Professional Documents
Culture Documents
Example-Site Investigation Factual Report
Example-Site Investigation Factual Report
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
TABLE OF CONTENT
Page
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDICES
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
1.0 INTRODUCTION.
This report presents the result of the subsurface exploration for Additional Soil Investigation
Factual Report For Rapid Project Refinery Process Area.
The work was carried out in accordance with the drawings and specifications given by the
Personnel of Messrs. Technip Geoproduction (M) Sdn Bhd. The site investigation works was
carried out accordance to the British Standard Code of Practice BS 5930: 1999 Code Practice
for Site Investigation and laboratory tests as per BS 1377: 1990 or otherwise instructed by the
client or mentioned in this report.
2. To carry out Standard Penetration Test (SPT 63.5kg hammer having a free fall of
760mm) to determine the natural bearing resistance of the subsoil.
3. To obtain disturbed and undisturbed soil samples for carrying out the laboratory tests to
determine the natural and relevant physical properties of the subsoil pertaining to the
site.
4. To carry out Field Vane Shear Test to measure the in-situ shear strength of the soil.
5. To carry out Trial Pits Test to observe the true soil conditions.
7. To carry out Earth Resistivity Test in getting the knowledge for the necessary
earthing installation.
8. To carry out the Thermal Resistivity for the purpose ensuring the safe design of buried
high voltage electric cable.
9. To carry out the Downhole PS logging survey to obtain the geophysical properties of
soil at sites.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
3.1 GENERAL
Field exploration programme was conducted during the period of 05th August 2013 to
26th August 2013. The programme was supervised by our personnel from our office.
to be done for the design of the foundation for the proposed project.
The Boring equipment used was Rotary Drilling Rig which is capable of
boring and drilling to the depth about 120 meters. These boring rigs are also
suitable for advancing the borehole, sampling, in-situ testing and rock drilling in
accordance with the relevant specifications of each of these operations.
Soil drill was carried out by the rotary action of drill bit attached to the bottom
of a hollow rod, which cuts/discharges all material within the diameter of
borehole washed to the ground surface by drilling fluid pumped down the
drilling rod. Normally the drill bit is rarely allowed to extend more than 150mm
ahead of the bottom of the casing (if casing is used). Advancing of the borehole
is using drill rods with suitable drill bit and casing or where permitted, proper
drilling fluids. Advancing of the borehole will be such that the disturbance to
and contamination of the soil(s) immediately below the borehole will be kept to
minimum.
Casing was required in the soft or cohesionless soils, but is often omitted in
stiff, cohesive soils when only small representative samples are desired.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
i. Disturbed Sample
Disturbed samples may be obtained by any means as long as the soil sample
obtained is representative and unchanged in the constituent contents. After
the completion of the test, the sampler tube is removed and disassembled to
provide disturbed but representative samples.
Disturbed samples were taken from continuous sampling and split barrel
samples in conjunction with penetration resistance tests for purpose of
laboratory soil classification.
The procedure for rock drilling shall be in accordance with British Standard
Code of Practice BS 5930 Site Investigation. The diameter of core
acceptable shall be 54.00mm diameter (NMLC or NWX, NWM core barrels
where X and M refers to the design of corebit).
The Total Core Recovery (TCR) mean the ratio of the total length of good
quality core over the drilling length expressed the nearest 5%. Rock Quality
Designation (RQD) was the ratio of the total length of the good quality core
each exceeding 100mm in length over the drilling run correct to circular
circumference or in the case of broken rock fragment assembled to form
cores with circular circumference.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
The measurement of water table in the boreholes was done using either a
measuring tape or tape rod diameter or dip-meter as directed by the Client.
The recordings were repeated daily while boring for the drilled hole in
progress and were taken in the following time intervals: -
The water levels recorded in the borehole logs were levels observed in these
investigation holes during the period of the site investigation. Such
observed levels may not necessarily be the actual groundwater levels that
are subject to seasonal fluctuations from time to time.
For boreholes involving impervious stratum, the casing top was capped
overnight to prevent entry of rainwater and subsurface water.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
Generally, is carried out in all types of soil except the very soft and soft clays, at
1.5m intervals or change of strata or as instructed by the S.O. representative. In
case of soft clay, vane shear test shall be carried out instead of the SPT.
The value of the N as defined in the B.S. method was reported together with the
number of blow counts for each 75mm penetration of the sampling tube. The
blow counts for the first 150mm penetration (the seating drive) which do not
contribute the value of N was also included.
Two examples are 2,3,6,7,10,19 will give N=42 and 10,12,35 15/25mm will
give N=50/100mm. When a penetration resistance of 50 blows or 150mm
penetration was encountered in a seating drive, the test would stop and the SPT
value would be N*=50/150mm. The soil samples recovered from the split barrel
were preserved as disturbed samples as disturbed samples for subsequent
testing.
The vane is forced into the ground either from the ground surface or from the
bottom of a borehole. For penetration vane testing, the vane is housed in a
protective shoe to protect it from damage by stones or obstructions. At the
desired depth, the vane is pushed a short distance out of the housing into the
undisturbed soil by means of the torque rod, which runs inside the extension
tube to the surface. Once the vane is in position, a torque is applied through the
extension rod.
The readings were converted to kN/m2 by using the calibration graph attached
in Appendix D. The dimension of the vane used was 65.00mm diameter and
110.00mm in length. The final results, Su, of various depths were presented in
Appendix D - Field Vane Shear Test Results.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
The excavation of trial pits or trenches is often the most efficient method for observing
the true soil conditions. Disturbed soil is more likely to be recognised, particularly
backfill. A trial pits can also be used for more intensive in-situ testing where necessary.
Colour photographs of side faces should be taken whenever possible, with a prominent
scale marker, and a method of identifying the photographed face on the key plan. Where
sampling is necessary, it can be carried out either from disturbed samples obtained by
excavation, or open-tubes driven into the base or side face. The exact location and
orientation of the sample relative to the pit floor and walls must be recorded.
The equipment used for the piezocone test follows the British Standard Code of Practice
BS 1377 : Part 9 : 1990 and the International Reference Test Procedure for the Cone
Penetration Test (CPT).
The cone has transducers to measure cone resistance, local friction, water pressure and
uniaxial inclination. Cones are calibrated by manufacturer. A filter element
(Polypropylene) with diameter 35mm one size located in the cylindrical extension above
the base of the cone allows the pore water pressure generated during the penetration to be
measured by means of a pressure transducer located in the piezometer tip (u2 type cone).
In order to ensure that pore pressure measurements are not affected by the presence of air
in the measuring transducer, a de-airing procedure is carried out as required. The filters
are saturated by de-aired silicon or glycerin. A new filter is recommended for each
sounding location. Please note that following the initial de-airing procedure, it will only be
repeated if the cone is removed from the water into air, or at the beginning of each
working day, whichever is first.
The data acquisition system is Geomils GME 500 acquisition system. Signals from the
cone are transmitted to the GME 500 system via a cable threaded through the sounding
tubes. Depth registration is provided by an event marker activated via the action of the
hydraulic rams. The equipment provides:
a. A continuous listing (10 mm interval) of all measured parameters (cone resistance, local
friction, pore water pressure and inclination) recorded inside computer memory.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
The jacking unit is a 100 KN twin cylinder hydraulic ram with 120 KN upward forces.
The jacks, data acquisition and all accessories are mounted on a self-propelled crawler
chassis. The total weight of the unit is approximately 20 ton, additional reaction can be
provided by screw anchors installed using a hydraulic turning device.
The method use to carry out the test was Wenner 4 pin method. The common test type is
shown in Figure 3-1. The Wenner four pin methods is considered more accurate and
economic than the other methods, provided a current source of sufficient power is used.
Figure 3-1
Readings are usually taken at probe spacing of 2, 4, 6, 8, 10 and 20m. If the testing is
being performed for the purposes of ground potential rise (GPR) studies or for substation
design, readings up to 30 meter probe spacing should be performed. The calculated soil
resistivity is the average of the soil Resistivity from the surface to a depth equivalent to
the probe spacing. For example, a probe spacing of 20 metre between each probe will
provide the average soil resistivity between the surface and a depth of 20 metre.
In homogeneous isotropic earth the resistivity will be constant. However, if the earth is
non-homogeneous and the electrode spacing varied, a different value of resistivity (a)
will be found for each measurement. This measured value of resistivity is known as the
apparent resistivity. The apparent resistivity is a function of the array geometry, measured
voltage (v), and injected current (I).
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
For the arrays described in the previous section the apparent resistivity is found from the
field measurements using the following formulae.
The purpose of the soil thermal conductivity and temperature measurement is for the
purpose of ensuring the safe design of the buried high voltage electric cable. The
measurements are carried out at the locations specified by the client and at various depths
as required by clients instruction.
Thermal Resistivity conducted during 16th September 2013 until 22nd September 2013.
The results presented in Appendix H Thermal Conductivity / Thermal Resistivity
Result.
Downhole PS Logging survey conducted during the period of 20th October 2012 to 23rd
October 2012.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
Both disturbed and undisturbed samples were obtained at various depths and at every change of
soil strata for the purpose of identification, classification and testing. The following laboratory
tests were carried out in our laboratory in accordance with the British Standard Code 1377:
1990.
The results of the laboratory soil test are summarised in the Summary of Laboratory Test Result
as presented in Appendix J.
Soil Classification Test was conducted in accordance to BS: 1377. Soil Classification Test
was determined of basic physical properties. The tests are required for the classification
of soil in accordance with BS 5930. The test was included as follow:-
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
This test follows BS 1377: Part 2: 1990 Method 7. The bulk density of a soil is the
mass per unit volume of the soil including any water it contains, expressed in
Mg/m3. The linear measurement method 7.2 was used in this project for sample
obtained from undisturbed sampling method.
A sieve analysis consists of shaking the soil through a stack of wire screens with
opening of known sizes: the definition of particle diameter for a sieve test is,
therefore, the side dimensions of a square hole. The hydrometer method is based on
strokes equation for the velocity of a freely falling sphere: the definition of particle
diameter for hydrometer test is, therefore the diameter of a sphere of the same
density, which falls at the same velocity, as the particle is question. The test
procedure, which should be followed, depends on the soil in question. If nearly all it
grains are so large that they cannot pass through the square openings at 0.074mm
(No. 200 screen), the sieve analysis is preferable. For those soils, which are nearly
all finer than a No. 200 screen, the hydrometer test is recommended. Grained size
analysis has been widely used as a mean for identification and classification of soils.
d. Atterberg Limit
Atterberg Limit Determination Test was conducted in accordance to BS: 1377: Part
2: 1990 Test 4 & 5. The Liquid & Plastic Limit was determined to furnish basis for
the classification and identification of fine-grained cohesive soils. The liquid limit
defines the boundary lectures the liquid and plastic states. It is the water content at
which the soil has such smaller shear strength that it flows to close grove of
standard width (13mm) when jarred in a specific manner. The plastic limit defines
the boundary between the plastic and semi-solid states; it is the water content at
which the soil begins to crumble when rolls into threads of specific size (3mm). The
amount of water which must be added to change a soil from its plastic limit to its
liquid limit is measured by the Plasticity Index which is equal to the limit minus
the plastic limit. The natural moisture content at the time of testing was also
presented in the data.
e. Linear Shrinkage
Linear Shrinkage can be defined as the change in the length of a bar sample of soil
when dried (soil sample passing through 425m sieve test), from its Liquid Limit,
expressed as percentage (%) of the initial length ( l0 ). It can be used for soil of low
plasticity including silts, as well as for clays. The test can be calculated from the
equation:-
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
f. Specific Gravity
The odometer consolidation test is used for the determination of the consolidation
characteristics of soil of low permeability. Two parameter normally required are :-
The compressibility of the soil (expressed in terms of the coefficient of volume change)
which is measure of the amount by which the soil will compress when loaded and allowed
consolidating.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
The test is carried out by applying a sequence of five vertical loading and two unloading
to laterally confined specimen having a height of 20mm, and 50mm diameter. The
vertical compression under each load is observed over a period of time. Since no lateral
deformation is allowed, it is a One Dimensional Test, from which the One Dimensional
Consolidation parameter are derived, other parameters that are determined from the test
are the pre-compressions stress, Pc and compressions index Cc.
