Professional Documents
Culture Documents
QSGTL T-13377420 Systemisation Guidelines
QSGTL T-13377420 Systemisation Guidelines
C:\dmautop\temp\T-13377420_F001.doc
TABLE OF CONTENTS
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
8.0 REQUIREMENTS FOR THE EPC CONTRACTOR .................................................................... 17
9.0 APPENDICES.............................................................................................................................. 20
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
1.0 INTRODUCTION
For the purpose of pre-commissioning, commissioning, handover, start-up and normal
operation the complex shall be broken down. Appendix 1 shows schematically the
breakdown of the complex into trains, plants, units, SU blocks and systems.
For example, SU block 74-A-0 equals Unit 7400 Start-up Instrument Air Compressor and is
part of the utilities plant of the common train of the onshore complex. It has 3 functions:
compress air, make air on dew point spec (drying), and distribute the instrument air. These
three functions need to be/can be commissioned/started independently. Hence there are 3
systems:
Instrument air compressor
Air dryer
Air distribution
These 3 systems will go through the work process of pre-commissioning up to normal
operation (see Part IV Chapter 5).
The system definition shall serve as operational systems and commissioning system definition.
i.e., a commissioning system equals an operational system.
Towards the end of the construction phase the work shifts to a system basis to support the
system hand over and execution of the pre-commissioning, commissioning, start-up and initial
operation on a system basis.
Appendix 2 illustrates how systemisation is an integral part of implementation.
The system based pre-commissioning, commissioning and start up work requires detailed
preparation to optimise its duration. In general terms the work plan and its schedule is
developed by
1. defining systems
2. determine the activities per system
3. determine the relationship (logic) between the activities and mark those up on a logic
diagram
4. determine the duration (and other resource requirements) of every activity
5. populate a planning tool (primavera) with the data
6. analyse for robustness and optimize
The developed logic or WEF (Work Execution Flow-sheet) and planning, are used for
optimizing the C&SU phase by integrating and linking activities across all units, thus
compressing C&SU timing. When the C&SU is fully optimized the dates are fed back into the
construction and engineering phase/work to align and make sure that priorities are set at those
project phases in line with C&SU demands. Hence the scheduling can be made backwards in
time with the targeted feed-in as a fixed point to feed into the construction schedules. By doing
so it will provide the fit with the construction planning and engineering activities, thus
commissioning and start-up steer the front-end part.
The so developed logic and planning allows to determine completion dates for the various
systems (and areas) of the plant to ensure optimal C&SU, and thereafter execute the C&SU
activities in the most efficient manner.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
This note provides guidelines for the various steps
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
This systemisation approach should also be applied to all projects civil and buildings, utility
and process units as well as all supporting power and instrument facilities. Even third party
supplies and receipts like electricity and/or other utilities (oxygen/etc) will have to be integrated.
This philosophy shall therefore be incorporated throughout the various stages of the project
and coordinated by the projects commissioning manager and commissioning and start-up
planning team to ensure coherence and achievement of milestones.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
For Equipment that are common to all trains: N=0
For Equipment in Train 1: N=1
For Equipment in Train 2: N =2
And so on for additional trains.
UU is the first 2 digits of the unit number,
B is one letter A through Z except for I and O, indicating the different type of blocks within a
unit, and
b is the functional Block identifier in case of multiple strings (e.g. the nine parallel SGP
reactors); a zero (0) indicates that there are no parallel strings
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
2.3 Colour coding of systems
Colour coding shall be such that the individual systems can be easily recognised when looking
at the PEFS. For each colour mark up, a set should be compiled titled System Identification
List. This shall show every system number, system description and colour code identified.
The System Identification Lists from every colour mark up produced shall then be merged into
an Overall System Identification List.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
2.4 Some specifics on assigning items to systems
2.4.1 Instrumentation
The break between Instrument systems and other systems shall generally be at the cable
marshalling cabinets.
Subdivision shall be applied to systems, which may serve more than one geographical area
e.g. multi-core cables, junction boxes. Individual cables and segment cables shall be assigned
system numbers appropriate to the geographical area served.
External Field Bus segments shall be assigned system numbers appropriate to the
geographical areas served.
Each field instrument loop shall be assigned to the process system, which it serves.
Local indicators, pressure relief valves and other in-line devices shall be assigned a system
number derived from their locations as indicated in the process system colour mark-up.
Instrument AC Systems
Instrument AC systems shall typically include instrument ac transformers, high side breakers,
panels, incoming and tie breakers, inverters, and inverter dc supply breaker. Outgoing breakers
from the panels shall typically not be included.
DC Systems
DC systems shall typically include AC supply breakers to the source of DC generation, storage
batteries, DC buses and panels, breakers on panels for incoming DC bus supplies, and bus
ties. Outgoing breakers from the DC buses and panels to DC equipment shall typically not be
included.
