PROGRESS:
Due to the nature of the job going on in Gas Processing Plant II (GPP II), I was
advised to join the project because of its relevance to my field.
Introduced to Mr Seyi Head of GPP II project
Introduction to Electrical & Instrumentation (E&I) team in charge of GPP II headed
by Mr Aliu
Introduction to Abergyl (E&I contractor in charge of GPP II)
Liaised with contractor in connecting pneumatic tubing to Level Control valve
GPP II tour by Mr Aliu
Introduction to the Cryogenic facility (low temperature facility)
Identification of Instruments on site
Identification of Gas analyser
Was told that the plant runs on Delta V program
Identification of cable conduits where cable runs

PROBLEMS:
No problems were encountered
PLANS:
Looking forward to working with the contractors on executing the project