Point load test is an indirect method to determine unixial compressive strength (UCS) of
a sample. Sample is placed in between conical steel platens and loaded under
compression. Using correlation UCS 20 x Is (ISRM, 1985) , point load strength is
converted to unixial compressive strength. Equipment used is ELE (England) Point Load
apparatus. Testing procedures are as ISRM (1985) and samples tested were irregular
blocks of suitable size.
Uniaxial compressive strength test of intact rock often needed properties in engineering
designs of structures in rock. The test is carried out on intact rock with no discontinuities
and yields data on the rock materials properties. The length to diameter ratio of 2:1 is a
minimum for cylinders.
The Compaction Test is carried out to obtain relationships between compacted dry
density and soil moisture content, using two magnitudes of manual compactive effort, or
compaction by vibration. The method of this test is referred to BS 1377: 1990: Part 4.
Compaction of soil is the process by which the solid particles are packed more closely
together, usually by mechanical means, thereby increasing the dry density of the soil. The
dry density which can be achieved depends on the degree of compaction applied and on
the amount of water present in the soil. For a given degree of compaction of a given
cohesive soil there is an optimum moisture content at which the dry density obtained
reaches a maximum value. For cohesionless soils, optimum moisture content might be
difficult to define.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
Chemical Test was conducted in accordance to BS: 1377: Part 3: 1990.The test was
included as follow:-
a. PH Test
The PH Test was carried out in accordance with BS: 1377: Part 3 :1990 to
determine the PH value by electrometric method, which gives direct reading of the
pH value of a soil suspension water.
The organic matter content is carried out in accordance with BS: 1377: Part 3:
1990. The procedure covers the determination of the percentage by dry mass of
organic matters present in soil. The method, which uses dichromate oxidation, is
known as Walkley and Blacks method.
c. Sulphate Content
The sulphate content test is carried out in accordance with BS: 1377: Part 3:
1990. The procedures for determining the sulphate content of soil and ground
water. The results obtained give the sulphate content at the time of sampling only.
There are two methods for determining the sulphate contents of aggregate either
water-soluble sulphate content or total sulphate content.
d. Chloride Content
The chloride content test is carried out in accordance with BS: 1377:
Part 3: 1990. The test was carried out for determination of water-soluble and acid-
soluble chloride salt content in soil. Both procedures are based on Voldards
Method.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
5.0 COMMENTARY
The classification of the soil as represented in the report follows the BS 5930: 1981 Section 6
Description of soil and rocks.
It must be pointed out that, where the description of the samples from the laboratory results
differ from the field description of the soil layers, the laboratory results was supplemented and
in some instances, superseded the field description. The report is limited to the representation of
the soil information data gathered from the field works and laboratory test results. It should be
noted that natural moisture content and the ground level are subjected to seasonal variation and
the drainage condition of the adjoining areas.
With this site investigation report will give part of the information to enable the designer to
decide and design the foundation system of the proposed project.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
The interpretation of the results of the investigation and the final decision on the type of foundation
to adopt, rest with the Engineer.
Should there be any questions regarding our work, we should be pleased to discuss them with you.
Prepared by,
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX A
Site Plan
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX B
Additional Soil Investigation As-Built Layout
Refinery Process Area
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX C
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Project : Additional Soil Investigation Factual Report For RAPID Project - Refinery Process Area Borehole No. : PBH 10-1
Pages 1 of 3
Customer: : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(Ref)/2013
Date Started : 14/08/2013 Reduced Level : 1.835 m Coordinate, E : 67000.207 Type of Boring : Rotary Boring
Date Completed : 15/08/2013 Final Depth : 30.11 m N: -73400.016 Boring Diameter : 75mm to 125mm
Depth Sample Standard Penetration Test
Legend
Soil Description
From
R.L
& Sample Depth Recovery 75 75 75 75 75 75 'N' Remarks
(m) Lithology Ref. (m) Ratio mm mm mm mm mm mm Value
0.835
P1/ 1.00 250/450 1 1 1 2 2 3 8
Firm to stiff, medium brownish purple, slightly D2 to
gravelly slightly sandy CLAY. 1.45
-0.165
P2/ 2.00 200/450 2 3 2 3 3 3 11
Stiff, light purplish brown with medium yellow D3 to
mottled, sandy SILT. 2.45
-1.165
P3/ 3.00 300/450 1 1 1 2 1 2 6
Firm, medium brownish pale grey with medium D4 to
-1.665 purple mottled, SILT. 3.45
UD1 470/700
Medium brownish grey with medium purple 3.50
mottled, slightly sandy SILT. to
4.20
-5.665
P6/ 7.50 230/450 3 3 4 5 4 5 18
Medium dense, light greyish brown, silty D7 to
slightly gravelly fine to medium SAND. 7.95
-7.165
P7/ 9.00 290/450 2 3 3 3 3 3 12
Stiff, light brownish pale grey, slightly gravelly D8 to
sandy SILT. 9.45
Project : Additional Soil Investigation Factual Report For RAPID Project - Refinery Process Area Borehole No. : PBH 10-1
Pages 2 of 3
Customer: : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(Ref)/2013
Date Started : 14/08/2013 Reduced Level : 1.835 m Coordinate, E : 67000.207 Type of Boring : Rotary Boring
Date Completed : 15/08/2013 Final Depth : 30.11 m N: -73400.016 Boring Diameter : 75mm to 125mm
Depth Sample Standard Penetration Test
Legend
Soil Description
From
R.L
& Sample Depth Recovery 75 75 75 75 75 75 'N' Remarks
(m) Lithology Ref. (m) Ratio mm mm mm mm mm mm Value
Project : Additional Soil Investigation Factual Report For RAPID Project - Refinery Process Area Borehole No. : PBH 10-1
Pages 3 of 3
Customer: : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(Ref)/2013
Date Started : 14/08/2013 Reduced Level : 1.835 m Coordinate, E : 67000.207 Type of Boring : Rotary Boring
Date Completed : 15/08/2013 Final Depth : 30.11 m N: -73400.016 Boring Diameter : 75mm to 125mm
Depth Sample Standard Penetration Test
Legend
Soil Description
From
R.L
& Sample Depth Recovery 75 75 75 75 75 75 'N' Remarks
(m) Lithology Ref. (m) Ratio mm mm mm mm mm mm Value
Hard, light brownish purple, slightly gravelly P16/ 22.50 280/330 8 13 16 19 15/ 50/
D17 to 30mm 180mm
sandy SILT. 22.83
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Photo1 : DeepBoringLocationatPBH101
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Project : Additional Soil Investigation Factual Report For RAPID Project - Refinery Process Area Borehole No. : PBH 10-2
Pages 1 of 3
Customer: : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(Ref)/2013
Date Started : 12/08/2013 Reduced Level : 6.536 m Coordinate, E : 67400.125 Type of Boring : Rotary Boring
Date Completed : 12/08/2013 Final Depth : 33.14 m N: -73500.010 Boring Diameter : 75mm to 125mm
Depth Sample Standard Penetration Test
Legend
Soil Description
From
R.L
& Sample Depth Recovery 75 75 75 75 75 75 'N' Remarks
(m) Lithology Ref. (m) Ratio mm mm mm mm mm mm Value
P1/ 1.00 340/450 1 0 1 1 1 1 4
Soft to firm, medium to dark grey, slightly
D1 to
gravelly sandy SILT. 1.45
4.536
P2/ 2.00 250/450 1 0 1 0 1 1 3
Soft, yellowish grey, sandy CLAY. D2 to
2.45
0.536
P5/ 6.00 270/450 2 2 3 2 3 2 10
Stiff, medium reddish purple with pale grey D5 to
mottled, sandy SILT. 6.45
Project : Additional Soil Investigation Factual Report For RAPID Project - Refinery Process Area Borehole No. : PBH 10-2
Pages 2 of 3
Customer: : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(Ref)/2013
Date Started : 12/08/2013 Reduced Level : 6.536 m Coordinate, E : 67400.125 Type of Boring : Rotary Boring
Date Completed : 12/08/2013 Final Depth : 33.14 m N: -73500.010 Boring Diameter : 75mm to 125mm
Depth Sample Standard Penetration Test
Legend
Soil Description
From
R.L
& Sample Depth Recovery 75 75 75 75 75 75 'N' Remarks
(m) Lithology Ref. (m) Ratio mm mm mm mm mm mm Value
P9/ 12.00 280/450 2 2 3 4 5 4 16
Very stiff, medium purple with pale grey
D9 to
spotted, sandy SILT. 12.45
Project : Additional Soil Investigation Factual Report For RAPID Project - Refinery Process Area Borehole No. : PBH 10-2
Pages 3 of 3
Customer: : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(Ref)/2013
Date Started : 12/08/2013 Reduced Level : 6.536 m Coordinate, E : 67400.125 Type of Boring : Rotary Boring
Date Completed : 12/08/2013 Final Depth : 33.14 m N: -73500.010 Boring Diameter : 75mm to 125mm
Depth Sample Standard Penetration Test
Legend
Soil Description
From
R.L
& Sample Depth Recovery 75 75 75 75 75 75 'N' Remarks
(m) Lithology Ref. (m) Ratio mm mm mm mm mm mm Value
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Photo1 : DeepBoringLocationatPBH102
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX D
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Project : Additional Soil Investigation Factual Report For Rapid Project - Refinery Process Area
Client : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(REF)/2013
Equipment Type : Geonor H--10 Equipment Serial No. 1643 Vane Size, D : 65.00mm
Degree of
Degree of
Degree of
Degree of
Readings
Readings
Readings
Readings
Readings
Rotation
Rotation
Rotation
Rotation
Rotation
Gauge
Gauge
Gauge
Gauge
Gauge
18
2 0.0 102 202 2 0.0 102
4 1.0 104 204 4 1.5 104
6 2.0 106 206 6 3.0 106
8 3.5 108 208 8 4.0 108 16
Gauge Readings
26 14.0 126 226 26 9.0 126
28 15.0 128 228 28 9.0 128
30 15.0 130 230 30 9.0 130 10
32 16.0 132 232 32 9.0 132
34 17.5 134 234 34 9.0 134
36 18.0 136 236 36 9.0 136
8
38 18.0 138 238 38 138
40 18.0 140 240 40 140
42 18.0 142 242 42 142
44 18.0 144 244 44 144
6
46 18.0 146 246 46 146
48 18.0 148 248 48 148
50 18.0 150 250 50 150
52 18.0 152 252 52 152 4
54 18.0 154 254 54 154
56 156 256 56 156
58 158 258 58 158
60 160 260 60 160 2
Project : Additional Soil Investigation Factual Report For Rapid Project - Refinery Process Area
Client : Messrs. Technip Geoproduction (M) Sdn Bhd Job No. : GLSB/SI/2566-122(REF)/2013
Equipment Type : Geonor H--10 Equipment Serial No. 1643 Vane Size, D : 65.00mm
Degree of
Degree of
Degree of
Degree of
Readings
Readings
Readings
Readings
Readings
Rotation
Rotation
Rotation
Rotation
Rotation
Gauge
Gauge
Gauge
Gauge
Gauge
2 1.0 102 202 2 0.0 102
4 2.0 104 204 4 1.0 104 30
Gauge Readings
26 14.0 126 226 26 11.0 126
28 14.0 128 228 28 11.0 128
30 15.0 130 230 30 11.0 130
32 16.0 132 232 32 11.0 132
34 17.0 134 234 34 11.0 134
15
36 18.0 136 236 36 11.0 136
38 19.0 138 238 38 11.0 138
40 19.0 140 240 40 11.0 140
42 19.5 142 242 42 11.0 142
44 20.0 144 244 44 144
10
46 20.5 146 246 46 146
48 21.0 148 248 48 148
50 22.0 150 250 50 150
52 23.0 152 252 52 152
54 24.0 154 254 54 154
56 25.0 156 256 56 156 5
58 26.5 158 258 58 158
60 27.0 160 260 60 160
62 28.0 162 262 62 162
64 29.0 164 264 64 164
66 29.0 166 266 66 166 0
68 29.0 168 268 68 168 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Photo1 : FieldVaneShearTestatPBH173atdepth5.00m
Photo2 : FieldVaneShearTestatPBH173atdepth8.00m
OWNER REFERENCE
Project Package Originator Discipline Doc. Type Unit n Serial n
SUB12-
RAPID FE1 CVS ERP 0001 0002
GLB
CONTRACTOR REFERENCE Rev. Page
PETRONAS RAPID PROJECT Project Unit n Doc. Type Doc. Code Sequent. n
FEED PHASE B 25 / 30
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX E
Trial Pits
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
EndofNTP12at2.50m
TrialPitNo.
