 Air Cooled Condensing units 11-Jul-18 7-Aug-18 1,490.00 0.00% 0.00%
Zone 3 23-Sep-17 29-Jul-18
Ground floor level 23-Sep-17 13-Mar-18
CMWZ3GF-01 HVAC Equipments 23-Sep-17 28-Nov-17 215,534.00 0.46% 0.03%
CMWZ3GF-02 Ventilation Equipment/ Exhaust Fans 14-Nov-17 10-Jan-18 9,384.00 0.02% 0.00%
CMWZ3GF-03 Diffusers, Grilles, Duct works & other outlets 9-Jan-18 13-Mar-18 389,830.00 0.83% 0.00%
First floor level 22-Nov-17 15-May-18

1102 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
CMWZ3FF-01 HVAC Equipments 22-Nov-17 24-Jan-18 179,611.00 0.38% 0.04%
CMWZ3FF-02 Ventilation Equipment/ Exhaust Fans 25-Jan-18 18-Mar-18 7,820.00 0.02% 0.00%
CMWZ3FF-03 Diffusers, Grilles, Duct works & other outlets 19-Mar-18 15-May-18 324,859.00 0.69% 0.00%
Second floor level 8-Jan-18 26-Jun-18
CMWZ3SF-01 HVAC Equipments 8-Jan-18 18-Mar-18 179,611.00 0.38% 0.00%
CMWZ3SF-02 Ventilation Equipment/ Exhaust Fans 1-Mar-18 30-Apr-18 7,820.00 0.02% 0.00%
CMWZ3SF-03 Diffusers, Grilles, Duct works & other outlets 23-Apr-18 26-Jun-18 324,859.00 0.69% 0.00%
Third floor level 18-Feb-18 24-Jul-18
CMWZ3TF-01 HVAC Equipments 18-Feb-18 26-Apr-18 143,689.00 0.30% 0.00%
CMWZ3TF-02 Ventilation Equipment/ Exhaust Fans 11-Apr-18 9-Jun-18 6,256.00 0.01% 0.00%
CMWZ3TF-03 Diffusers, Grilles, Duct works & other outlets 22-May-18 24-Jul-18 259,887.00 0.55% 0.00%
Roof deck level 30-Jun-18 29-Jul-18
CMWZ3RD-01 Air Cooled Condensing units 30-Jun-18 29-Jul-18 1,646.00 0.00% 0.00%
Works common to all floors 20-Mar-18 18-Sep-18 2,348,233.00 4.98%
CW-01 Lift/ Conveying System 20-Mar-18 20-Jun-18 1,470,830.00 3.12% 0.00%
CW-02 Linen Chute 21-Jun-18 25-Jul-18 83,006.00 0.18% 0.00%
CW-03 External Faade Works 11-Jul-18 18-Sep-18 794,397.00 1.69% 0.00%
External Works 24-Aug-17 25-Aug-18 1,717,396.21 3.64%
Utilities 24-Aug-17 24-Jul-18
CEWU-01 Storm drainage system 24-Aug-17 23-Oct-17 90,505.00 0.19% 0.00%
CEWU-02 Grease Interceptor 18-Oct-17 26-Oct-17 42,550.00 0.09% 0.00%
CEWU-03 Sanitary sewage system 24-Oct-17 14-Dec-17 83,019.00 0.18% 0.02%
CEWU-04 Potable and Fire water distribution system 5-Nov-17 27-Dec-17 75,871.00 0.16% 0.02%
CEWU-05 Site Grounding & System 4-Jan-18 13-Feb-18 38,074.13 0.08% 0.00%
CEWU-06 Gate Barrier 30-Apr-18 13-May-18 138,000.00 0.29% 0.00%
CEWU-07 Hydraulic road blocker 14-May-18 29-May-18 457,369.00 0.97% 0.00%
CEWU-08 Site lighting works 30-May-18 24-Jul-18 19,374.08 0.04% 0.00%
Buildings 3-Oct-17 16-Jan-18
CEWB-01 Construction of Guard House 3-Oct-17 8-Nov-17 24,704.00 0.05% 0.00%
CEWB-02 Construction of Genset Room 9-Nov-17 19-Dec-17 17,006.00 0.04% 0.01%
CEWB-03 Construction of Meter Room, Unit Substation Room & Garbag 2-Dec-17 16-Jan-18 31,245.00 0.07% 0.00%
Parking 14-Feb-18 25-Aug-18
CEWP-01 Asphalt Road 14-Feb-18 12-Apr-18 322,626.00 0.68% 0.00%
CEWP-02 Construction of Parking area/ Shade 14-Apr-18 9-Jul-18 345,000.00 0.73% 0.00%
