Professional Documents
Culture Documents
Field Studies For Rating of Tungabhadra Left Bank Canal - Paper 24032017
Field Studies For Rating of Tungabhadra Left Bank Canal - Paper 24032017
Field Studies For Rating of Tungabhadra Left Bank Canal - Paper 24032017
hydrological and hydraulic data. The operation measurements were performed simultaneously
and maintenance of irrigation systems requires with the two methods to present a comparison of
collecting regular data on water levels and discharge measurement made by current
discharges. The calibration of canal sections or meter[14] which is the conventional method[2][3]
structures provides information on canal and latest developed technique, ADCP [13].
discharges and hence supports the efficient day- Results show that the relative error is very
to-day water management and regulation of small with the ADCP over the conventional
irrigation systems. The Tungabhadra Dam is method. Besides the total value of discharge, the
constructed across the Tungabhadra River, a ADCP method also offers detailed information
tributary of the Krishna River. The dam is near about velocity distribution over the cross
the town of Hospet in Karnataka. It is a section.
multipurpose dam serving irrigation, electricity
1.0 INTRODUCTION
FIGURE1:TUNGABHADRA PROJECT Tungabhadra dam Project (Figure 1) is an
interstate, Multipurpose Project between the
two states viz. Karnataka and Andhra
Pradesh. The Project consists of a High level
masonry dam constructed across
Tungabhadra River near Munirabad town in
Koppal Districts of Karnataka State. The
reservoir upstream of Tungabhadra dam has
a storage capacity of about 120 TMC. The
water from this reservoir is used for
generating 126 MW of electricity and
irrigating 3, 62,800 Ha of agricultural lands
in Karnataka and Andhra Pradesh. Water
from the dam is released in to the Left Bank
Canal (LBC) and is utilized for power
generation and irrigation in the Karnataka
state. Three power houses are constructed
on the LBC, one at the foot hill of the dam,
and other two are at Shivapur and Sanapur.
Tail water from the dam power house is
carried to Shivapur and Sanapur reservoir
through LBC. Tail water of Shivapur power
house is released in to LBC. The length of
LBC is about 225 km in Karnataka,
Operation and maintenance of this canal is
generation, flood control, etc. This is a joint
under control of Irrigation Department,
project of Karnataka, Andhra Pradesh and
Telangana after its completion in 1953. The Government of Karnataka. Estimation of
water level profiling was done at the CH 28 in canal discharge at the head at CH 28 in Mile
1, is therefore very significant.
Gauging Site
Left Bank
Main Canal
Tungabhadra
Dam
WL (FSL)
4.65
1V
4.05
1.5H 1V
1.5H
25.46
FIG. NOT TO SCALE & ALL DIMNS. IN METRES
0
3.0 FIELD MEASUREMENTS FOR prescribed in BIS 1192: 1981 and ISO 748:
TUNGABHADRA LEFT BANK CANAL 1997 using Current Meter & Echo Sounder
[1]
The field studies were carried out at .
the canal site for gauge and corresponding The discharges in the canal were also
discharge at the gauging site. The measured and confirmed by Acoustic
observations were confined to the discharge Doppler Current Profile (ADCP) using
range as indicated below. River Surveyor instrument for better
Discharges from 72.62 m3/s (2564 accuracy [13].
ft3/s) to 124.37 m3/sec. (4392 ft3/s ).
During the field measurements, the 4.0 Discharge Measurement using
discharge in the canal was gradually Area Velocity Method
increased from lower to higher water depths. 4.1 Gauge Observations
Different sets of observations were carried For confirmation of stable flow
out for different water levels in the canal [14]. condition at the gauging site, gauge
observations were made at a regular interval
3.1 Objective from two to three hours prior to
Studies were conducted in commencement of discharge measurements
Tungabhadra Left Bank Canal at ch.28 in and also during the period of discharge
mile 1, for different gauge levels to find out measurements. It was observed that zero at
corresponding discharges and establish the average bed level of the canal i.e. depth
gauge discharge correlation for the above measurements and gauge readings were
gauging site [15]. same. A gauge plate graduated in feet was
mounted on the inside wall of the gauge
well. Figure 5 depicts the view of the gauge
3.2 Methodology well at site. The gauge data, as observed
The discharge in the canal was during these studies, is given in Table-1.
