Time schedule pekerjaan pabrikasi Tie rod

No. Item pekerjaan Volume Sat Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14

1 1st rod procurement 65 btg 5

2 Rod cutting 15 btg 2

3 Rod threading 95 btg 7

4 Plate washer proc. 2 lbr 2

5 Plate cutting 200 bh 3

6 Washer holing 200 bh 7

7 Bolts & nuts proc. 1200 set 4

8 1st delivery to Jepara 50 set 1

9 2nd rod procurement 69 set 5

10 Rod cutting 19 set 2

11 Rod threading 105 btg 7

12 2nd delivery to Jepara 50 set 1

Getting P.O. 2nd procurement Assental ready S P A R E