SUNRISE CITY PLOT V PROJECT

METHOD STATEMENT

FOR

FLOOR / WALL PENETRATION

FOR

ALL MEP SERVICES


METHOD STATEMENT
SUNRISE CITY
for Floor / Wall Penetration
PLOT V PROJECT
for All MEP Services

TABLE OF CONTENTS page no.

1.0 Aim .. 3

2.0 Scope of Works ....... 3

3.0 References ....... 3

4.0 Sequence of Works

4.1 General..... 3

4.2 Penetration of Floor Slab......... 3

4.3 Concrete Wall Penetration .......... 5

4.4 Brick Wall Penetration ................... 5

5.0 Safety Method........ 6

6.0 Inspection & Testing...... 7

Page 2 of 7
METHOD STATEMENT
SUNRISE CITY
for Floor / Wall Penetration
PLOT V PROJECT
for All MEP Services

1.0 Aim

To describe works associated with the installation of floor/wall penetration for all MEP Services.

2.0 Scope of Works

This method of statement covers all works relating to areas having cable racks, trunkings, trays,
conduits, pipes, ducting or any MEP services passing through floor slabs and walls. Works are
carried out based on construction schedule and detailed shop drawings.

3.0 References

Approved shop drawings.

4.0 Sequence of Works

4.1 General:

Openings of all MEP services shall be made from temporary approved timber box
formwork prior to concrete casting slab and wall.
The dimensions of timber box shall follow accordingly to the approved shop drawing
penetration.
Timber box thickness shall not be less than 15mm and within the box should have a
timber support.
The installation of timber box shall be inspected & approved by the Engineer before
casting concrete.

4.2 Penetration of Floor Slab:

Basic steps procedure for opening installation as stated below:


Approved method of statement by the Engineers.
Approved shop drawings.
Preparation of materials.
Coordination with builders prior to sleeve opening installation.
Proceeding works installation.
Inspection by the Engineers.

Page 3 of 7
METHOD STATEMENT
SUNRISE CITY
for Floor / Wall Penetration
PLOT V PROJECT
for All MEP Services

4.2.1 Setting of Timber Box For Floor Slab Openings:

Prepare materials such as measuring tape, paint marker, nails, timber box, hand tool, bar
level etc.
The outer dimension of timber boxes shall be the same dimension of opening as per
approved shop drawings. The height of timber boxes shall be higher than 100mm from
structural level.
After the formwork have been completely finished, measure and paint to mark the
position of timber box openings on the formwork.
Installation of timber boxes base on builder reference line as shown on Detail-1.
The timber boxes shall be held to the right position by using the nails driving directly to
formwork and inside the boxes.
After the installation of timber box, install additional rebar to reinforce the floor slabs
openings by builders as per Detail-1 & 2.
Cover the timber box for safety purposes.
Check the timber boxes position carefully when casting concrete to prevent any movable
position.
Timber boxes shall be removed after concrete curing been done.

MAIN REBAR

TIMBER BOX

RE-INFORCED REBAR FOR


FLOOR OPENING

NAIL

REINFORCED REBAR

NOTE:

-QUANTITY AND SIZE OF REINFORCED REBAR (1,2,3)


2 SHALL BE DEPEND TO OPENING SIZE.
3 1
-DETAILED INSTALLATION FOR RE-INFORCED REBAR
SHALL BE APPLIED EITHER JAC'S INSTRUCTION ON EI/A/046
IN CASE OF THE UNDER 700 mm OF OPENING DIAMETER
OR JAC'S REPLY ON TSN/RFI/C/119 IN CASE OF THE OVER
700 mm ONE.

Detail-1
Installation of timber box for floor openings

Page 4 of 7
METHOD STATEMENT
SUNRISE CITY
for Floor / Wall Penetration
PLOT V PROJECT
for All MEP Services

TIMBER BOX

STRUCTURAL LEVEL

100
FORMWORK FOR FLOOR SLAB

Detail-2
Height of timber boxes beside structural level.

4.3 Concrete Wall Penetration:

4.3.1 Setting of timber box for concrete wall openings:

Prepare materials such as measuring tape, timber box, hand tool, marker, bar level etc.
The installation procedure of timber box for concrete wall opening is the same with the
installation for floor openings.
It is necessary to cover both side timber boxes before setting formwork for concrete
wall.

4.4 Brick Wall Penetration:

4.4.1 Making Opening For Brick Wall Penetration:

Dimension of openings according to approved shop drawing should be coordinated with


builders.
Openings for brick wall penetration shall be coordinated with the builder when laying of
brick wall.

Page 5 of 7
METHOD STATEMENT
SUNRISE CITY
for Floor / Wall Penetration
PLOT V PROJECT
for All MEP Services

BRICK WALL SILICA CALCIUM


BOARD 25MM.T
APPROVED
METHOD OF FIRE
FIRE SEAL COMPOUND
CABLE LADDER
50 100
30

30

SILICA CALCIUM
BOARD 25MM.T
M10 ANCHOR BOLT

200 mm

LESS THAN 1000 mm LESS THAN 1000 mm

Detail-3
Filling and covering brick wall opening.

5.0 Safety Method

a. General:

The safety procedures generally have to be applied for all Engineers, Supervisors, and
Workers as stated below:
Make sure that all personal protection equipment (PPE) be provided on site before
starting of work such as helmet, safety boots, safety glasses, glove, mask etc.
Make sure that PPE must wear in the correctly way when working.
Tools and equipments shall be inspected by authorized person before carried out the
work.
Barricades and sign posts for warning shall be provided on site.
Cleaning properly after working in specific area.

b. Working on formwork for floor slab:


Workers working on formwork for floor slab must wear PPE at any time.
To follow builders warning sign on floor slab where are have openings.

Page 6 of 7
METHOD STATEMENT
SUNRISE CITY
for Floor / Wall Penetration
PLOT V PROJECT
for All MEP Services

Workers working on formwork for floor slab have to pay attention to the
openings/surrounding area.
Scaffolding and ladders shall be provided and be ready to use at any time in
order to prepare for all contingencies.

c. Removing timber box:


Barricade under floor slab opening area before removing timber boxes.

6.0 Inspection and Testing


- Materials shall be checked for quality, quantity and size by Engineer.
- Check technical installation after setting.
- Check concealed conduits
Shop drawing approved.
Material approved.
Visual Inspection:
o Check quality of concealed and exposed conduits on site.
o Check installation according to approved shop drawings.
o Check size, position and condition of concealed and exposed conduits.
Shop drawing marked as per actual installation

Page 7 of 7