:NTP12
Project:AdditionalSoilInvestigationWorksForRapidProjectRefineryProcessArea.
GEOLAB (M) SDN BHD (210351-V)
Coordinate,E1836.6966
:
Foundation,Soil&ConcreteSpecialists
Client:Messrs.TechnipGeoproduction(M)SdnBhd Date:07thOctober2013 N4957.5089
:
Top
Mediumtodarkbrownwithpalegreystreaked,darkbrownanddarkgreyspotted,slightly gravellysandySILTwithalotofrootlet.
Yellowishbrownwithreddishbrownmottled,sandySILTwithatracesofrootlets.
EndofNTP13at3.00m
TrialPitNo.
:NTP13
Project:AdditionalSoilInvestigationWorksForRapidProjectRefineryProcessArea.
GEOLAB (M) SDN BHD (210351-V)
Coordinate,E1425.0711
:
Foundation,Soil&ConcreteSpecialists
Client:Messrs.TechnipGeoproduction(M)SdnBhd Date:07thOctober2013 N5802.8530
:
OWNER REFERENCE
Project Package Originator Discipline Doc. Type Unit n Serial n
SUB12-
RAPID FE1 CVS ERP 0001 0002
GLB
CONTRACTOR REFERENCE Rev. Page
PETRONAS RAPID PROJECT Project Unit n Doc. Type Doc. Code Sequent. n
FEED PHASE B 26 / 30
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX F
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
1.0 INTRODUCTION
2.0 SCOPES OF WORK
3.0 DESCRIPTION OF THE CONE PENETRATION TEST
3.1 EQUIPMENT
3.2 METHOD OF TEST
4.0 SUMMARY
4.1 SUMMARY OF CONE PENETRATION TEST
4.2 SUMMARY OF DISSIPATION TEST
5.0 REMARKS
APPENDICES
1. INTRODUCTION
Following an drawings and specification from MESSRS. TECHNIP
GEOPRODUCTION (M) SDN BHD, Soil Investigation Work which comprised 4 numbers of
Cone Penetration Tests & 3 numbers of Dissipation Test was carried out by Geolab (M) Sdn.
Bhd.
This report represents the results of 4 numbers of Cone Penetration Tests & 3 numbers
of Dissipation Tests results for the above mentioned project site. Please refer to item 4.1 for
Summary of Cone Penetration Tests & item 4.2 for Summary of Dissipation Tests.
The field work was carried out in accordance with the drawing and specification given by
the personnel of Client/Consultant. The site investigation works was carried out in accordance
with the British Standard Code of Practice BS 1377 : Part 9 : 1990 and the International
Reference Test Procedure for Cone Penetration Test (CPT).
Field testing program was conducted during the period of 23-08-2013 to 26-08-2013.
This program was supervised by our personnel from our office who was responsible for Cone
Penetration Test.
2. SCOPE OF WORK
The scope of work involved in this investigation includes the following: -
2.1 To carry out 4 numbers of Cone Penetration Tests and 3 numbers of Dissipation Tests
for Clients Engineer/Designer to determine/inetpret the Engineering Parameters of
the existing soil strata.
Page - 2
GLSB/CPT/17-134/2013 (02)
Page - 3
GLSB/CPT/17-134/2013 (02)
Dissipation Test
a. Dissipation test will be carried out at Consultant or Client Representatives specified
depth.
b. Dissipation test will be carried out by stopping penetration at specified depth and
record the in-situ pore pressure and time taken (This recording will be automatically
carried out by the GME 500 data acquisition systems program). During the
dissipation test process the rods will be clamped.
c. When the pore pressure dissipation reach more than 50% on as specified by the
consultant/client representative the dissipation test will be terminated by continuing
penetration (Continuing CPT).
Page - 4
GLSB/CPT/17-134/2013 (02)
Page - 5
4.0 Summary
4.1 Summary of Cone Penetration Test
ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Water Depth
Reference Date (Start / Tested Total Time Time for
No. Test No. at Start Time Cone ID Termination* Remarks
CPT Complete) Depth (m) (Min) U50 (Min)
(m) [BGL]
2.01 hr
5.0 REMARKS
Total 4 numbers of Cone Penetration Tests and 3 numbers of Dissipation Tests were
successfully completed at the Project of for ADDITIONAL SOIL INVESTIGATION
FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA on 26-08-
13. The tests results are presented in Appendix D & E.
Shall there be any queries about our works and our test results, please do not hesitate to
contact us.
Page - 6
APPENDIX A
8 WWW.HOGENT
WWW.HOGENT
.HOGENTOGLER.COM
OGLER.COM
APPENDIX B
Cone Specifications
Project : ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Owner : MESSRS PETROLIAM NASIONAL BERHAD (PETRONAS) Job No. GLSB/CPT/17-134/13 (02)
Client : MESSRS TECHNIP GEOPRODUCTION (M) SDN BHD W.O No.
Cone Resistance, qc (MPa) Sleeve Friction, fs (kPa) Pore Water Pressure, u2 (kPa) Friction Ratio, Rf (%)
0 4 8 12 16 20 0 100 200 300 400 500 0 150 300 450 600 750 0 2 4 6 8 10
0 0 0 0
U2 Uo
4 4 4 4
Depth (m)
8 8 8 8
12 12 12 12
16 16 16 16
20 20 20 20
Project : ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Owner : MESSRS PETROLIAM NASIONAL BERHAD (PETRONAS) Job No. GLSB/CPT/17-134/13 (02)
Client : MESSRS TECHNIP GEOPRODUCTION (M) SDN BHD W.O No.
Cone Resistance, qc (MPa) Sleeve Friction, fs (kPa) Pore Water Pressure, u2 (kPa) Friction Ratio, Rf (%)
0 4 8 12 16 20 0 100 200 300 400 500 0 150 300 450 600 750 0 2 4 6 8 10
0 0 0 0
U2 Uo
4 4 4 4
Depth (m)
8 8 8 8
12 12 12 12
16 16 16 16
20 20 20 20
Project : ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Owner : MESSRS PETROLIAM NASIONAL BERHAD (PETRONAS) Job No. GLSB/CPT/17-134/13 (02)
Client : MESSRS TECHNIP GEOPRODUCTION (M) SDN BHD W.O No.
Cone Resistance, qc (MPa) Sleeve Friction, fs (kPa) Pore Water Pressure, u2 (kPa) Friction Ratio, Rf (%)
0 4 8 12 16 20 0 100 200 300 400 500 0 150 300 450 600 750 0 2 4 6 8 10
0 0 0 0
U2 Uo
4 4 4 4
Depth (m)
8 8 8 8
12 12 12 12
16 16 16 16
20 20 20 20
Project : ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Owner : MESSRS PETROLIAM NASIONAL BERHAD (PETRONAS) Job No. GLSB/CPT/17-134/13 (02)
Client : MESSRS TECHNIP GEOPRODUCTION (M) SDN BHD W.O No.
Cone Resistance, qc (MPa) Sleeve Friction, fs (kPa) Pore Water Pressure, u2 (kPa) Friction Ratio, Rf (%)
0 4 8 12 16 20 0 100 200 300 400 500 0 150 300 450 600 750 0 2 4 6 8 10
0 0 0 0
U2 Uo
4 4 4 4
Depth (m)
8 8 8 8
12 12 12 12
16 16 16 16
20 20 20 20
Project : ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Owner : MESSRS PETROLIAM NASIONAL BERHAD (PETRONAS) Job No. : GLSB/CPT/17-134/13 (02)
Client : MESSRS TECHNIP GEOPRODUCTION (M) SDN BHD W.O No. : Duration : 60.50 min
CPT No. : PCPT 10-1 Test Date : 25-8-2013 Water Depth at Start Time : 1.200 m(B.G.L) T50 : 37.992 min
Test Depth : 6.50 m (B.G.L) Cone ID : C10CFIIP.G68 Equilibrium Pore Water Pressure : 0.053 MPa U50 : 0.213 MPa
Max
Min
T50 = 37.99 Min
Interval
100 0.372
80 0.308
Normalized Excess Pore Water Pressure, U (%)
70
60 0.245
50 0.213 MPa
40 0.181
30
20 0.117
10
0 0.053
0.01 0.10 1.00 10.00 100.00 1000.00 10000.00
Time, t (min)
Project : ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Owner : MESSRS PETROLIAM NASIONAL BERHAD (PETRONAS) Job No. : GLSB/CPT/17-134/13 (02)
Client : MESSRS TECHNIP GEOPRODUCTION (M) SDN BHD W.O No. : Duration : 30.00 min
CPT No. : PCPT-10-2 Test Date : 24-8-2013 Water Depth at Start Time : 1.200 m(B.G.L) T50 : 1.823 min
Test Depth : 7.50 m (B.G.L) Cone ID : C10CFIIP.G68 Equilibrium Pore Water Pressure : 0.063 MPa U50 : 0.192 MPa
Max
Min
T50 = 1.82 Min
Interval
100 0.321
80 0.270
Normalized Excess Pore Water Pressure, U (%)
70
60 0.218
50 0.192 MPa
40 0.166
30
20 0.115
10
0 0.063
0.01 0.10 1.00 10.00 100.00 1000.00 10000.00
Time, t (min)
Project : ADDITIONAL SOIL INVESTIGATION FACTUAL REPORT FOR RAPID PROJECT - REFINERY PROCESS AREA
Owner : MESSRS PETROLIAM NASIONAL BERHAD (PETRONAS) Job No. : GLSB/CPT/17-134/13 (02)
Client : MESSRS TECHNIP GEOPRODUCTION (M) SDN BHD W.O No. : Duration : 30.00 min
CPT No. : PCPT 60-1 Test Date : 26-8-2013 Water Depth at Start Time : 1.300 m(B.G.L) T50 : 1.625 min
Test Depth : 5.50 m (B.G.L) Cone ID : C10CFIIP.G68 Equilibrium Pore Water Pressure : 0.042 MPa U50 : 0.239 MPa
Max
Min
T50 = 1.63 Min
Interval
100 0.437
80 0.358
Normalized Excess Pore Water Pressure, U (%)
70
60 0.279
50 0.239 MPa
40 0.200
30
20 0.121
10
0 0.042
0.01 0.10 1.00 10.00 100.00 1000.00 10000.00
Time, t (min)
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX G
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
1000
m)
Aparwnt Resistivity (
100
10
0
0 1 "
" Spacing (m) 10 100
Project: PETRONAS RAPID PROJECT, FEED PHASE
Geolab
Point: ERT-9 Method: Wenner Date : 07-10-13
Electrod Modified Measured Modified Measured Modeled Layer Soil Model Depth
Layer
Spacing (m) Resistance (
) Resistivity (
m) Resistivity (
m) Thickness (m) (m)
0.001 872.67 0.100000001
1 144.600 908.55 1 872.67 0.77 0.77
2 76.900 966.35 2 944.75 0.75 1.52
3 54.140 1020.51 3 1224.05 1.53 3.05
4 39.140 983.70 4 992.64 2.89 5.94
5 31.060 975.78 5 556.06 6.27 12.21
7 21.640 951.78 6 1093.93 17.79 30.00
9 15.730 889.51
12 11.030 831.64
15 8.897 838.52
20 6.679 839.31
25 5.550 871.79
30 4.854 914.96
1000
100
0 1 10 100
"
" Spacing (m)
Project PETRONAS RAPID PROJECT, FEED PHASE
100
m)
Aparwnt Resistivity (
10
0
0 1 "
" Spacing (m) 10 100
Project: PETRONAS RAPID PROJECT, FEED PHASE
Geolab
Point: ERT-17 Method: Wenner Date : 30-09-13
Electrod Modified Measured Modified Measured Modeled Layer Soil Model Depth
Layer
Spacing (m) Resistance (
) Resistivity (
m) Resistivity (
m) Thickness (m) (m)
0.001 354.28 0.100000001
1 55.970 351.67 1 354.28 0.64 0.64
