FOR
SLAB ON GRADE
METHOD OF STATEMENT
FOR SLAB ON GRADE
A. Clean the area of any loose materials prior to start any work
make sure that the compacted fill to received concrete is
approved by the consultant Engineer.
B. Check the dimensions and elevations from the approved shop
drawing.
C. Apply termite control according to manufacturers
recommendation by using spray on the backfilled soil to
received concrete and follow the time limit as per
2. Curing
A. Keep surfaces continuously moist for not less than seven days
with water.
END