CEWP-03 Pavement markings & signages 10-Jul-18 25-Aug-18 32,053.00 0.07% 0.00%

1103 of 2424
WK-48
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
30-Nov-17
Landscaping & Hardscape Works (All Area) 14-Feb-18 1-Aug-18 506,292.00 1.07%
CHW-01 Hardscaping Works 14-Feb-18 29-May-18 128,672.00 0.27% 0.00%
CHW-02 Landscaping & Irrigation System 25-Apr-18 1-Aug-18 377,620.00 0.80% 0.00%
Testing & Commissioning 9-Aug-18 29-Oct-18 104,750.00 0.22%
MEP 9-Aug-18 29-Oct-18
TCM-01 Functional Testing of Individual services 9-Aug-18 12-Sep-18 0 0.00%
TCM-02 Pre-commissioning 26-Aug-18 29-Sep-18 0 0.00%
TCM-03 Final Testing & Commissioning 12-Sep-18 16-Oct-18 104,750.00 0.22% 0.00%
TCM-04 Punchlist 19-Sep-18 29-Oct-18 0 0.00%
TCM-05 Wild Air 17-Oct-18 20-Oct-18 0 0.00%
Project Handing Over 21-Oct-18 30-Nov-18 20,000.00 0.04%
PHO-01 As-Built Drawings 21-Oct-18 24-Nov-18 0 0.00%
PHO-02 Demobilization 30-Oct-18 28-Nov-18 20,000.00 0.04% 0.00%
PHO-03 Handing Over 29-Nov-18 30-Nov-18 0 0.00%
Planned Weekly Progress Percentage - Incremental 1.75%
Planned Weekly Progress Percentage - Cumulative 41.10%
47,126,293.00 100.00% WK-48
30-Nov-17

1104 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
General 3-Jan-17 30-Nov-18 1,181,000.00 2.51%
Enabling Works 15-Feb-17 31-Mar-17
EW-01 Site Survey Works 15-Feb-17 26-Feb-17 65,000.00 0.14% 0.00%
EW-02 Geotechnical Investigation and Report 19-Feb-17 22-Mar-17 45,000.00 0.10% 0.00%
EW-03 Site Clearing and Grubbing 19-Feb-17 25-Feb-17 64,322.00 0.14% 0.00%
EW-04 Demolition of Existing Curbstone and Walkways for Site Acces 26-Feb-17 3-Mar-17 43,000.00 0.09% 0.00%
EW-05 Installation of Portable Cabin Facilities, Fence, Signboards, Po 2-Mar-17 24-Mar-17 750,000.00 1.59% 0.00%
EW-06 Installation of office furnitures & equipments 25-Mar-17 31-Mar-17 213,678.00 0.45% 0.00%
Construction 12-Mar-17 20-Sep-18
Foundations 12-Mar-17 19-Jun-17 6,546,679.00 13.89%
Stone Column Works 23-Mar-17 6-May-17
CFSC-01 Stone columns @ Zone 3 23-Mar-17 6-May-17 1,230,689.00 2.61% 0.00%
Raft Foundation/ Substructure 12-Mar-17 19-Jun-17
Zone 01 12-Mar-17 24-Apr-17
CFRFZ1-01 Excavation, levelling & compaction & termite protection works 12-Mar-17 20-Mar-17 61,770.00 0.13% 0.00%
CFRFZ1-02 Lean concrete & vapour barrier 21-Mar-17 21-Mar-17 83,010.00 0.18% 0.00%
CFRFZ1-03 Waterproofing 22-Mar-17 23-Mar-17 12,657.00 0.03% 0.00%
CFRFZ1-04 Formworks 25-Mar-17 30-Mar-17 286,178.00 0.61% 0.00%
CFRFZ1-05 Rebar Installation 1-Apr-17 8-Apr-17 707,913.00 1.50% 0.00%
CFRFZ1-06 Concrete Works 9-Apr-17 9-Apr-17 512,107.00 1.09% 0.00%
CFRFZ1-07 Filling & compaction under slab on grade 10-Apr-17 16-Apr-17 102,336.00 0.22% 0.00%
CFRFZ1-08 Slab on grade 17-Apr-17 24-Apr-17 223,236.00 0.47% 0.00%
Zone 02 21-Mar-17 9-May-17
CFRFZ2-01 Excavation, levelling & compaction & termite protection works 21-Mar-17 30-Mar-17 52,267.00 0.11% 0.00%