2 28.352 356.29 2 349.60 0.65 1.29
3 20.017 377.31 3 299.68 1.26 2.55
4 15.652 393.38 4 676.93 2.91 5.45
5 13.192 414.43 5 271.88 6.85 12.31
7 9.722 427.60 6 789.00 17.69 30.00
9 7.616 430.67
12 5.761 434.34
15 4.687 441.74
20 3.797 477.15
25 3.267 513.19
30 2.815 530.61
100
0 1 10 100
"
" Spacing (m)
Project PETRONAS RAPID PROJECT, FEED PHASE
100
m)
Aparwnt Resistivity (
10
0
0 1 "
" Spacing (m) 10 100
Project: PETRONAS RAPID PROJECT, FEED PHASE
Geolab
Point: ERT-18 Method: Wenner Date : 30-09-13
Electrod Modified Measured Modified Measured Modeled Layer Soil Model Depth
Layer
Spacing (m) Resistance (
) Resistivity (
m) Resistivity (
m) Thickness (m) (m)
0.001 363.99 0.100000001
1 52.150 327.67 1 363.99 0.70 0.70
2 23.871 299.98 2 267.85 0.69 1.39
3 15.749 296.87 3 260.21 1.35 2.74
4 12.240 307.62 4 341.30 2.74 5.47
5 10.379 326.07 5 440.24 5.49 10.96
7 8.114 356.87 6 907.55 19.04 30.00
9 6.759 382.21
12 5.701 429.84
15 5.115 482.07
20 4.325 543.48
25 3.761 590.75
30 3.341 629.76
100
0 1 10 100
"
" Spacing (m)
Project PETRONAS RAPID PROJECT, FEED PHASE
100
m)
Aparwnt Resistivity (
10
0
0 1 "
" Spacing (m) 10 100
Project: PETRONAS RAPID PROJECT, FEED PHASE
Geolab
Point: ERT-19 Method: Wenner Date : 30-09-13
Electrod Modified Measured Modified Measured Modeled Layer Soil Model Depth
Layer
Spacing (m) Resistance (
) Resistivity (
m) Resistivity (
m) Thickness (m) (m)
0.001 328.44 0.100000001
1 50.150 315.10 1 328.44 0.70 0.70
2 24.122 303.12 2 290.58 0.70 1.40
3 16.130 304.04 3 285.14 1.39 2.78
4 12.444 312.75 4 302.25 2.72 5.50
5 10.373 325.88 5 464.97 5.09 10.59
7 8.122 357.22 6 927.69 19.41 30.00
9 6.759 382.21
12 5.726 431.73
15 5.169 487.12
20 4.393 552.04
25 3.880 609.52
30 3.390 639.00
100
0 1 10 100
"
" Spacing (m)
Project PETRONAS RAPID PROJECT, FEED PHASE
1000
m)
Aparwnt Resistivity (
100
10
0
0 1 "
" Spacing (m) 10 100
Project: PETRONAS RAPID PROJECT, FEED PHASE
Geolab
Point: ERT-20 Method: Wenner Date : 07-10-13
Electrod Modified Measured Modified Measured Modeled Layer Soil Model Depth
Layer
Spacing (m) Resistance (
) Resistivity (
m) Resistivity (
m) Thickness (m) (m)
0.001 874.64 0.100000001
1 144.600 908.55 1 874.64 0.78 0.78
2 76.900 966.35 2 930.53 0.75 1.52
3 54.140 1020.51 3 1267.10 1.53 3.05
4 39.770 999.53 4 982.71 2.84 5.89
5 31.060 975.78 5 553.25 6.24 12.12
7 21.640 951.78 6 1094.65 17.88 30.00
9 15.730 889.51
12 11.030 831.64
15 8.897 838.52
20 6.679 839.31
25 5.550 871.79
30 4.854 914.96
1000
100
0 1 10 100
"
" Spacing (m)
Project PETRONAS RAPID PROJECT, FEED PHASE
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX H
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Coordinate :
Elevation :
Soil Type :
Weather :
K (Thermal R (Thermal
Soil Type / Depth Conductivity) Resistivity) Temp.
Test Number Date / Time
Weather (m) -1 -1 -1 (Deg C)
(Wm C ) (mCW )
Slightly Sandy a) Surface 0.76 1.31 30.7
16-09-13
SILT b) Surface 1.25 0.80 30.4
TCT-14
c) Surface 0.63 1.59 31.2
14:30 Sunny
Average 0.88 1.23 30.8
a) Surface 0.53 1.69 31.9
19-09-13 Dry Soil
b) Surface 0.17 5.95 31.6
TCT-15
c) Surface 1.12 0.90 31.6
17:00 Sunny
Average 0.61 2.85 31.7
Slightly Sandy a) Surface 1.05 0.95 30.8
16-09-13
SILT b) Surface 1.14 0.88 30.2
TCT-16
c) Surface 1.02 0.98 31.2
14:20 Sunny
Average 1.07 0.94 30.7
a) Surface 1.36 0.74 34.5
20-09-13 Dry, SILT
b) Surface 1.15 0.87 35.8
TCT-17
c) Surface 0.68 0.02 35.1
11:30 Sunny
Average 1.06 0.54 35.1
a) Surface 2.07 0.48 32.2
22-09-13 Dry, SILT
b) Surface 1.48 0.67 31.0
TCT-18
c) Surface 1.53 0.65 30.9
16:20 Sunny
Average 1.69 0.60 31.4
Slightly Sandy a) Surface 1.07 0.95 30.3
16-09-13
SILT b) Surface 1.14 0.88 32.3
TCT-19
c) Surface 1.02 0.98 30.5
14:10 Sunny
Average 1.08 0.94 31.0
Slightly Sandy a) Surface 1.41 0.71 33.6
16-09-13
SILT b) Surface 1.62 0.62 33.2
TCT-20
c) Surface 0.98 1.02 35.1
14:00 Sunny
Average 1.34 0.78 34.0
OWNER REFERENCE
Project Package Originator Discipline Doc. Type Unit n Serial n
SUB12-
RAPID FE1 CVS ERP 0001 0002
GLB
CONTRACTOR REFERENCE Rev. Page
PETRONAS RAPID PROJECT Project Unit n Doc. Type Doc. Code Sequent. n
FEED PHASE B 29 / 30
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX I
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
3. RESULTS OF INVESTIGATION
3.1 Results of Downhole PS Logging 6
LIST OF FIGURES
LIST OF TABLES
APPENDIX
1.1 Introduction
The purpose of this geophysical investigation is to obtain the geophysical properties of the
soil at sites. Geophysical tests were performed to obtain the P-wave and S-wave velocities of
the soil strata. These results provide the designer with the information pertinent to the seismic
wave velocities of the materials. This data may be used as input into static/dynamic analysis,
as means for computing Shear modulus, Youngs modulus and Poissons Ratio.
1
2. SCOPE OF WORK FOR DOWNHOLE PS LOGGING
Generally, the source is a sledgehammer which is struck vertically onto a steel plate on the
ground placed near to the borehole (ie, Compressional or P wave source) or, alternatively,
horizontally by striking the both ends of the wooden block (ie, shear or S wave source). The
wooden block is firmly sitting on the ground. The source is struck for P wave transmission as
well as for S wave transmission, and travel time from the moment of source initiation until
reception at the geophone is recorded. The geophone is next moved to a new depth and the
process is repeated.
For Downhole PS-Logging test, the wave propagates downward. Hence P-wave is monitored
by the vertical sensors while S-wave is generated through hitting the two ends of the wooden
block. This causes two waves of which one is the reverse of the other. Interval velocity
(instantaneous velocity over an interval) is determined by comparing successive readings.
This procedure is repeated at a specified depth interval from the bottom of the hole to the top.
2
2.2 Seismograph Equipment
The system used for this project was a 24-Channel seismograph manufactured by Oyo
Corporation, Japan, Model McSeis SX-XP. The particulars of this instrument are listed in
Table 2.
3
Table 2 Specification of McSeis - SX XP
McSeis - SX XP
Data Acquisition
Number of Channels 1,3,6,12 or 24 + 1 AUX
Input Impedance Differential 20 k/0.05 F
Gain 24, 36, 48, 60 dB
Frequency Band 2 - 4600 Hz
A/D Resolution 24 bits
Setting feasible to 33.3, 50, 100, 200, 500, 1000, 2000sec
Sample rate
Setting feasible to 1024, 2048, 4096, 8192, 16384 words
Pre-Trigger 0 (OFF), 128 (ON)
Data Length 0, 128 samples
Trigger Level 100-1000 mV (100mV step), Setting to OFF feasible
System
CPU ULV Intel Celeron Processor 400MHz
Display 640 x 480 dots 10.4 inch LCD VGA
Hard Disk 80GB
Memory 256MB
OS Windows XP SP2 Professional
LCD 1024 x 768 dots 10.4-inch Color
Display
Size XGA : TFT
USB (for external printer, memory, mouse, other USB drive)
Interface
External keyboard I/F (for device maintenance)
Dc 12V (10.5 ~ 14.0V)
Operating Power Supply
2.5 A (standby), 3.0 A (acquisition)
Dimensions 330 (W) x 280 (D) x 220 (H) mm
Weight 8kg
4
2.3 Borehole Pick 3315 for PS-Logging
The Model BHP-3315 Borehole Pick is what we call the Borehole Geophone used for PS
logging to measure P-Wave and S-Wave velocities of the ground. This instrument is
constituted by the 3-component geophone, the unit to affect the pressurized contact of the
system to the borehole wall, and the cable with additional installation of the water supply
tube. In the geophone unit, the geophone of moving coil type is being built, constituted by
one component vertical and two components horizontal. The effective unit to the pressurized
contact of the system to the borehole wall is adapting the method of pressurizing, inflating,
and expanding the external rubber tube in the geophone for its pressurized contact to the
borehole wall. Furthermore, the cable with additional installation of the water supply tube is
used for transferring the signal from the geophone, and for supplying the water that serves to
give pressure to and inflate the rubber tube. Having the features effective for PS logging,
being handy dimensionally, and easily accessible to its operation.
Being designed small in size and light in weight, the Instruments can applied for the
borehole of comparatively small diameter (56mm)
Adopting the unit to affect the pressurized contact of the system to the borehole wall
by the rubber tube, the instrument can be fixed at the optional depth in the borehole.
Being unitized with the cable, the water supply tube for inflating the rubber tube
eliminates the complexity with jobs in the site, and enables inserting into the
borehole, and drawing out from it this Instrument.
With the depth scale marked on it, the cable offers easy access to verify the measuring
depth.
5
3. RESULTS OF INVESTIGATION
3.1 Results of Downhole PS Logging
a) P-Wave
In case of down-hole method, wave propagates downward. Therefore, P-Wave is monitored
by the vertical sensor. The distance between wave sources and sensor is calculated based on
horizontal distance of wave sources from the mouth of the borehole and depth of sensor is
calculated by the following formula:
l= X 2 + d2
Here, X is the distance from the source to the mouth of the borehole, d is the depth of the
sensor.
