Perhitungan Kabel, Pipa, dan Selang Plastik

Sa. Kabel

Kabel KWh Utama : (3x40)+(3x40)+180= 420 cm

Fasa: 40+40= 80 cm

Netral:40+40= 80 cm

Ground: 40+40+200= 280 cm

Grup 1:

Utama: (3122)+(363)+(3x43)= 684 cm

Fasa: 122+63+43= 228 cm

Netral: 122+63+43= 228 cm

Ground: 122+63+43= 228 cm

kamar 1 : (3x20)+(4x50)+(3x69)(3x115)+(3x50)+(2x61)= 1084 cm

Fasa: 20+(2x50)+69+115+50+61= 415 cm

Netral: 20+50+69+115+50+61= 365 cm

Ground: 20+50+69+115+50= 304 cm

Dapur : (4x50)+(2x40)+(2x15)= 310 cm

Fasa: (2x50)+40+15= 155 cm

Netral:50+40+15= 105 cm

Ground: 50 cm

Teras Belakang :(2x26)+(2x43)+(2x50)+(2x68)+(2x126)= 626 cm

Fasa: 26+43+(2x50)+68+126= 363 cm

Netral: 26+43+68+126= 263 cm


Grup II:

Utama: (3x122)+(353)+(3x70)+(3x112)+(3x50)= 1221 cm

Fasa: 122+53+70+112+50= 407 cm

Netral: 122+53+70+112+50= 407 cm

Ground: 122+53+70+112+50= 407 cm

Ruang Tamu dan Teras Depan : (3x50)+(3x50)+(3x53)+(2x10)+(2x75)+(2x125)=


879 cm

Fasa: 50+(3x50)+(2x53)+10+75+125= 516 cm

Netral : 50+53+10+75+125= 313 cm

Ground: 50 cm

Kamar 2: (3x30)+(5x74)+(5x50)+(3x62)+(3x52)+(3x50)+(2x61)= 1324 cm

Fasa: 30+(3x74)+(3x50)+(2x62)+(3x52)+(3x50)+61= 893 cm

Netral: 30+74+50+62+61= 277 cm

Ground: 30+74+50= 154 cm

1. Total kabel keseluruhan : 420+684+1084+310+626+1221+879+1324= 6548 cm

= 65,48 m

Total kabel keseluruhan ditambah 10% = 65,48+(65,48x0,1)= 65,48+6,548=


72,03 m

2. Total kabel Fasa : 80+228+415+155+363+407+516+893= 3057 cm = 30,57m

Total kabel fasa ditambah toleransi 10% = 30,57+(30,57x0,1) = 30,57+3,057 =


33,63 m
3. Total kabel netral : 80+228+365+105+263+407+313+277= 2038 cm = 20,38m

Total kabel netral ditambah 10% = 20,38+(20,38x0,1)= 20,38+2,033 = 22,42 m

4. Total kabel ground : 220+228+304+50+407+50+154= 1453 cm = 14,53m

Total kabel ground ditambah 10% = 14,53+(14,53x0,1)= 14,53+1,453= 15,98


m

b. Pemipaan

Pipa KWh 180+40+40= 260cm =2,6 m

Pipa Grop1

=120+60+40+40+20+40+65+115+45+60+45+40+15+20+40+45+65+120=
995cm = 9,95 m

Pipa Grop 2

= 120+150+70+110+45+45+45+50+10+70+120+30+70+45+60+50+45+60=
1195cm = 11,95 m

Total Keseluruhan Pipa = 2,6+9,95+11,95= 24,5 m