Distributed Control or Monitoring Systems
Equipment scoped within the boundaries of the basic system shall typically include power
supplies, buses, operator stations, programmer stations input/output (I/O) modules,
process control stations, data links, and process interface units up to field terminations.
Generally the DCS / Field break point shall be the field side of the marshalling cabinets or
home run terminal boxes. Each unit configuration shall require case-by-case review.
System boundaries shall typically be designated: -
Cables from field devices and equipment of only one start up system to the I/O interface
(typically a programmable logic controller (PLC), multiplexer, or I/O rack) shall be scoped
with the system associated with the field devices and equipment.
If cables from several systems terminate in a common junction box and a multi-conductor
cable connects to the I/O interface, scope the multi-conductor cable in the distributed
control or monitoring system.
Where a single monitor input monitors activities of more than one system for switchgear
breakers, the cable is scoped with the associated bus.
2.4.2 Piping
Line numbers shall be assigned the system number as indicated in the process system colour
mark-up.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
Process systems shall consist of one or more hydro/service or pneumatic test packs. Test pack
number shall be advised by construction and collated against system.
Test pack limits shall not normally over run system limits. However, in the case of tie-ins to
existing lines, test pack limits may be required to overrun system limits to accommodate
spading requirements.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
heat exchanger in the appropriate system. Since the heat exchanger is always identified with
the system that it heats or cools for, it is identified with the receiver system.
Therefore, if a heat exchanger requires the service water system to remove the heat form the
closed cooling water system, the heat exchanger is identified with the closed cooling water
system since it receives a service. Similarly, if a heat exchanger requires the condensate
system to provide cooling for the steam seal system, the heat exchanger is identified with the
steam seal system.
Since the scoping of valves associated with a heat exchanger is sometimes confusing, the
following four guidelines are suggested:
Where the service system has manual isolation valves to the heat exchanger, the service
system shall be scoped to include these valves.
Where the service system has a control valve or motor-operated valve interfacing with the
heat exchanger, these valves shall be scoped with the heat exchanger, since they are
controlled by inputs from the receiving system.
Where the service system has both manual isolation valves and control or motor-operated
valves interfacing with a heat exchanger, the manual isolation valves shall be scoped with
the service system and the control or motor-operated valves scoped with the heat
exchanger as part of the receiving system.
Where there are no valves in the service system interfacing with the heat exchanger, all
piping back to the service system header shall be scoped with the heat exchanger as part
of the receiving system.
Cooling Water Systems
These systems primarily contain pumps and heat exchangers that provide heating or cooling to
the system. The piping boundaries are as follows:
Main supplies and branch headers that provide cooling to other systems in normal service.
Branch headers providing make-up or back-up supply from and including the first isolation
valve on the header.
Note that for associated piping, consideration shall be given to the pre-commissioning
activities. The system definition should support optimized blowing and flushing in terms of
longest blow paths up to e.g. the heat exchanger
Steam Generating Equipment
The steam side and fireside are scoped into separate systems, as follows:
The steam side begins at the economizer inlet, includes the water walls and drum(s), and
ends at the super heater outlet header.
The fireside includes the FD fans, over-fire / under-fire / primary air fans, air heaters, and
ductwork leaving the unit and terminates at the beginning of the flue gas treatment
equipment. In combined cycle installations with an isolation damper installed between the
combustion turbine and the steam generator, the fireside begins at the downstream side of
the isolation damper.
The steam side extends to and includes the unit drain isolation valves. Excluded are branch
headers after the first isolation valves to feed pump turbines, soot blowers, plant heating,
etc.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
Main and Reheat Steam Systems
All main steam header piping and branch headers to the first isolation valve (valve included)
from the main component supplying steam up to the turbine stop valves (valves excluded). All
turbine stop, intercept, and control valves are scoped with the turbine.
Excluded are branch headers, except those to traps and drains, after the first isolation valve to
items such as feed water pump turbines, gland sealing system, condenser air removal system,
auxiliary steam system, etc. These headers are scoped with the respective system to which
they are supplying steam.
Gland Sealing Steam and Exhaust
All piping from root valve(s) of gland steam supply (ies) to turbine seals, but excluding root
valve(s).
All piping from turbine seals to condensing units, including exhaust fans on condensing
units.
All drain pipes from turbine casing drains, turbine stop, control and intercept valves to
condenser.
Extraction Steam
All main and branch headers from turbine casing to feed water heaters and main
condensers.
All other branch headers to first isolation valve, including valve.
Ventilation Systems
Ventilation systems are predominantly building orientated, e.g., turbine-building ventilation.
However, not all fans are directly involved in the main airflow stream of the building ventilation.
Therefore, the following shall apply:
All fans, ducts, filters, and dampers required for air balancing supply and/or exhaust fans
shall be scoped the same as the main building ventilation system.