Time-Distance curve is plotted which shows the relationship between t and d. This curve is
divided into several appropriate regions of straight lines. P-Wave velocity was obtained from
l
these lines as
t
b) S-Wave
S-Wave is created through hitting the two ends of the timber. This causes two waves of
which one is the reverse of the other. The two waves are detected and monitored from the
horizontal sensor of the borehole pick. The waveforms are superimposed with each other and
the more obvious reversed waveform, from any of the two horizontal sensors, is used for
analysis for each depth. And processing all the superimposed waveforms with depth, it can be
observed that the occurrence of these waves is delayed with increasing depth. The time
difference between the peak with the highest magnitude and the first break time is monitored
at the shallowest depth. Hence, this lapse in time is taken as constant for all depth. Thus, a
Time-Distance curve is plotted and the velocity of S-Wave is obtained in the same manner as
P-Wave.
6
c) Analysis Result of PS-Logging
The records obtained at each depth are traced up in order of depth. Results are further used
for analysis of soil geological and physical properties.
Elastic coefficient of the soil/rock can be calculated from compression and shear wave
velocities by using the following equations:
Vs 2
Rigidity factor G=
g
Youngs Modulus E = 2 (1 + ) G
V
[( P )2 2]
VS
Poissons Ratio =
V
2 [( P )2 1]
VS
Where
Vp : Compression wave velocity, m/sec
Vs : Shear wave velocity, m/sec
: Density, g/cm3
g : Acceleration due to gravity, 9.8m/s2
7
APPENDIX A
Time (msec)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
P Wave
Velocity
15
16 S Wave
Velocity
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1.0 906.92 292.78 9.81 1.8 - - - - - 8 Firm Stiff Medium Brown With Light Grey and
1.5 906.92 292.78 9.81 1.8 1572.85 0.154 0.442 4,535.55 0.445 Light Black Sandy SILT
2.0 920.78 294.63 9.81 1.8 1592.81 0.156 0.443 4,596.75 0.451
2.5 920.78 294.63 9.81 1.8 1592.81 0.16 0.443 4,596.75 0.451 10 Stiff Medium Grey with pale Brown sandy
3.0 1181.88 290.02 9.81 1.8 1,543.33 0.151 0.468 4,531.11 0.444 12 SILT
3.5 1181.88 290.02 9.81 1.8 1,543.33 0.151 0.468 4,531.11 0.444
4.0 965.66 255.95 9.81 1.8 1,201.99 0.118 0.462 3,515.14 0.345
4.5 965.66 255.95 9.81 1.8 1,201.99 0.118 0.462 3,515.14 0.345 27 Very Stiff Medium Orange with medium grey
5.0 1395.95 306.52 9.81 1.8 1,723.90 0.169 0.475 5,084.36 0.499 Sandy SILT
5.5 1395.95 306.52 9.81 1.8 1,723.90 0.169 0.475 5,084.36 0.499
6.0 1327.08 300.28 9.81 1.8 1,654.45 0.162 0.473 4,874.07 0.478 20
Very Stiff Medium Orange with Light grey and
6.5 1327.08 300.28 9.81 1.8 1,654.45 0.162 0.473 4,874.07 0.478
Light Purple sandy
7.0 1391.44 313.96 9.81 1.8 1,808.66 0.177 0.473 5,328.96 0.523
7.5 1391.44 313.96 9.81 1.8 1,808.66 0.177 0.473 5,328.96 0.523 22
8.0 1313.83 307.52 9.81 1.8 1,735.21 0.170 0.471 5,105.04 0.501 Very Stiff medium purple with light grey sandy
8.5 1313.83 307.52 9.81 1.8 1,735.21 0.170 0.471 5,105.04 0.501
9.0 984.64 234.87 9.81 1.8 1,012.20 0.099 0.470 2,975.53 0.292 14
Stiff Medium Orange with Medium Brown
9.5 984.64 234.87 9.81 1.8 1,012.20 0.099 0.470 2,975.53 0.292 sandy SILT
10.0 997.23 225.34 9.81 1.8 931.72 0.091 0.473 2,745.02 0.269
10.5 997.23 225.34 9.81 1.8 931.72 0.091 0.473 2,745.02 0.269 15
11.0 1867.21 449.46 9.81 1.8 3706.69 0.364 0.469 10,892.09 1.068
11.5 1867.21 449.46 9.81 1.8 3706.69 0.364 0.469 10,892.09 1.068
12.0 1730.90 396.85 9.81 1.8 2889.76 0.28 0.472 8,508.95 0.834 32
Hard Medium Purple with Light Grey Sandy
12.5 1730.90 396.85 9.81 1.8 2,889.76 0.283 0.472 8,508.95 0.834 SILT
13.0 1809.33 400.03 9.81 1.8 2,936.25 0.288 0.474 8,657.84 0.849
13.5 1809.33 400.03 9.81 1.8 2,936.25 0.288 0.474 8,657.84 0.849 27 Very Stiff medium purple with light grey sandy
14.0 1865.74 410.05 9.81 1.8 3,085.08 0.303 0.475 9,098.67 0.892 SILT
14.5 1865.74 410.05 9.81 1.8 3,085.08 0.303 0.475 9,098.67 0.892
15.0 1835.97 448.32 9.81 1.8 3,687.86 0.362 0.468 10,829.75 1.062 29
15.5 1835.97 448.32 9.81 1.8 3,687.86 0.362 0.468 10,829.75 1.062 Very Stiff medium purple with light Yellow
16.0 1874.98 474.52 9.81 2.0 4,590.56 0.450 0.466 13,457.54 1.320 sandy SILT
16.5 1874.98 474.52 9.81 2.0 4,590.56 0.450 0.466 13,457.54 1.320 50
Hard Medium Purple with Light Grey and Fale
17.0 1807.50 497.13 9.81 2.0 5,038.58 0.494 0.459 14,703.40 1.442 Yellow Sandy SILT
17.5 1807.50 497.13 9.81 2.0 5,038.58 0.494 0.459 14,703.40 1.442
18.0 1973.79 471.53 9.81 2.0 4,532.86 0.445 0.470 13,324.23 1.307 50
18.5 1973.79 471.53 9.81 2.0 4,532.86 0.445 0.470 13,324.23 1.307
19.0 1978.73 495.84 9.81 2.0 5,012.34 0.492 0.467 14,701.19 1.442
19.5 1978.73 495.84 9.81 2.0 5,012.34 0.492 0.467 14,701.19 1.442 50
20.0 1989.35 522.45 9.81 2.0 5,564.78 0.546 0.463 16,282.09 1.597
Hard medium purple with pale grey, yellow and
20.5 1989.35 522.45 9.81 2.0 5564.78 0.546 0.463 16,282.09 1.597 dark orange mottled sandy SILT
21.0 1978.05 501.65 9.81 2.0 5130.57 0.503 0.466 15,039.06 1.475 50
21.5 1978.05 501.65 9.81 2.0 5130.57 0.50 0.466 15,039.06 1.475
22.0 2109.71 624.29 9.81 2.0 7,945.82 0.779 0.452 23,074.91 2.263
22.5 2109.71 624.29 9.81 2.0 7,945.82 0.779 0.452 23,074.91 2.263 50
23.0 2141.55 614.75 9.81 2.0 7,704.80 0.756 0.455 22,422.48 2.199
23.5 2141.55 614.75 9.81 2.0 7,704.80 0.756 0.455 22,422.48 2.199
24.0 2131.38 644.55 9.81 2.0 8469.92 0.831 0.450 24,557.18 2.408 50
24.5 2131.38 644.55 9.81 2.0 8469.92 0.831 0.450 24,557.18 2.408
25.0 2175.03 634.37 9.81 2.0 8204.35 0.80 0.454 23,850.25 2.339
25.5 2175.03 634.37 9.81 2.0 8,204.35 0.805 0.454 23,850.25 2.339 50
Hard medium purple with pale grey dark yellow
26.0 2186.34 605.71 9.81 2.0 7,479.83 0.734 0.458 21,817.67 2.140 an dark orange mottled sandy SILT
26.5 2186.34 605.71 9.81 2.0 7,479.83 0.734 0.458 21,817.67 2.140
27.0 2112.20 638.15 9.81 2.0 8,302.46 0.814 0.450 24,073.39 2.361
27.5 2112.20 638.15 9.81 2.0 8302.46 0.814 0.450 24,073.39 2.361
28.0 2142.23 629.45 9.81 2.0 8077.62 0.792 0.453 23,469.58 2.302 50
Analysis Result of Downhole PS-Logging
Project Name: Downhole PS Logging Survey at Pengerang Johor BH No.: PBH 10-10
Page 1 of 2
Soil Column
Depth (m) Symbol ( : G.L) N-Value Poisson's Ratio G (Gpa) E (Gpa)
Top Soil 0 20 40 60 80 100 0.4 0.42 0.44 0.46 0.48 0.5 0 0.2 0.4 0.6 0.8 1 1.2 0 0.5 1 1.5 2 2.5 3
__ 0 0 0
0 0
_
_
_
_
__ 1 x x x
Firm Stiff Medium Brown With 1 1 1 1
_ x x
_ x x x Light Grey and Light Black
_ x x Sandy SILT
_ x x x
__ 2 x x 2 2 2 2
_ x x x
_ x x
_ x x x
_ x x
Stiff Medium Grey with pale
__ 3 x x x Brown sandy SILT 3 3 3 3
_ x x x
_ x x -Ditto-
_
_
__ 4 4 4 4 4
_ No Recovery
_
_ x x x
_ x x
__ 5 x x x 5 5 5 5
_ x x Very Stiff Medium Orange with
_ x x x
medium grey Sandy SILT
_ x x
_ x x x
__ 6 x x 6 6 6 6
_
_ Very Stiff Medium Orange with
_ Light grey and Light Purple
_
__ 7 sandy 7 7 7
7
_
_
_
_ Very Stiff medium purple with
__ 8 light grey sandy 8 8 8 8
_
_
_
_
__ 9 9 9 9 9
_ x x x
_ x x Stiff Medium Orange with
_ x x x
Medium Brown sandy SILT
_ x x
__ 10 x x x 10 10 10 10
_ x x
_ x x x
_ x x
_ x x x
__ 11 x x 11 11 11 11
_ x x x
_ x x -Ditto-
_ x x x
_ x x
__ 12 x x x 12 12 12 12
_ x x
_ x x x
_ x x
Hard Medium Purple with Light
_ x x x Grey Sandy SILT
__ 13 x x 13 13 13 13
_ x x x
_ x x
_ x x
_ x x x
__ 14 x x 14 14 14 14
_ x x x Very Stiff medium purple with
_ x x
light grey sandy SILT
_ x x x
_ x x
__ 15 x x x 15 15 15 15
_ x x
_ x x x
_ x x Very Stiff medium purple with
_ x x x
light Yellow sandy SILT
__ 16 x x 16 16 16 16
_ x x x
_ x x
_ x x x
_ x x Hard Medium Purple with Light
__ 17 x x x 17 17 17 17
_ x x Grey and Fale Yellow Sandy
_ x x x SILT
_ x x
_ x x x
__ 18 x x 18 18 18 18
_ x x x
_ x x
_ x x x
_ x x Hard, -Ditto-
__ 19 x x x 19 19 19 19
_ x x
_ x x x
_ x x
_ x x x
__ 20 x x Hard, -Ditto- 20 20 20 20
Analysis Result of Downhole PS-Logging
Project Name: Downhole PS Logging Survey at Pengerang Johor BH No.: PBH 10-10
Page 2 of 2
Soil Column
Depth (m) Symbol ( : G.L) N-Value Poisson's Ratio G (Gpa) E (Gpa)
x x x
0 20 40 60 80 100 0.4 0.42 0.44 0.46 0.48 0.5
0 0.2 0.4 0.6 0.8 1 1.2 1.4
__20 x x 0 1 2 3 4
20 20 20 20
_ x x x
_ x x Hard medium purple with pale
_ x x x grey, yellow and dark orange
_ x x
mottled sandy SILT
__ 21 x x x 21 21 21 21
_ x x
_ x x x
_ x x
_ x x x
__ 22 x x 22 22 22 22
_ x x x
_ x x
_ x x x
_ x x -Ditto-
__23 x x x 23 23 23 23
_ x x
_ x x x
_ x x
_ x x x
__24 x x 24 24 24 24
_ x x x Hard medium purple with pale
_ x x grey dark yellow an dark orange
_ x x x
_ x x
mottled sandy SILT
__ 25 x x x 25 25 25 25
_ x x x
_ x x
_ x x x
_ x x
__ 26 x x x 26 26 26 26
_ x x
_ x x x
_ x x
_ x x x
__ 27 x x 27 27 27 27
_ x x x
_ x x
_ x x x
_
__28 28 28 28 28
_
_
_
_
__ 29 29 29 29 29
_
_
_
_
__ 30 30 30 30 30
_
_
_
_
__ 31 31 31 31 31
_
_
_
_
__ 32 32 32 32 32
_
_
_
_
__ 33 33 33 33 33
_
_
_
_
__ 34 34 34 34 34
_
_
_
_
__ 35 35 35 35 35
_
_
_
_
__ 36 36 36 36 36
_
_
_
_
__ 37 37 37 37 37
_
_
_
_
__ 38 38 38 38 38
_
_
_
_
__ 39 39 39 39 39
_
_
_
_
__ 40 40 40 40 40
APPENDIX B
Site Photographs
Project : AdditionalSoilInvestigationFactualReportForRapidProject
RefineryProcessArea
Customer : Messrs.TechnipGeoproduction(M)SdnBhd
Photo1 : DownholePSLoggingLocationatPBH1010
OWNER REFERENCE
Project Package Originator Discipline Doc. Type Unit n Serial n
SUB12-
RAPID FE1 CVS ERP 0001 0002
GLB
CONTRACTOR REFERENCE Rev. Page
PETRONAS RAPID PROJECT Project Unit n Doc. Type Doc. Code Sequent. n
FEED PHASE B 2 / 30
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.