CFRFZ2-02 Lean concrete & vapour barrier 1-Apr-17 1-Apr-17 70,240.00 0.15% 0.00%
CFRFZ2-03 Waterproofing 2-Apr-17 3-Apr-17 10,709.00 0.02% 0.00%
CFRFZ2-04 Formworks 4-Apr-17 11-Apr-17 242,150.00 0.51% 0.00%
CFRFZ2-05 Rebar Installation 12-Apr-17 20-Apr-17 599,003.00 1.27% 0.00%
CFRFZ2-06 Concrete Works 22-Apr-17 22-Apr-17 433,323.00 0.92% 0.00%
CFRFZ2-07 Filling & compaction under slab on grade 23-Apr-17 30-Apr-17 86,592.00 0.18% 0.00%
CFRFZ2-08 Slab on grade 1-May-17 9-May-17 188,892.00 0.40% 0.00%
Zone 03 1-Apr-17 19-Jun-17
CFRFZ3-01 Excavation, levelling & compaction & termite protection works 1-Apr-17 6-May-17 44,348.00 0.09% 0.00%
CFRFZ3-02 Lean concrete & vapour barrier 7-May-17 7-May-17 59,597.00 0.13% 0.00%
CFRFZ3-03 Waterproofing 8-May-17 9-May-17 9,087.00 0.02% 0.00%

1105 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CFRFZ3-04 Formworks 10-May-17 18-May-17 205,461.00 0.44% 0.00%
CFRFZ3-05 Rebar Installation 20-May-17 29-May-17 508,245.00 1.08% 0.00%
CFRFZ3-06 Concrete Works 30-May-17 31-May-17 583,125.00 1.24% 0.00%
CFRFZ3-07 Filling & compaction under slab on grade 1-Jun-17 8-Jun-17 73,472.00 0.16% 0.00%
CFRFZ3-08 Slab on grade 10-Jun-17 19-Jun-17 160,272.00 0.34% 0.00%
Skeleton Works 25-Apr-17 4-Jan-18 4,509,487.00 9.57%
Zone 1 25-Apr-17 11-Sep-17
Ground floor level 25-Apr-17 25-May-17
CSWZ1GF-01 Rebar installation 25-Apr-17 10-May-17 25,540.00 0.05% 0.00%
CSWZ1GF-02 Formworks 11-May-17 23-May-17 10,325.00 0.02% 0.00%
CSWZ1GF-03 Concrete works 24-May-17 25-May-17 18,475.00 0.04% 0.00%
First floor level 27-May-17 28-Jun-17
Slab, beams & stairs 27-May-17 28-Jun-17
CSWZ1FF-01 Formworks 27-May-17 3-Jun-17 41,095.00 0.09% 0.00%
CSWZ1FF-02 Rebar, tendons & duct installation 4-Jun-17 13-Jun-17 57,000.00 0.12% 0.00%
CSWZ1FF-03 Concrete works 14-Jun-17 15-Jun-17 73,537.00 0.16% 0.00%
CSWZ1FF-04 Post tensioning 17-Jun-17 28-Jun-17 44,654.00 0.09% 0.00%
Columns 17-Jun-17 26-Jun-17
CSWZ1FF-05 Rebar installation 17-Jun-17 20-Jun-17 12,770.00 0.03% 0.00%
CSWZ1FF-06 Formworks 21-Jun-17 25-Jun-17 5,162.00 0.01% 0.00%
CSWZ1FF-07 Concrete works 26-Jun-17 26-Jun-17 9,238.00 0.02% 0.00%
Second floor level 27-Jun-17 25-Jul-17
Slab, beams & stairs 27-Jun-17 25-Jul-17
CSWZ1SF-01 Formworks 27-Jun-17 2-Jul-17 41,095.00 0.09% 0.00%
CSWZ1SF-02 Rebar, tendons & duct installation 3-Jul-17 10-Jul-17 57,000.00 0.12% 0.00%
CSWZ1SF-03 Concrete works 11-Jul-17 12-Jul-17 73,537.00 0.16% 0.00%
CSWZ1SF-04 Post tensioning 13-Jul-17 25-Jul-17 44,654.00 0.09% 0.00%
Columns 13-Jul-17 22-Jul-17
CSWZ1SF-05 Rebar installation 13-Jul-17 17-Jul-17 12,770.00 0.03% 0.00%
CSWZ1SF-06 Formworks 18-Jul-17 20-Jul-17 5,162.00 0.01% 0.00%
CSWZ1SF-07 Concrete works 22-Jul-17 22-Jul-17 9,238.00 0.02% 0.00%
Third floor level 23-Jul-17 17-Aug-17
Columns 6-Aug-17 14-Aug-17
