OR ASSIGNMENT 1 09.10.

2017

Q.1 Solutions:
According to the question objective function is to minimize the total leasing cost.
Constraints are:
1) For each month, sum of the leased space in the previous months, leased in the current month and leased
for the coming periods is greater than or equal to the required space of that month.
2) It is not possible to lease more than remaining months to the planning period.
3) Constraints are non-negative.

Equations:
Objective Function:
Eq.1 -

Cost = 65 5=1 (, 1) + 100 4=1 (, 2) + 135 3=1 (, 3) + 160 2=1 (, 4) + 190 (, 5)

Constraints:

1) 5=1 (1, ) 30,000


2) 5=2 (1, ) + 4=1 (2, ) 20,000
3) 5=3 (1, ) + 4=2 (2, ) + 3=1 (3, ) 40,000
4) 5=4 (1, ) + 4=3 (2, ) + 3=2 (3, ) + 2=1 (4, ) 10,000