CONFIDENTIAL Not to disclose without authorization
OWNER REFERENCE
Project Package Originator Discipline Doc. Type Unit n Serial n
SUB12-
RAPID FE1 CVS ERP 0001 0002
GLB
CONTRACTOR REFERENCE Rev. Page
PETRONAS RAPID PROJECT Project Unit n Doc. Type Doc. Code Sequent. n
FEED PHASE B 30 / 30
Factual Report Additional Soil Investigation Works for RAPID Project Refinery Process Area
APPENDIX J
Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the
copyright owner.
Compression Test
Bulk Unit Weight
Modulus Young's
Moisture Content
Chloride Content
Chloride Content
Sulphate Content
Sulphate Content
Particle Size Distribution Atterberg Limit 1-D Consolidation Test
Organic Content
Linear Shinkage
Specific Gravity
Poisson Ratio's
Test
Uniaxial
Borehole No.
Plastic Index
Liquid Limit
Plastic Limit
Void Pre-con. Comp.
Sample No.
IS
UU CU
pH
Depth
Gravel
Ratio Pressure Index
Sand
Clay
Silt
C f Cu f e Pc Cc
metre % kg/mm3 Mg/m3 % % % % % % % % kN/m2 deg. kN/m2 deg. kN/m2 MPa MPa GPa % % g/l mg/l %
NOTE; NP : NON-PLASTIC NES : NOT ENOUGH SAMPLE NA : NOT APPLICABLE * TESTING IN PROGRESS
Compression Test
Bulk Unit Weight
Modulus Young's
Moisture Content
Chloride Content
Chloride Content
Sulphate Content
Sulphate Content
Particle Size Distribution Atterberg Limit 1-D Consolidation Test
Organic Content
Linear Shinkage
Specific Gravity
Poisson Ratio's
Test
Uniaxial
Borehole No.
Plastic Index
Liquid Limit
Plastic Limit
Void Pre-con. Comp.
Sample No.
IS
UU CU
pH
Depth
Gravel
Ratio Pressure Index
Sand
Clay
Silt
C f Cu f e Pc Cc
metre % kg/mm3 Mg/m3 % % % % % % % % kN/m2 deg. kN/m2 deg. kN/m2 MPa MPa GPa % % g/l mg/l %
NOTE; NP : NON-PLASTIC NES : NOT ENOUGH SAMPLE NA : NOT APPLICABLE * TESTING IN PROGRESS
Authorized Signatories:
Date tested
28-Aug-13
P7/D7 9.00 33
2 95.04 135.92 125.76 10.16 30.72 33.07
1 95.56 145.56 133.28 12.28 37.72 32.56
P10/D10 13.50 32
2 95.56 145.86 133.78 12.08 38.22 31.61
1 95.42 123.98 117.58 6.40 22.16 28.88
PBH 10-2 P13/D13 18.00 29
2 95.70 117.52 112.62 4.90 16.92 28.96
1 95.44 139.84 130.40 9.44 34.96 27.00
P16/D16 22.50 27
2 95.32 137.12 128.16 8.96 32.84 27.28
1 95.58 133.40 126.88 6.52 31.30 20.83
P18/D18 25.50 21
2 95.36 135.06 128.16 6.90 32.80 21.04
1 95.62 127.44 121.66 5.78 26.04 22.20
P20/D20 28.50 23
2 95.12 134.86 127.30 7.56 32.18 23.49
1 95.22 121.26 114.58 6.68 19.36 34.50
P1/D2 1.00 34
2 95.58 119.68 113.60 6.08 18.02 33.74
1 95.60 133.14 129.20 3.94 33.60 11.73
PBH 10-3 P3/D4 3.00 12
2 95.42 131.48 127.48 4.00 32.06 12.48
1 95.42 141.16 133.22 7.94 37.80 21.01
P6/D7 7.50 22
2 95.74 124.88 119.60 5.28 23.86 22.13
GLSB/SI/ 2566-122(Refinery Process) /2013 2nd September 2013
3 of 297
Date tested
28-Aug-13
Date tested
28-Aug-13
24-Aug-13
28-Aug-13
24-Aug-13
** Base on Table 1 : Factors For One-Point Cone Penetrometer Liquid Limit Test; BS 1377 : Part 2 : 1990 : 4.4
GLSB/SI/ 2566-122(Refinery Process) /2013 2nd September 2013
20 of 297
** Base on Table 1 : Factors For One-Point Cone Penetrometer Liquid Limit Test; BS 1377 : Part 2 : 1990 : 4.4
GLSB/SI/ 2566-122(Refinery Process) /2013 2nd September 2013
21 of 297
** Base on Table 1 : Factors For One-Point Cone Penetrometer Liquid Limit Test; BS 1377 : Part 2 : 1990 : 4.4
GLSB/SI/ 2566-122(Refinery Process) /2013 2nd September 2013
22 of 297
** Base on Table 1 : Factors For One-Point Cone Penetrometer Liquid Limit Test; BS 1377 : Part 2 : 1990 : 4.4
GLSB/SI/ 2266-122(Refinery Process) /2013 2nd September 2013
76 of 297
Linear Shrinkage
Initial Length Oven Dried LD
Depth Mould
Borehole No. Sample No. LO Length LD 100 x 1-
Code LO
100
90
80
70
Percentage Passing,%
60
50
40
30
20
10
0
0.001 0.01 0.1 1 10 100
Grain diameter,mm
100
90
80
70
Percentage Passing,%
60
50
40
30
20
10
0
0.001 0.01 0.1 1 10 100
Grain diameter,mm
0.002 0.006 0.02 0.063 0.2 0.6 2.0 20.0 60.0
FINE MEDIUM COARSE FINE MEDIUM COARSE FINE MEDIUM COARSE
CLAY
SILT SAND GRAVEL COBBLE
5% 9% 86 % 0%
UNCONSOLIDATED UNDRAINED
TRIAXIAL COMPRESSION TEST
(UU TEST)
120
100
80
60
40
20
0
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280
NORMAL STRESS, kN/m2
UU TRIAXIAL COMPRESSION TEST
SOILPRO TECHNICAL SERVICES SDN BHD
Project: PETRONAS RAPID PROJECT Sample No. : PBH10-01/UD1
Location: REFINERY PROCESS AREA Depth, m : 3.50
Ring Factor : 0.00133 kN/div
Client: Geolab (M) Sdn Bhd Tested by : Nor
Lab.Ref : L130366 Date : 02.09.2013
140
120
Sample Size
100 Dia.: 50.0 mm
Length : 100.0 mm
80 Area : 1963.5 mm
60
40
20
0
0 2 4 6 8 10 12 14 16 18 20 22
Strain, %
CHECKED BY:
UU TRIAXIAL COMPRESSION TEST
SOILPRO TECHNICAL SERVICES SDN BHD
140
120
100
80
60
40
20
0
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340
NORMAL STRESS, kN/m2
UU TRIAXIAL COMPRESSION TEST
SOILPRO TECHNICAL SERVICES SDN BHD
Project: PETRONAS RAPID PROJECT Sample No. : PBH10-02/UD1
Location: REFINERY PROCESS AREA Depth, m : 5.00
Ring Factor : 0.00133 kN/div
Client: Geolab (M) Sdn Bhd Tested by : Nor
Lab.Ref : L130366 Date : 02.09.20013
140
120
Sample Size
100 Dia.: 50.0 mm
Length : 100.0 mm
80 Area : 1963.5 mm
60
40
20
0
0 2 4 6 8 10 12 14 16 18 20 22
Strain, %
CHECKED BY:
CONSOLIDATED UNDRAINED
TRIAXIAL COMPRESSION TEST
(CU TEST)
Customer : M/S Technip Geoproduction (M) Sdn. Bhd. Date Tested : 3-Sep-13
Consultant : - Job No. : GLSB/SI/2566-122/2013
Borehole No.
Sample No.
Width, W Diameter, D
Test Type
Load
Depth De2 De Is F Is(50) UCS
P
W1 W2 W D1 D2 D
PBH C1 18.30 i 113.0 99.0 106.0 45.0 41.0 43.0 15.87 5803.4 76.2 2.73 1.21 3.31 69.41
10-14
C2 19.80 i 138.0 115.0 126.5 33.0 29.2 31.1 3.92 5009.1 70.8 0.78 1.17 0.91 19.20
C3 21.30 i 69.2 68.5 68.9 51.5 51.5 51.5 4.78 4514.6 67.2 1.06 1.14 1.21 25.38
PBH C1 17.30 i 104.0 104.0 104.0 52.0 52.0 52.0 4.12 6885.7 83.0 0.60 1.26 0.75 15.78
10-26
C2 18.80 i 125.1 125.3 125.2 52.0 52.0 52.0 8.37 8289.3 91.0 1.01 1.31 1.32 27.76
PBH C1 28.00 i 61.8 61.8 61.8 40.2 37.2 38.7 1.08 3045.2 55.2 0.35 1.05 0.37 7.79
17-1
PBH C2 24.30 i 83.0 77.0 80.0 33.5 33.8 33.7 5.35 3427.6 58.5 1.56 1.07 1.67 35.16
17-2
C3 25.80 i 90.0 89.9 90.0 35.0 33.8 34.4 4.89 3939.8 62.8 1.24 1.11 1.37 28.87
Note :
d = diametral; a = axial; b = block; i = irregular lump test; = perpendicular; // = parallel to planes of weakness
Customer : M/S Technip Geoproduction (M) Sdn. Bhd. Date Tested : 3-Sep-13
Consultant : - Job No. : GLSB/SI/2566-122/2013
Borehole No.
Sample No.