CSWZ1TF-05 Rebar installation 6-Aug-17 9-Aug-17 9,577.00 0.02% 0.00%
CSWZ1TF-06 Formworks 10-Aug-17 13-Aug-17 3,873.00 0.01% 0.00%

1106 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ1TF-07 Concrete works 14-Aug-17 14-Aug-17 6,928.00 0.01% 0.00%
Slab, beams & stairs 23-Jul-17 17-Aug-17
CSWZ1TF-01 Formworks 23-Jul-17 26-Jul-17 41,095.00 0.09% 0.00%
CSWZ1TF-02 Rebar, tendons & duct installation 27-Jul-17 2-Aug-17 57,000.00 0.12% 0.00%
CSWZ1TF-03 Concrete works 3-Aug-17 5-Aug-17 73,537.00 0.16% 0.00%
CSWZ1TF-04 Post tensioning 6-Aug-17 17-Aug-17 44,654.00 0.09% 0.00%
Roof deck level 15-Aug-17 10-Sep-17
Slab, beams & stairs 15-Aug-17 10-Sep-17
CSWZ1RD-01 Formworks 15-Aug-17 19-Aug-17 10,958.00 0.02% 0.00%
CSWZ1RD-02 Rebar, tendons & duct installation 20-Aug-17 26-Aug-17 15,200.00 0.03% 0.00%
CSWZ1RD-03 Concrete works 27-Aug-17 28-Aug-17 19,610.00 0.04% 0.00%
CSWZ1RD-04 Post tensioning 29-Aug-17 10-Sep-17 14,885.00 0.03% 0.00%
Columns 29-Aug-17 6-Sep-17
CSWZ1RD-05 Rebar installation 29-Aug-17 2-Sep-17 3,192.00 0.01% 0.00%
CSWZ1RD-06 Formworks 3-Sep-17 5-Sep-17 1,292.00 0.00% 0.00%
CSWZ1RD-07 Concrete works 6-Sep-17 6-Sep-17 2,309.00 0.00% 0.00%
Upperroof deck level 7-Sep-17 11-Sep-17
Slab, beams & stairs 7-Sep-17 11-Sep-17
CSWZ1UD-01 Formworks 7-Sep-17 9-Sep-17 2,740.00 0.01% 0.00%
CSWZ1UD-02 Rebar installation 10-Sep-17 10-Sep-17 3,800.00 0.01% 0.00%
CSWZ1UD-03 Concrete works 11-Sep-17 11-Sep-17 4,902.00 0.01% 0.00%
Zone 2 10-May-17 15-Nov-17
Ground floor level 10-May-17 18-Jun-17
CSWZ2GF-01 Rebar installation 10-May-17 28-May-17 44,359.00 0.09% 0.00%
CSWZ2GF-02 Formworks 29-May-17 13-Jun-17 17,932.00 0.04% 0.00%
CSWZ2GF-03 Concrete works 14-Jun-17 18-Jun-17 32,089.00 0.07% 0.00%
First floor level 19-Jun-17 24-Jul-17
Slab, beams & stairs 19-Jun-17 24-Jul-17
CSWZ2FF-01 Formworks 19-Jun-17 27-Jun-17 95,166.00 0.20% 0.00%
CSWZ2FF-02 Rebar, tendons & duct installation 28-Jun-17 9-Jul-17 132,000.00 0.28% 0.00%
CSWZ2FF-03 Concrete works 10-Jul-17 11-Jul-17 170,296.00 0.36% 0.00%
CSWZ2FF-04 Post tensioning 12-Jul-17 24-Jul-17 103,410.00 0.22% 0.00%
Columns 12-Jul-17 24-Jul-17
CSWZ2FF-05 Rebar installation 12-Jul-17 18-Jul-17 29,572.00 0.06% 0.00%
CSWZ2FF-06 Formworks 19-Jul-17 23-Jul-17 11,955.00 0.03% 0.00%

1107 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ2FF-07 Concrete works 24-Jul-17 24-Jul-17 21,393.00 0.05% 0.00%
Second floor level 25-Jul-17 29-Aug-17
Columns 17-Aug-17 29-Aug-17
CSWZ2SF-05 Rebar installation 17-Aug-17 23-Aug-17 29,572.00 0.06% 0.00%
CSWZ2SF-06 Formworks 24-Aug-17 28-Aug-17 11,955.00 0.03% 0.00%
CSWZ2SF-07 Concrete works 29-Aug-17 29-Aug-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 25-Jul-17 29-Aug-17
CSWZ2SF-01 Formworks 25-Jul-17 2-Aug-17 95,166.00 0.20% 0.00%
CSWZ2SF-02 Rebar, tendons & duct installation 3-Aug-17 14-Aug-17 132,000.00 0.28% 0.00%
