The cost of electricity

What India needs to do for reliability, security


and affordability of electric supply
day when solar is available and a rapid ramp
up in the evening. This lowers the capacity
factor of dispatchable generators. The DNEP
acknowledges technological and operational
challenges posed by the integration of VRE
into the grid. It highlights the loss of genera-
tion efficiency, high maintenance cost, and
R.B. Grover
higher emissions of combined cycle plants
due to cycling and ramping. It details grid in-
The cost of electricity can be divided into tegration cost of VRE in qualitative terms.
plant-level costs, grid-level costs, and other A recent report by the Department of En-
costs. Plant-level costs consist of capital, op- ergy, U.S., highlights another element that is
eration and maintenance, and fuelling cost. smoothening of transients in the grid by the
Capital cost is reflected in the cost of genera- inertia of the rotating mass present in
tion by way of interest on debt and return on thermal power plants, while solar plants
equity. For nuclear power plants, capital cost have no such feature.
is high, but fuelling cost is low. System costs have been
For coal-fired power plants, quantified by the Nuclear En-
capital cost is low, but fuelling ergy Agency of the OECD and
cost is high. The capital cost of differ across countries de-
solar and wind is continuously pending on the extent of pres-
decreasing; fuelling cost is nil. ence of sources like natural
GETTY IMAGES

Electricity reaches a con- gas. According to this quanti-


sumer through the grid. Laying fication, system cost of VRE
a grid needs significant invest- sources is much higher than
ment. A distributor buys elec- nuclear and coal. True parity
tricity from a generator, adds of VRE sources will be
transmission and distribution charges, a achieved only when the sum of generation
charge to recover technical losses, operating cost and system cost matches with that from
expenses, and his profit to determine the tar- dispatchable sources.
iff to be charged from a consumer. Since sev-
eral generators are connected to the grid, in- Other costs
teraction with the grid and grid-management Other costs include those arising from the in-
policies influence the working of a generator. fluence of electricity generation on health,
At present, electricity markets do not assign influence on existing generation capacity
any price to system effects, that is, to the due to adding new capacity, cost of acci-
complex interactions among various gener- dents, security of supplies and net energy
ators connected to the grid. gain for society.
In recent years, a large capacity based on In the Economic Survey 2016-17 (Volume
variable renewable energy (VRE) sources has 2), an attempt has been made to estimate
been connected to the grid. These sources grid-level costs and some other costs. The
are intermittent, but get priority feed-in due survey uses the term social cost of carbon
to nil fuelling cost. A grid manager must en- to represent economic cost of greenhouse
sure that enough dispatchable generation ca- gas emissions. It also adds health costs, costs
pacity is connected to the grid to meet the of intermittency, opportunity cost of land,
peak load in the evening when solar power is cost of government incentives and cost
not available. Dispatchable generation is arising from stranded assets. It, thus, in-
provided by baseload technologies like coal cludes not only system cost, but a significant
and nuclear, and by large hydropower. part of other costs as well. It estimates that
Grid-level costs have several components: the total social cost of renewables was 11 per
grid connection, grid extension and rein- kWh, around three times that of coal.
forcement, short-term balancing costs, and Conventional metrics like levellised cost
long-term costs for maintaining adequate of electricity generation cannot be relied on
back-up supply. VRE sources demand much to compare intermittent and dispatchable
higher back-up, grid connection and rein- electric supply options. Indias electricity re-
forcement costs. This aspect needs attention quirements are enormous. It doesnt need a
during policy formulation. technology versus technology debate, but a
In December 2016, the Central Electricity policy framework that integrates all low-car-
Authority issued a draft national electricity bon energy technologies with coal in a man-
plan (DNEP), which refers to system effect ner that ensures reliability and security of
and resulting system cost at several places. electric supply along with affordability and
The emphasis on VRE sources without climate-resilient development.
any investment in energy storage has conver-
ted daily load profile for dispatchable gener- R.B. Grover is Homi Bhabha Chair, Department of
ating stations into a duck curve, that is, Atomic Energy, and member, Atomic Energy
with a reduced electricity load during the Commission