Width, W Diameter, D
Test Type
Load
Depth De2 De Is F Is(50) UCS
P
W1 W2 W D1 D2 D
PBH C1 23.00 i 164.0 164.2 164.1 65.0 41.8 53.4 23.20 11157.3 105.6 2.08 1.40 2.91 61.14
17-3
C2 24.50 i 120.1 120.3 120.2 44.3 42.2 43.3 7.41 6619.1 81.4 1.12 1.24 1.39 29.25
C3 26.00 i 104.0 104.0 104.0 52.0 52.0 52.0 15.29 6885.7 83.0 2.22 1.26 2.79 58.57
PBH C1 25.60 i 68.0 64.0 66.0 45.0 45.0 45.0 2.82 3781.5 61.5 0.75 1.10 0.82 17.18
17-4
C3 28.60 i 103.0 99.0 101.0 52.0 52.0 52.0 2.17 6687.1 81.8 0.32 1.25 0.41 8.51
C4 30.10 i 70.0 70.0 70.0 52.0 52.0 52.0 3.88 4634.6 68.1 0.84 1.15 0.96 20.18
Note :
d = diametral; a = axial; b = block; i = irregular lump test; = perpendicular; // = parallel to planes of weakness
Client : M/S PETRONAS & M/S TECHNIP GEOPRODUCTION (M) SDN BHD
Job No. : Tested Date : 29-09-13
100.00
Stress (kN/mm2)
80.00
y = 277088x
60.00
40.00
y = -44537x
20.00
0.00
-0.002500 -0.002000 -0.001500 -0.001000 -0.000500 0.000000 0.000500 0.001000 0.001500
Strain (mm/mm)
100
96.33 MPa
Stress (N/mm2)
80
60
40
20
0
0 50 100 150 200 250 300 350
Time (sec)
PBH10-6_C1_17m.xls Page 1 - 1
DETERMINATION OF YOUNG'S MODULUS, POISSON RATIO AND
UNCONFINED COMPRESSIVE STRENGTH ON ROCK
Client : M/S PETRONAS & M/S TECHNIP GEOPRODUCTION (M) SDN BHD
Job No. : Tested Date : 29-09-13
140.00
120.00
Stress (kN/mm2)
100.00
80.00
y = 319468x
60.00
40.00
y = -71745x
20.00
0.00
-0.002000 -0.001500 -0.001000 -0.000500 0.000000 0.000500 0.001000 0.001500
Strain (mm/mm)
140
100
80
60
40
20
0
0 50 100 150 200 250 300 350
Time (sec)
PBH10-6_C2_18.5m.xls Page 1 - 1
DETERMINATION OF YOUNG'S MODULUS, POISSON RATIO AND
UNCONFINED COMPRESSIVE STRENGTH ON ROCK
Client : M/S PETRONAS & M/S TECHNIP GEOPRODUCTION (M) SDN BHD
Job No. : Tested Date : 29-09-13
90.00
80.00
70.00
Stress (kN/mm2)
60.00
50.00
40.00 y = 250375x
30.00
y = -25933x 20.00
10.00
0.00
-0.003000 -0.002500 -0.002000 -0.001500 -0.001000 -0.000500 0.000000 0.000500 0.001000 0.001500
Strain (mm/mm)
100
Stress (N/mm2)
80 89.52 MPa
60
40
20
0
0 50 100 150 200 250 300 350
Time (sec)
PBH10-6_C3_20m.xls Page 1 - 1
CLASSIFICATION TEST
Subject Matter : Determination of Moisture Content, Particle Size Distribution for Coarse
Grained and Particle Size Distribution for Fine Grained on soil sample
submitted.
Authorized Signatories:
Mass of Mass of
Ave.
Date tested
container moisture dry soil Content
Depth container container Moisture
m2-m3 Content
m1 m2 m3 m2-m3 m3-m1 x 100
m3-m1
metre (g) (g) (g) (g) (g) % %
1 93.46 130.72 125.32 5.40 31.86 16.95
13-Nov-13
25-Oct-13
NTP 12 - 0.00 16
2 91.44 132.38 126.72 5.66 35.28 16.04
1 94.84 124.78 119.44 5.34 24.60 21.71
NTP 13 - 0.50 22
2 94.16 128.48 122.30 6.18 28.14 21.96
GLSB/SI/2566-122 (Refinery Process)/2013 15th November 2013
3 of 4
100
90
80
70
Percentage Passing,%
60
50
40
30
20
10
0
0.001 0.01 0.1 1 10 100
Grain diameter,mm
100
90
80
70
Percentage Passing,%
60
50
40
30
20
10
0
0.001 0.01 0.1 1 10 100
Grain diameter,mm
Subject : To carry out Compaction Test (6) nos. and CBR Soaked 1 mould method (6)
nos.on samples received.
Owner : MESSRS. PETROLIAM NASIONAL BERHAD (PETRONAS)
Level 73, Tower 2, Petronas Twin Towers,
Kuala Lumpur City Centre,
50088 Kuala Lumpur
Results:
Sample : Reddish brown with pale grey mottled, light purple and light yellow spotted, sandy SILT
Borehole No. : NTP-12 Depth (m) : 0.0-1.0
Method of Compaction: (1) 4.5kg rammer 27 blow, 5 layers
Modified Proctor (2) Single/separate sample
a Test No. 1 2 3 4 5 6
3
b Volume of mould (v) cm 1005 1005 1005 1005 1005
c Wt. of compacted soil + mould g 6803 6898 6984 7052 7021
d Wt. of mould g 5021 5021 5021 5021 5021
e Wt. of compacted soil c-d g 1782 1877 1963 2031 2000
f Wet density P = e Mg/m3 1.77 1.87 1.95 2.02 1.99
b
g Container no. S14 1K G17 11B 9B 14B 5B 15B 1B 7B
Moisture Content
h Wt. of wet soil + cont. g 123.1 123.3 123.2 123.6 123.4 123.5 123.7 123.8 123.8 123.6
i Wt. of dry soil + cont. g 116.0 116.2 114.0 114.3 111.8 112.0 109.8 109.9 107.4 107.4
j Wt. of container g 18.7 18.7 18.8 23.3 23.5 23.6 24.4 24.4 23.6 23.7
k Wt. of water (W w) h-i g 7.1 7.1 9.2 9.3 11.6 11.5 13.9 13.9 16.4 16.2
l Wt. of dry soil (W s) i-j g 97.3 97.5 95.2 91.0 88.3 88.4 85.4 85.5 83.8 83.7
m Moisture content m = k % 7.3 7.3 9.7 10.2 13.1 13.0 16.3 16.3 19.6 19.4
l 7.3 9.9 13.1 16.3 19.5
1.80
1.70
AIR VOID 0%
AIR VOID 5%
1.60
1.50
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
21
Note: Opinions and interpretation expressed herein are outside the Scope of SAMM Accreditation
GLSB/CV/R6971-771/13 27th November 2013
3 of 19
TOP
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.4 13.2 3
5.0 0.8 20.0 4
BOTTOM
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 1.1 13.2 8
5.0 1.5 20.0 8
Soil Description : Reddish brown with pale grey mottled, light purple and light yellow spotted, sandy SILT
Borehole No : NTP 12 Depth(m) :0.0 - 1.0
10
7
Force, kN
0
0 1 2 3 4 5 6 7 8
TOP BOTTOM
Penetration, mm
GLSB/CV/R6971-771/13 27th November 2013
5 of 19
Results:
Sample : Reddish brown with pale grey mottled, light purple and light yellow spotted, sandy SILT
Borehole No. : NTP-12 Depth (m) : 1.0-2.0
Method of Compaction: (1) 4.5kg rammer 27 blow, 5 layers
Modified Proctor (2) Single/separate sample
a Test No. 1 2 3 4 5 6
3
b Volume of mould (v) cm 1005 1005 1005 1005 1005
c Wt. of compacted soil + mould g 6789 6890 6981 7041 7006
d Wt. of mould g 5021 5021 5021 5021 5021
e Wt. of compacted soil c-d g 1768 1869 1960 2020 1985
f Wet density P = e Mg/m3 1.76 1.86 1.95 2.01 1.98
b
g Container no. C1 C2 C3 C4 C5 C6 C7 C8 C9 C10
Moisture Content
h Wt. of wet soil + cont. g 122.0 122.2 122.1 122.2 122.4 122.0 122.1 122.3 122.2 122.5
i Wt. of dry soil + cont. g 115.2 115.2 113.1 113.5 111.3 110.6 108.5 108.9 106.2 106.7
j Wt. of container g 18.7 18.5 18.6 18.6 18.5 18.3 18.6 18.8 18.6 21.7
k Wt. of water (W w) h-i g 6.8 7.0 9.0 8.7 11.1 11.4 13.6 13.4 16.0 15.8
l Wt. of dry soil (W s) i-j g 96.5 96.7 94.5 94.9 92.8 92.3 89.9 90.1 87.6 85.0
m Moisture content m = k % 7.0 7.2 9.5 9.2 12.0 12.4 15.1 14.9 18.3 18.6
l 7.1 9.3 12.2 15.0 18.4
1.80
AIR VOID 5%
1.60
1.50
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
21
Note: Opinions and interpretation expressed herein are outside the Scope of SAMM Accreditation
GLSB/CV/R6971-771/13 27th November 2013
6 of 19
TOP
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.4 13.2 3
5.0 0.8 20.0 4
BOTTOM
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 1.0 13.2 8
5.0 1.5 20.0 8
Soil Description : Reddish brown with pale grey mottled, light purple and light yellow spotted, sandy SILT
Borehole No : NTP 12 Depth(m) :1.0 - 2.0
10
7
Force, kN
0
0 1 2 3 4 5 6 7 8
TOP BOTTOM
Penetration, mm
GLSB/CV/R6971-771/13 27th November 2013
8 of 19
Results:
Sample : Reddish brown with pale grey mottled, light purple and light yellow spotted, sandy SILT
Borehole No. : NTP-12 Depth (m) : 2.0-3.0
Method of Compaction: (1) 4.5kg rammer 27 blow, 5 layers
Modified Proctor (2) Single/separate sample
a Test No. 1 2 3 4 5 6
3
b Volume of mould (v) cm 1005 1005 1005 1005 1005
c Wt. of compacted soil + mould g 6698 6804 6899 6964 6935
d Wt. of mould g 4904 4904 4904 4904 4904
e Wt. of compacted soil c-d g 1794 1900 1995 2060 2031
f Wet density P = e Mg/m3 1.79 1.89 1.99 2.05 2.02
b
g Container no. E1 E2 E3 E4 E5 E6 E7 E8 E9 E10
Moisture Content
h Wt. of wet soil + cont. g 120.1 120.0 120.3 120.1 120.2 120.4 120.5 120.1 120.2 120.3
i Wt. of dry soil + cont. g 113.0 113.1 111.4 111.3 108.9 109.1 106.8 106.6 104.4 104.2
j Wt. of container g 17.2 16.6 16.5 16.6 16.7 17.3 16.9 16.6 16.4 16.7
k Wt. of water (W w) h-i g 7.1 6.9 8.9 8.8 11.3 11.3 13.7 13.5 15.8 16.1
l Wt. of dry soil (W s) i-j g 95.8 96.5 94.9 94.7 92.2 91.8 89.9 90.0 88.0 87.5
m Moisture content m = k % 7.4 7.2 9.4 9.3 12.3 12.3 15.2 15.0 18.0 18.4
l 7.3 9.3 12.3 15.1 18.2
1.90
1.80
AIR VOID 0%
1.70
AIR VOID 5%
1.60
AIR VOID 10%
1.50
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
21
Note: Opinions and interpretation expressed herein are outside the Scope of SAMM Accreditation
GLSB/CV/R6971-771/13 27th November 2013
9 of 19
TOP
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.4 13.2 3
5.0 0.8 20.0 4
BOTTOM