CSWZ2SF-03 Concrete works 15-Aug-17 16-Aug-17 170,296.00 0.36% 0.00%
CSWZ2SF-04 Post tensioning 17-Aug-17 29-Aug-17 103,410.00 0.22% 0.00%
Third floor level 30-Aug-17 4-Oct-17
Columns 23-Sep-17 4-Oct-17
CSWZ2TF-05 Rebar installation 23-Sep-17 28-Sep-17 29,572.00 0.06% 0.00%
CSWZ2TF-06 Formworks 30-Sep-17 3-Oct-17 11,955.00 0.03% 0.00%
CSWZ2TF-07 Concrete works 4-Oct-17 4-Oct-17 21,393.00 0.05% 0.00%
Slab, beams & stairs 30-Aug-17 4-Oct-17
CSWZ2TF-01 Formworks 30-Aug-17 7-Sep-17 95,166.00 0.20% 0.00%
CSWZ2TF-02 Rebar, tendons & duct installation 9-Sep-17 19-Sep-17 132,000.00 0.28% 0.00%
CSWZ2TF-03 Concrete works 20-Sep-17 21-Sep-17 170,296.00 0.36% 0.00%
CSWZ2TF-04 Post tensioning 23-Sep-17 4-Oct-17 103,410.00 0.22% 0.00%
Roof deck level 5-Oct-17 9-Nov-17
Columns 29-Oct-17 9-Nov-17
CSWZ2RD-05 Rebar installation 29-Oct-17 4-Nov-17 14,786.00 0.03% 0.00%
CSWZ2RD-06 Formworks 5-Nov-17 8-Nov-17 5,978.00 0.01% 0.00%
CSWZ2RD-07 Concrete works 9-Nov-17 9-Nov-17 10,696.00 0.02% 0.00%
Slab, beams & stairs 5-Oct-17 9-Nov-17
CSWZ2RD-01 Formworks 5-Oct-17 14-Oct-17 25,378.00 0.05% 0.00%
CSWZ2RD-02 Rebar, tendons & duct installation 15-Oct-17 25-Oct-17 35,200.00 0.07% 0.00%
CSWZ2RD-03 Concrete works 26-Oct-17 28-Oct-17 45,412.00 0.10% 0.00%
CSWZ2RD-04 Post tensioning 29-Oct-17 9-Nov-17 34,470.00 0.07% 0.00%
Upperroof deck level 11-Nov-17 15-Nov-17
Slab & beams 11-Nov-17 15-Nov-17
CSWZ2UD-01 Formworks 11-Nov-17 12-Nov-17 6,344.00 0.01% 0.00%
CSWZ2UD-02 Rebar installation 13-Nov-17 14-Nov-17 8,800.00 0.02% 0.00%

1108 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ2UD-03 Concrete works 15-Nov-17 15-Nov-17 11,353.00 0.02% 0.00%
Zone 3 20-Jun-17 4-Jan-18
Ground floor level 20-Jun-17 30-Jul-17
CSWZ3GF-02 Rebar installation 20-Jun-17 10-Jul-17 37,302.00 0.08% 0.00%
CSWZ3GF-01 Formworks 11-Jul-17 25-Jul-17 15,079.00 0.03% 0.00%
CSWZ3GF-03 Concrete works 26-Jul-17 30-Jul-17 26,984.00 0.06% 0.00%
First floor level 31-Jul-17 6-Sep-17
Slab, beams & stairs 31-Jul-17 6-Sep-17
CSWZ3FF-01 Formworks 31-Jul-17 9-Aug-17 80,026.00 0.17% 0.00%
CSWZ3FF-02 Rebar, tendons & duct installation 10-Aug-17 22-Aug-17 111,000.00 0.24% 0.00%
CSWZ3FF-03 Concrete works 23-Aug-17 24-Aug-17 143,204.00 0.30% 0.00%
CSWZ3FF-04 Post tensioning 26-Aug-17 6-Sep-17 86,958.00 0.18% 0.00%
Columns 26-Aug-17 6-Sep-17
CSWZ3FF-05 Rebar installation 26-Aug-17 31-Aug-17 24,868.00 0.05% 0.00%
CSWZ3FF-06 Formworks 2-Sep-17 5-Sep-17 10,053.00 0.02% 0.00%
CSWZ3FF-07 Concrete works 6-Sep-17 6-Sep-17 17,989.00 0.04% 0.00%
Second floor level 7-Sep-17 15-Oct-17
Slab, beams & stairs 7-Sep-17 15-Oct-17
CSWZ3SF-01 Formworks 7-Sep-17 17-Sep-17 80,026.00 0.17% 0.00%
CSWZ3SF-02 Rebar, tendons & duct installation 18-Sep-17 30-Sep-17 111,000.00 0.24% 0.00%
CSWZ3SF-03 Concrete works 1-Oct-17 2-Oct-17 143,204.00 0.30% 0.00%
CSWZ3SF-04 Post tensioning 3-Oct-17 15-Oct-17 86,958.00 0.18% 0.00%
