Author: Duncan Mellor & Angelo Bucon Publish Date: July 20, 2017
Since the release of Oracle Primavera P6 EPPM 15.2 (and later), a number of functions have been changed to
run as background tasks in Job Services. This includes functions such as Adding Baselines, Copying and
Pasting Projects and XML Exports.
Moving these tasks from the client to Job Services has benefits in performance and improved usability.
Users can now continue their work while requests that may take some time are executed in the background.
In this edition of Tips and Tricks, we will discuss the role of P6 Job Services, show you how to add and update
baselines, export projects as XML files, and give you tips on how to maintain data synchronicity between the
P6 Client and Database.
In P6 15.2 and beyond, the image of the project on the client is NOT the one that gets updated by the Job
Services task that adds the Baseline. It is the image of the project stored in the database that is updated.
This means that the image of the project on the client and the image of the project in the Primavera database
are not in sync until there is an explicit (F5) refresh executed when the Job Services task is completed. This
process can be seen in image the image below.
As discussed, beginning with P6 EPPM version 15.2, the Add Baseline functionality was changed to work as a
background job service.
When a user is performing this operation in the P6 Professional client, a pop-up window shows the message
Job has been scheduled. See Job Status for more details.