Professional Documents
Culture Documents
Int Payment Certificate
Int Payment Certificate
Int Payment Certificate
Interim payments occur through out the construction period. The primary
mechanism by which the contractor gets paid for the work carried out. This
becomes the cash how between the employees at the pre - determined intervals.
(monthly)
These payments are determined by the value of work carried out by the
contractor during this period. In general this may call monthly valuations.
Sometimes the interim valuations can be called stage payments or milestone
payments paid at specific times when the contractor achieves the various stages
of completion ( eg : substructure, ground floor level, wall & floor, finishes of
ground floor, 1st floor )
Retention money - Deduct 10% of work done from each IPC and
the limit of retention is 5% (5% of the contract sum)
Retention money is kept to reduce the risk of any defects done by
the contractor.
Project :
Client :
Contractor :
Contractor sum : Rs (excluding VAT)
Maximum retension money : Rs Date of commencement .
(5% of the contract sum)
Mobilization Advance received : Rs Date of completion ..
5. Fluctuations Rs.
sub total
Deductions
Chief Quantity surveyor Principle Architect
Proposed office building for ICBT at Bambalapitiya
Rupees one million eight hundred and fourteen thousand and two hundred and
twenty eight and ninety four cents is due to the contractor in respect of interim
payment certificate No.6
..
Chief Quantity Surveyor Principal Architect
Key Issues in Interim and final valuations
Since the quantities set out in the BOQ ( CTAD/SBD/02) condition of contact
clause 14.1)