Columns 3-Oct-17 15-Oct-17
CSWZ3SF-05 Rebar installation 3-Oct-17 9-Oct-17 24,868.00 0.05% 0.00%
CSWZ3SF-06 Formworks 10-Oct-17 14-Oct-17 10,053.00 0.02% 0.00%
CSWZ3SF-07 Concrete works 15-Oct-17 15-Oct-17 17,989.00 0.04% 0.00%
Third floor level 16-Oct-17 22-Nov-17
Columns 11-Nov-17 22-Nov-17
CSWZ3TF-05 Rebar installation 11-Nov-17 16-Nov-17 24,868.00 0.05% 0.00%
CSWZ3TF-06 Formworks 18-Nov-17 21-Nov-17 10,053.00 0.02% 0.00%
CSWZ3TF-07 Concrete works 22-Nov-17 22-Nov-17 17,989.00 0.04% 0.00%
Slab, beams & stairs 16-Oct-17 22-Nov-17
CSWZ3TF-01 Formworks 16-Oct-17 25-Oct-17 80,026.00 0.17% 0.00%
CSWZ3TF-02 Rebar, tendons & duct installation 26-Oct-17 7-Nov-17 111,000.00 0.24% 0.00%
CSWZ3TF-03 Concrete works 8-Nov-17 9-Nov-17 143,204.00 0.30% 0.00%

1109 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CSWZ3TF-04 Post tensioning 11-Nov-17 22-Nov-17 86,958.00 0.18% 0.00%
Roof deck level 23-Nov-17 31-Dec-17
Columns 19-Dec-17 31-Dec-17
CSWZ3RD-05 Rebar installation 19-Dec-17 25-Dec-17 12,434.00 0.03% 0.00%
CSWZ3RD-06 Formworks 26-Dec-17 30-Dec-17 5,026.00 0.01% 0.00%
CSWZ3RD-07 Concrete works 31-Dec-17 31-Dec-17 8,995.00 0.02% 0.00%
Slab, beams & stairs 23-Nov-17 31-Dec-17
CSWZ3RD-01 Formworks 23-Nov-17 3-Dec-17 21,340.00 0.05% 0.01%
CSWZ3RD-02 Rebar, tendons & duct installation 4-Dec-17 16-Dec-17 29,600.00 0.06% 0.02%
CSWZ3RD-03 Concrete works 17-Dec-17 18-Dec-17 38,188.00 0.08% 0.00%
CSWZ3RD-04 Post tensioning 19-Dec-17 31-Dec-17 28,986.00 0.06% 0.00%
Upperroof deck level 1-Jan-18 4-Jan-18
Slab & beams 1-Jan-18 4-Jan-18
CSWZ3UD-01 Formworks 1-Jan-18 2-Jan-18 5,335.00 0.01% 0.00%
CSWZ3UD-02 Rebar installation 3-Jan-18 3-Jan-18 7,400.00 0.02% 0.00%
CSWZ3UD-03 Concrete works 4-Jan-18 4-Jan-18 9,547.00 0.02% 0.00%
Finishing Works 28-Jun-17 20-Sep-18 12,516,492.10 26.56%
Zone 1 28-Jun-17 26-May-18
Ground floor level 28-Jun-17 16-Nov-17
CFWZ1GF-01 Masonry works 28-Jun-17 5-Sep-17 74,960.00 0.16% 0.00%
CFWZ1GF-02 Waterproofing at wet areas 2-Aug-17 14-Sep-17 2,308.00 0.00% 0.00%
CFWZ1GF-03 Finishes 14-Aug-17 28-Oct-17 408,192.00 0.87% 0.00%
CFWZ1GF-04 Doors & windows installation 24-Sep-17 30-Oct-17 258,514.00 0.55% 0.00%
CFWZ1GF-05 Metal works 26-Sep-17 30-Oct-17 152,386.00 0.32% 0.00%
CFWZ1GF-06 Specialties 31-Oct-17 16-Nov-17 68,973.00 0.15% 0.00%
First floor level 16-Aug-17 17-Mar-18
CFWZ1FF-01 Masonry works 16-Aug-17 24-Oct-17 149,920.00 0.32% 0.00%
CFWZ1FF-02 Waterproofing at wet areas 20-Sep-17 7-Nov-17 2,885.00 0.01% 0.00%
CFWZ1FF-03 Finishes 30-Sep-17 13-Dec-17 182,530.00 0.39% 0.04%
CFWZ1FF-04 Doors & windows installation 9-Nov-17 16-Dec-17 114,895.00 0.24% 0.05%
CFWZ1FF-05 Metal works 15-Nov-17 25-Dec-17 22,855.00 0.05% 0.01%
CFWZ1FF-06 Special Construction (Steam Bath room equip., Sauna room eq 15-Nov-17 17-Mar-18 663,350.00 1.41% 0.08%
CFWZ1FF-07 Specialties 14-Dec-17 11-Jan-18 30,655.00 0.07% 0.00%