measured by Area-Velocity method as
FIGURE 5: GAUGE WELL ON LBC AT CH. 28 IN MILE 1
4.2 Depth measurements using Echo located at the center of each of segment.
Sounder Velocities were measured at 0.2, 0.6 and
The canal section of base width 0.8 depth from the surface. Velocity
25.46 m (83.53 ft) at ch. 28, was divided measurements were carried out using
into 7 equal segments to cover the flow self-recording propeller type current
having uniform depth. Two segments were meter average velocity on each vertical of
marked on either sides for lower water level a segment was worked out as:
and four segments were marked for higher V V0.8
water level to cover the flow in the sloping V0.6 0.2
Vav 2
bank canal portion. Depths were measured 2
at the center of each of the vertical using Discharges were computed using
Echo sounder, where sufficient depth was values of areas of the segments and
available. Sounding rod was used to average velocity of the segment as per
measure the small depths in the end the mid section method given in IS 1192:
segments. Details of verticals are shown in 1981.
Figure 6. Depths were measured at the start Various observations were carried
and end of the measurements and average out for different gauge levels in canal
value was taken as the depth for range from 10.1 ft to 12.5 ft at the above
computation of area of the segment. site in August 2014, March 2015 and
4.3 Velocity measurements using August 2015. Details of these
Current Meter observations are given in Table 1.
Velocity measurements were
subsequently taken at the verticals
SEGMENT
WIDTH
OBSERVATION DEPTH & VELOCITY
WL (FSL) POINTS VERTICAL
O 0.2D
4.65
1V 4.05
O 0.6D 1V
1.5 H O 0.8D 1.5 H
FIG. NOT TO SCALE,
ALL DIMNS. IN METRES 25.46
5.0 ANALYSIS OF FIELD DATA The gauge and discharge data as observed
on Tungabhadra Left Bank Canal at ch 28
The technical features/specifications in mile 1 is given in Table 1 and the
as described above, clearly show that same is plotted in Figure 9.
accuracy of ADCP is higher than the
current meter used for measurements in
the canal. Hence, data collected by the
ADCP and Current Meter is compared
and better results are incorporated in
Table 1.
TABLE 1
GAUGE DISCHARGE DATA OF TUNGABHADRA LEFT BANK CANAL AT CH 28 IN
MILE 1
Based on the field studies for rating of Where Q = Discharge in ft3/s and
Tungabhadra Left Bank canal at ch 28 in
mile 1. carried out by CWPRS, Pune G = Gauge / depth in feet.
following recommendations are made:
ii) Rating curve and rating chart based
i) The gauge and discharge data is on above statistical relationship are
given in Table 1 and plot of gauge given in Figure 9 and Table 2
vs. discharge is given in Figure 9. A respectively.
statistical analysis of the above field
data revealed following relationship References:
between gauge and discharge of the 1. BIS 1192: 1981, Velocity area methods
best fit curve. for measurement of flow in open
channels.
2. Herschy RW (1985), Stream flow structures near Chicago, Illinois, April
measurement, Elsevier Applied Science October 1993: U.S. Geological Survey
Publishers Water-Resources Investigations Report
3. ISO 748: 1997, Measurement of liquid 94-4112, 48 p.
flow in open channels Velocity are 10. Operational Hydrology Report No. 13;
methods WMO - No. 519, World Meteorological
4. Chen YC, Chiu CL (2002) An efficient rganization,Geneva.
method of discharge measurement in 11. Rantz, S. E., Measurement and
tidal streams. J Hydrol 265(1 4):212 computation of streamflow, Volume 1,
224 Measurement of stage and discharge,
5. Chiu CL, Chen YC (2003) An efficient 12. Sauer, V. B. and R. W. Meyer,
method of discharge estimation based Determination of error individual
on probability concept. J Hydraul Res discharge measurements, U.S. Geol.
41(6):589596 Survey.
6. Lemon, D. D., D. Billenness and J. 13. Teledyne RD Instruments (2006)
Lampa, 2002. Recent advances in Acoustic Doppler Current Profiler
estimating uncertainties in discharge Principles of Operation a Practical
measurements with the ASFM. Proc. Primer.
Hydro 2002, Kiris, Turkey. 14. WMO 1980 Manual on Stream
7. Maidment, D.R., 1992. Handbook of Gauging. Vol I, Fieldwork. Vol II,
Hydrology, McGraw-Hill, New York. Computation of Discharge.
8. Nihei, Y., Irokawa, Y., Ide, K., and 15. Technical Report No 5348, January
Takamura, T. (2008) Study on River- 2016, CWPRS, Pune
Discharge Measurements using
Accoustic Doppler Current Profilers,
Journal of Hydraulic, Coastal and
Environmental Engineering, vol.64,
No.2, pp.99-114.