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 1.3 13.2 10
5.0 1.5 20.0 8
Soil Description : Reddish brown with pale grey mottled, light purple and light yellow spotted, sandy SILT
Borehole No : NTP 12 Depth(m) :2.0 - 3.0
10
7
Force, kN
0
0 1 2 3 4 5 6 7 8
TOP BOTTOM
Penetration, mm
GLSB/CV/R6971-771/13 27th November 2013
11 of 19
Results:
Sample : Medium to dark brown with pale grey streaked, sandy SILT
Borehole No. : NTP-13 Depth (m) : 0.0-1.0
Method of Compaction: (1) 4.5kg rammer 27 blow, 5 layers
Modified Proctor (2) Single/separate sample
a Test No. 1 2 3 4 5 6
3
b Volume of mould (v) cm 1005 1005 1005 1005 1005
c Wt. of compacted soil + mould g 6802 6940 7048 7073 7010
d Wt. of mould g 5021 5021 5021 5021 5021
e Wt. of compacted soil c-d g 1781 1919 2027 2052 1989
f Wet density P = e Mg/m3 1.77 1.91 2.02 2.04 1.98
b
g Container no. A1 A2 A3 A4 A5 A6 A7 A8 A9 A10
Moisture Content
h Wt. of wet soil + cont. g 125.3 125.5 125.3 125.4 125.5 125.4 125.4 125.3 125.2 125.4
i Wt. of dry soil + cont. g 115.8 116.0 114.0 113.8 111.9 111.9 110.1 110.0 107.8 108.0
j Wt. of container g 24.5 34.6 23.4 32.2 32.9 24.9 33.5 29.3 29.5 31.2
k Wt. of water (W w) h-i g 9.5 9.5 11.3 11.6 13.6 13.5 15.3 15.3 17.4 17.4
l Wt. of dry soil (W s) i-j g 91.3 81.4 90.6 81.6 79.0 87.0 76.6 80.7 78.3 76.8
m Moisture content m = k % 10.4 11.7 12.5 14.2 17.2 15.5 20.0 19.0 22.2 22.7
l 11.0 13.3 16.4 19.5 22.4
1.80
1.70
AIR VOID 0%
1.60
AIR VOID 5%
Note: Opinions and interpretation expressed herein are outside the Scope of SAMM Accreditation
GLSB/CV/R6971-771/13 27th November 2013
12 of 19
TOP
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.2 13.2 2
5.0 0.5 20.0 3
BOTTOM
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.6 13.2 5
5.0 1.0 20.0 5
Soil Description : Medium to dark brown with pale grey streaked, sandy SILT
Borehole No : NTP 13 Depth(m) :0.0 - 1.0
10
7
Force, kN
0
0 1 2 3 4 5 6 7 8
TOP BOTTOM
Penetration, mm
GLSB/CV/R6971-771/13 27th November 2013
14 of 19
Results:
h Wt. of wet soil + cont. g 123.4 123.0 123.2 123.6 123.1 123.4 123.3 123.2 123.1 123.5
i Wt. of dry soil + cont. g 114.1 113.5 112.0 112.2 109.7 110.2 108.0 107.9 105.7 106.2
j Wt. of container g 18.7 18.6 18.5 18.6 18.5 18.3 18.6 18.8 18.6 21.7
k Wt. of water (W w) h-i g 9.3 9.5 11.2 11.4 13.4 13.2 15.3 15.3 17.4 17.3
l Wt. of dry soil (W s) i-j g 95.4 94.9 93.5 93.6 91.2 91.9 89.4 89.1 87.1 84.5
m Moisture content m = k % 9.7 10.0 12.0 12.2 14.7 14.4 17.1 17.2 20.0 20.5
l 9.9 12.1 14.5 17.1 20.2
1.80
AIR VOID 0%
1.70
AIR VOID 5%
1.60
1.50
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
21
Note: Opinions and interpretation expressed herein are outside the Scope of SAMM Accreditation
GLSB/CV/R6971-771/13 27th November 2013
15 of 19
TOP
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.3 13.2 2
5.0 0.6 20.0 3
BOTTOM
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.6 13.2 5
5.0 0.9 20.0 5
Soil Description : Yellowish brown with reddish brown mottled, sandy SILT
Borehole No : NTP 13 Depth(m) :1.0 - 2.0
10
7
Force, kN
0
0 1 2 3 4 5 6 7 8
TOP BOTTOM
Penetration, mm
GLSB/CV/R6971-771/13 17th November 2013
17 of 19
Results:
h Wt. of wet soil + cont. g 124.6 124.3 124.4 124.6 124.5 124.6 124.5 124.3 124.6 124.5
i Wt. of dry soil + cont. g 115.2 115.1 113.3 113.3 111.1 111.4 109.2 109.0 107.2 107.2
j Wt. of container g 18.6 18.7 18.8 24.4 23.5 24.4 23.7 23.3 23.6 23.6
k Wt. of water (W w) h-i g 9.4 9.2 11.1 11.3 13.4 13.2 15.3 15.3 17.4 17.3
l Wt. of dry soil (W s) i-j g 96.6 96.4 94.5 88.9 87.6 87.0 85.5 85.7 83.6 83.6
m Moisture content m = k % 9.7 9.5 11.7 12.7 15.3 15.2 17.9 17.9 20.8 20.7
l 9.6 12.2 15.2 17.9 20.8
1.80
AIR VOID 5%
1.60
1.50
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
21
Note: Opinions and interpretation expressed herein are outside the Scope of SAMM Accreditation
GLSB/CV/R6971-771/13 27th November 2013
18 of 19
TOP
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.2 13.2 2
5.0 0.5 20.0 3
BOTTOM
Penetration,mm Load, kN Standard Load, kN CBR Value
2.5 0.6 13.2 5
5.0 0.9 20.0 5
Soil Description : Yellowish brown with reddish brown mottled, sandy SILT
Borehole No : NTP 13 Depth(m) :2.0 - 3.0
10
7
Force, kN
0
0 1 2 3 4 5 6 7 8
TOP BOTTOM
Penetration, mm
CHEMICAL TEST
Samples Description : Refer to Table 1 & 2: Samples Description and Results of Analysis
Conditions of Receipts : Thirty eight bottles of water samples approximately 1.5L and twenty four
samples of soil weighing approximately 500g were received.
Authorized Signatory:
Results:
RESULTS
Sulphate Organic Chloride Passing
Sample pH Value
Content Content Content 2mm
- % % % %
1. PBH10-03/P1D2/1.00 4.0 0.07 0.1 <0.01 97
2. PBH10-05/P6D7/7.50 4.0 0.05 0.2 <0.01 98
3. PBH10-08/P3D4/3.00 4.0 0.04 1.4 <0.01 99
4. PBH10-9/P10D11/13.50 4.8 0.04 0.1 <0.01 98
5. PBH10-10/P11D12/15.00 5.6 0.05 0.1 <0.01 73
6. PBH10-12/P3D4/3.00 3.7 0.05 0.2 <0.01 98
7. PBH10-13/P7D7/9.50 6.1 0.04 <0.1 <0.01 92
8. PBH10-15/P3D4/3.00 2.9 0.49 20.9 <0.01 98
9. PBH10-16/P5D5/6.00 3.7 0.04 0.2 <0.01 97
10. PBH10-17/P9D9/12.00 4.2 0.03 0.1 <0.01 87
11. PBH10-20/P4D5/4.50 4.2 0.06 0.2 <0.01 94
12. PBH10-22/P9D10/12.00 4.3 0.03 0.1 <0.01 98
13. PBH10-23/P6D6/7.50 4.1 0.06 0.1 0.01 96
14. PBH10-30/P13D14/18.00 4.7 0.06 0.1 <0.01 95
15. PBH10-31/P11D12/15.00 4.7 0.04 <0.1 <0.01 97
16. PBH10-32/P5D6/6.00 5.1 0.05 <0.1 <0.01 22
17. PBH10-33/P13D14/18.00 4.7 0.05 <0.1 0.01 97
18. PBH10-35/P8D9/10.5 5.9 0.09 2.7 <0.01 100
19. PBH10-35/P14D15/19.5 5.4 0.04 <0.1 <0.01 99
20. PBH10-36/P12D12/16.50 6.4 0.05 <0.1 <0.01 96
21. PBH10-37/P14D14/19.50 4.5 0.04 0.1 0.01 43
22. PBH17-02/P13D14/18.00 5.7 0.07 0.1 <0.01 94
23. PBH17-04/P10D11/13.50 4.0 0.04 <0.1 <0.01 79
24. NTP13/0.50 4.6 0.08 0.4 <0.01 99
GLSB/CH/SI/2566-122(Refinery Process)/13(3) 14 November 2013
3 of 4
RESULTS
Sample pH Value Sulphate Content Chloride Content
- g/l mg/l
1. PBH10-01/GROUNDWATER 3.4 0.09 17
2. PBH10-02/GROUNDWATER 5.7 0.03 43
3. PBH10-03/GROUNDWATER 4.7 0.02 16
4. PBH10-04/GROUNDWATER 4.2 0.01 10
5. PBH10-05/GROUNDWATER 3.2 0.24 29
6. PBH10-06/GROUNDWATER 5.6 0.03 18
7. PBH10-07/GROUNDWATER 5.2 0.03 11
8. PBH10-08/GROUNDWATER 4.3 0.02 13
9. PBH10-09/GROUNDWATER 3.9 0.02 20
10. PBH10-10/GROUNDWATER 5.0 0.03 7.4
11. PBH10-11/GROUNDWATER 4.0 0.03 22
12. PBH10-12/GROUNDWATER 4.1 0.02 12
13. PBH10-13/GROUNDWATER 4.5 0.02 11
14. PBH10-14/GROUNDWATER 5.4 0.02 17
15. PBH10-15/GROUNDWATER 4.1 0.03 22
16. PBH10-16/GROUNDWATER 5.4 0.01 11
17. PBH10-17/GROUNDWATER 5.2 0.01 11
18. PBH10-18/GROUNDWATER 3.4 0.26 1900
19. PBH10-20/GROUNDWATER 5.4 0.01 11
20. PBH10-21/GROUNDWATER 5.6 0.02 18
21. PBH10-22/GROUNDWATER 4.8 0.10 6.8
22. PBH10-23/GROUNDWATER 4.4 0.02 11
23. PBH10-25/GROUNDWATER 3.9 0.02 12
GLSB/CH/SI/2566-122(Refinery Process)/13(3) 14 November 2013
4 of 4
RESULTS
Sample pH Value Sulphate Content Chloride Content
- g/l mg/l
24. PBH10-26/GROUNDWATER 4.3 0.01 19
25. PBH10-27/GROUNDWATER 3.6 0.03 14
26. PBH10-28/GROUNDWATER 4.7 0.03 8.1
27. PBH10-30/GROUNDWATER 5.6 0.03 16
28. PBH10-31/GROUNDWATER 4.3 0.03 9.9
29. PBH10-32/GROUNDWATER 4.5 0.02 8.1
30. PBH10-33/GROUNDWATER 4.5 0.01 10
31. PBH10-34/GROUNDWATER 3.9 0.02 14
32. PBH10-35/GROUNDWATER 4.3 0.02 12
33. PBH10-36/GROUNDWATER 6.4 0.02 7.4
34. PBH10-37/GROUNDWATER 6.3 0.01 23
35. PBH17-01/GROUNDWATER 6.1 0.03 12
36. PBH17-02/GROUNDWATER 4.7 0.02 8.1
37. PBH17-03/GROUNDWATER 6.1 0.02 11
38. PBH17-04/GROUNDWATER 3.6 0.05 5.0
Job No : L130366
SOILPRO TECHNICAL SERVICES SDN BHD (380315-T) Date : 19.09.2013
16 Jalan TIB-1/17, Taman Industri Bolton, 68100 Batu Caves, Selangor, Malaysia
CERTIFICATE OF CHEMICAL
Tel: 603-6188 6975, 03-6188 9964 Fax: 603-6185 5903
eMail: soilpro@tm.net.my Website: http://soilpro.com.my ANALYSIS
Notes: The tests reported herein have been reported in accordance with BS1377 : 1990, Part 3
This document shall not be reproduced except in full.
APPROVED SIGNATORY
for SOILPRO TECHNICAL SERVICES SDN BHD 19.09.2013
(Company No.380315-T)
Notes: The tests reported herein have been reported in accordance with BS1377 : 1990, Part 3
This document shall not be reproduced except in full.
APPROVED SIGNATORY
for SOILPRO TECHNICAL SERVICES SDN BHD 19.09.2013
(Company No.380315-T)