Second floor level 10-Oct-17 31-Jan-18
CFWZ1SF-01 Masonry works 10-Oct-17 18-Dec-17 284,848.00 0.60% 0.06%

1110 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CFWZ1SF-02 Waterproofing at wet areas 8-Nov-17 26-Dec-17 2,885.00 0.01% 0.00%
CFWZ1SF-03 Finishes 14-Nov-17 17-Jan-18 172,530.00 0.37% 0.04%
CFWZ1SF-04 Doors & windows installation 20-Dec-17 20-Jan-18 114,895.00 0.24% 0.00%
CFWZ1SF-05 Metal works 26-Dec-17 28-Jan-18 22,855.00 0.05% 0.00%
CFWZ1SF-06 Specialties 18-Jan-18 31-Jan-18 30,655.00 0.07% 0.00%
Third floor level 12-Dec-17 16-Apr-18
CFWZ1TF-01 Masonry works 12-Dec-17 13-Feb-18 224,880.00 0.48% 0.00%
CFWZ1TF-02 Waterproofing at wet areas 4-Jan-18 17-Feb-18 3,462.00 0.01% 0.00%
CFWZ1TF-03 Finishes 1-Feb-18 3-Apr-18 106,265.00 0.23% 0.00%
CFWZ1TF-04 Metal works 4-Mar-18 4-Apr-18 22,855.00 0.05% 0.00%
CFWZ1TF-05 Doors & windows installation 7-Mar-18 7-Apr-18 74,682.00 0.16% 0.00%
CFWZ1TF-06 Specialties 4-Apr-18 16-Apr-18 22,991.00 0.05% 0.00%
Roof deck level 17-Apr-18 22-May-18
CFWZ1RD-01 Masonry works 17-Apr-18 7-May-18 14,992.00 0.03% 0.00%
CFWZ1RD-02 Roof Waterproofing 5-May-18 10-May-18 151,592.00 0.32% 0.00%
CFWZ1RD-03 Finishes 6-May-18 20-May-18 42,506.00 0.09% 0.00%
CFWZ1RD-04 Metal works 7-May-18 17-May-18 7,618.00 0.02% 0.00%
CFWZ1RD-05 Doors installation 19-May-18 22-May-18 11,490.00 0.02% 0.00%
Upperroof deck level 12-May-18 26-May-18
CFWZ1UD-01 Roof Waterproofing 12-May-18 15-May-18 16,844.00 0.04% 0.00%
CFWZ1UD-02 Finishes 21-May-18 26-May-18 10,626.00 0.02% 0.00%
Zone 2 25-Jul-17 27-Aug-18
Ground floor level 25-Jul-17 17-Dec-17
CFWZ2GF-01 Masonry works 25-Jul-17 8-Oct-17 63,428.00 0.13% 0.00%
CFWZ2GF-02 Waterproofing at wet areas 10-Sep-17 23-Oct-17 9,430.00 0.02% 0.00%
CFWZ2GF-03 Finishes 19-Sep-17 27-Nov-17 605,709.00 1.29% 0.00%
CFWZ2GF-04 Metal works 24-Oct-17 27-Nov-17 35,285.00 0.07% 0.00%
CFWZ2GF-05 Wood & plastics 1-Nov-17 25-Nov-17 23,000.00 0.05% 0.00%
CFWZ2GF-06 Doors & windows installation 2-Nov-17 11-Dec-17 327,451.00 0.69% 0.12%
CFWZ2GF-07 Specialties 26-Nov-17 17-Dec-17 87,365.00 0.19% 0.06%
First floor level 30-Aug-17 24-Mar-18
CFWZ2FF-01 Masonry works 30-Aug-17 25-Nov-17 126,855.00 0.27% 0.00%
CFWZ2FF-02 Waterproofing at wet areas 24-Oct-17 16-Dec-17 2,811.00 0.01% 0.00%
CFWZ2FF-03 Finishes 11-Nov-17 5-Feb-18 403,806.00 0.86% 0.07%
CFWZ2FF-04 Metal works 25-Jan-18 10-Mar-18 44,106.00 0.09% 0.00%

1111 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
CFWZ2FF-05 Doors & windows installation 6-Feb-18 24-Mar-18 272,876.00 0.58% 0.00%
CFWZ2FF-06 Specialties 6-Feb-18 8-Mar-18 58,244.00 0.12% 0.00%
Second floor level 21-Oct-17 9-May-18
CFWZ2SF-01 Masonry works 21-Oct-17 21-Jan-18 241,025.00 0.51% 0.04%
CFWZ2SF-02 Waterproofing at wet areas 17-Dec-17 7-Feb-18 2,810.86 0.01% 0.00%
CFWZ2SF-03 Finishes 7-Jan-18 3-Apr-18 403,806.24 0.86% 0.00%
