Professional Documents
Culture Documents
Item Activity Unit Scope From (Chainage) Weight TO (Chainage) Total Done To Date Physical Progress (%)
Item Activity Unit Scope From (Chainage) Weight TO (Chainage) Total Done To Date Physical Progress (%)
TOTAL
TO PHYSICAL
ITEM ACTIVITY UNIT SCOPE DONE TO
(CHAINAGE) (CHAINAGE) WEIGHT PROGRESS
DATE
(%)
0+000 4+500 4.5
Site clearance Km 35 13.3 5.054
0+000 8+800 8.8
7 Base
km 35 0+000 4+500 4.5 9 1.16
1st Seal
9
(14/20) km 35 4.5 5 0.64
2ND Seal
10
(6/10) km 35 4.5 5 0.64
Cross pipe
11 culvert
(1200mm) m 271 0 5 0
Cross pipe
12 culvert
(900mm) m 1680 0+000 3+500 46 5 0.14
Access pipe
13 culvert
(600mm) m 840 0+000 3+500 420 5 2.50
Road
14 Km 35 0 5 0
Furniture
100 22.37
FROM
TO
ITEM ACTIVITY UNIT SCOPE TOTAL PHYSICAL
(CHAINAG (CHAINAG
E) DONE TO WEIGHT PROGRESS
E)
DATE (%)
Site clearance
1 Km 34 0+000 10+800 10.8 7 2.22
Earthworks(fill)
3 Km 34 0+000 10+400 10.4 8 1.65
Earthworks(Cut)
4 Km 34 0+000 10+400 10.4 8 2.45
Subgrade
5 Km 34 0+040 9+500 9.5 8 2.24
Base
7 km 34 1+300 3+420 2.1 9 0.56
Prime Coat
8 km 34 0+000 3+420 3.5 5 0.51
Access pipe
culvert (600mm)
13 m 816 0+000 6+700 340 5 2.08
Road Furniture
14 Km 34 0 5 0.00
100 16.17