CFWZ2SF-04 Metal works 11-Mar-18 23-Apr-18 44,106.00 0.09% 0.00%
CFWZ2SF-05 Doors & windows installation 25-Mar-18 9-May-18 218,301.00 0.46% 0.00%
CFWZ2SF-06 Specialties 4-Apr-18 5-May-18 58,244.00 0.12% 0.00%
Third floor level 3-Dec-17 25-Jun-18
CFWZ2TF-01 Masonry works 3-Dec-17 5-Mar-18 190,283.00 0.40% 0.03%
CFWZ2TF-02 Waterproofing at wet areas 1-Feb-18 26-Mar-18 2,249.00 0.00% 0.00%
CFWZ2TF-03 Finishes 22-Feb-18 14-May-18 403,806.00 0.86% 0.00%
CFWZ2TF-04 Metal works 24-Apr-18 6-Jun-18 44,106.00 0.09% 0.00%
CFWZ2TF-05 Doors & windows installation 10-May-18 25-Jun-18 218,301.00 0.46% 0.00%
CFWZ2TF-06 Specialties 15-May-18 14-Jun-18 58,244.00 0.12% 0.00%
Roof deck level 19-May-18 27-Aug-18
CFWZ2RD-01 Masonry works 19-May-18 21-Jul-18 12,686.00 0.03% 0.00%
CFWZ2RD-02 Roof Waterproofing 17-Jun-18 29-Jul-18 128,270.00 0.27% 0.00%
CFWZ2RD-03 Finishes 26-Jun-18 13-Aug-18 161,522.00 0.34% 0.00%
CFWZ2RD-04 Metal works 14-Jul-18 19-Aug-18 8,821.00 0.02% 0.00%
CFWZ2RD-05 Doors installation 18-Jul-18 19-Aug-18 54,575.00 0.12% 0.00%
CFWZ2RD-06 Specialties 20-Aug-18 27-Aug-18 29,122.00 0.06% 0.00%
Upperroof deck level 30-Jul-18 19-Aug-18
CFWZ2UD-01 Roof Waterproofing 30-Jul-18 2-Aug-18 14,252.00 0.03% 0.00%
CFWZ2UD-02 Finishes 14-Aug-18 19-Aug-18 40,381.00 0.09% 0.00%
Zone 3 7-Sep-17 20-Sep-18
Ground floor level 7-Sep-17 24-Feb-18
CFWZ3GF-01 Masonry works 7-Sep-17 27-Nov-17 53,817.00 0.11% 0.00%
CFWZ3GF-02 Waterproofing at wet areas & Water tank 18-Oct-17 9-Dec-17 27,332.00 0.06% 0.01%
CFWZ3GF-03 Finishes 28-Oct-17 28-Jan-18 669,468.00 1.42% 0.11%
CFWZ3GF-04 Wood & plastics 5-Dec-17 28-Dec-17 46,000.00 0.10% 0.01%
CFWZ3GF-05 Doors & windows installation 12-Dec-17 17-Jan-18 361,920.00 0.77% 0.00%
CFWZ3GF-06 Metal works 21-Jan-18 24-Feb-18 29,671.00 0.06% 0.00%
CFWZ3GF-07 Specialties 1-Feb-18 18-Feb-18 96,562.00 0.20% 0.00%

1112 of 2424
WK-49
Activity ID Activity Name BL1 Start BL1 Finish Budgeted Cost Weighted %
7-Dec-17
First floor level 24-Oct-17 24-Apr-18
CFWZ3FF-01 Masonry works 24-Oct-17 24-Jan-18 107,635.00 0.23% 0.02%
CFWZ3FF-02 Waterproofing at wet areas 16-Dec-17 5-Feb-18 3,107.00 0.01% 0.00%
CFWZ3FF-03 Finishes 31-Dec-17 2-Apr-18 446,312.00 0.95% 0.00%
CFWZ3FF-04 Doors & windows installation 15-Feb-18 27-Mar-18 301,600.00 0.64% 0.00%
CFWZ3FF-05 Metal works 1-Mar-18 4-Apr-18 37,089.00 0.08% 0.00%
CFWZ3FF-06 Specialties 3-Apr-18 24-Apr-18 80,468.00 0.17% 0.00%
Second floor level 10-Dec-17 13-Jun-18
CFWZ3SF-01 Masonry works 10-Dec-17 12-Mar-18 204,507.00 0.43% 0.00%
CFWZ3SF-02 Waterproofing at wet areas 1-Feb-18 25-Mar-18 3,107.00 0.01% 0.00%
CFWZ3SF-03 Finishes 19-Feb-18 22-May-18 446,312.00 0.95% 0.00%
CFWZ3SF-04 Metal works 7-Apr-18 10-May-18 37,089.00 0.08% 0.00%
CFWZ3SF-05 Doors & windows installation 7-Apr-18 16-May-18 241,280.00 0.51% 0.00%
CFWZ3SF-06 Specialties