All fans, ducts, filters, and dampers that operate independently of the main airflow stream
or merely recirculate part of the main airflow stream shall be scoped as a subsystem of the
main building ventilation system
2.4.4 Electrical
Use the guidelines below to assist in determining the scope of the system and its boundaries.
Offsite power systems
The off-sites shall typically be limited to incoming transmission lines, buses, and circuit
breakers that are required to energize the yard. Transformers may be involved if they are other
than auxiliary and main unit transformers. Protective relaying required to energize the off-sites
shall typically be included with the off-sites system.
Auxiliary and Main Unit Transformer System
The auxiliary and main unit transformer system shall include the transformers, all auxiliaries, all
transformer protection, and transformer feeds on both the high and low sides up to but not
including the first device (circuit breaker, disconnect switch, removable links, etc.) that can
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
isolate the transformer. The method of isolating the main generator should be determined on a
case-by-case basis.
Power Distribution Systems
Each voltage level shall typically be scoped to include all components necessary to provide
distribution at that voltage.
First-level voltage distribution within the plant shall typically include the incoming breaker(s) or
disconnect switch (es) to the auxiliary transformer(s), auxiliaries, relay protection, low side
distribution buses, incoming feeder breakers, and bus tie breakers.
Note: Outgoing system voltages shall typically include the distribution buses for the system
voltage, the step down transformer (including auxiliaries) supplying the voltage along
with its high side breaker, all distribution bus incoming breakers from the step down
transformers, all bus tie breakers, and all associated relay protection.
Subsequent system voltages shall typically include the distribution buses for the system
voltage, the step down transformer (including auxiliaries) supplying the voltage along with its
high side breaker, all distribution bus incoming breakers from the step down transformers, all
bus tie breakers, and all associated relay protection.
Note: Incoming breakers from auxiliary generating units and outgoing breakers to motors and
lower voltage systems shall typically not be included.
Motor control centres (MCC) shall typically include MCC buses; incoming feeder breakers,
supply breakers on load centres, and any MCC tie breakers. Outgoing breakers shall not be
included. They shall typically be included with the system they service. So equipment MCC,
isolators, control cables and associated instrumentation are assigned to the process / EFD
system in which the mechanical equipment / instrument is located.
Lighting, small power / convenience outlets, and essential services supplies shall be assigned
system numbers from the main switchboard up to the local distribution board. Downstream
subdivisions shall be carried out at site, where deemed necessary, on a plant area, building,
etc basis.
UPS, instruments and electrical supply to the telecommunication system shall be assigned
instrument system numbers from the breaker at the main switchboard. This is due to the
anticipated involvement of instruments discipline in commissioning these systems.
2.4.5 Buildings
Each building shall be considered as one system. Service items within the building (HVAC, Fire
& Gas, Lighting, etc.) shall be considered as subsystems of the building system where
appropriate.
2.4.7 Tie-ins
Tie-ins are an integral part of the corresponding system, unless otherwise specified. Tie-ins
that are required independently of the corresponding system, e.g. tie-ins to third parties
(electrical grid etc) shall be clearly marked and assigned a separate system number.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
2.5 System definitions as part of other documentation
System limits and numbers shall be added to the PFS / PEFS using CAD systems as an
overlay. This will enable the production of single system drawings and the addition of system
boundary markers to the piping data sheets with again links to other data bases i.e. instrument,
electrical, civil such that the compilation of components up to process/utility system level can
easily be seen. The use by all staff concerned in the engineering and execution teams of a
single source of information gives large benefits when assessing progress, assessing what/if
scenarios and using commissioning and start-up logic/schedule to steer the construction
progress and priorities.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
Level 1 giving a high level view of blocks within the project and the way they interact with
each other
Level 2 shall give a more detailed view of the same information as stored in Level 1, but
goes to the level of units within the blocks.
Level 3 shall detail out systems within the blocks and units;
Level 4 shall contain all possible details on equipment and components in the systems, and
is as such the lowest level of detail to exist in the QGTL planning and scheduling hierarchy.
5.0 DURATION
Each activity, obviously, takes a specific minimum time, which is an input into the schedule.
There is, however, an additional issue that relates to the novelty, complexity, and carbon copy
characteristic of the system under consideration. Each category comes with its own set of
measures, precautions and tests. Novelty assessment and complexity identification shall be
done in the implementation phase of the project as part of the flawless start-up initiative.
Novelty, or prototype, items come with fall back options, which shall have their own additional
activities. Complex systems will often be built up from simpler subsystems and will thus require
additional tests on the composite system. Carbon copies will have tests that will be set by the
level of the risk that they present upon failure.
Duration for activities should always reflect realistic durations to complete the activity, and not
the duration required to meet milestones. In addition, complex or large activities should contain
an element for corrective action.
6.1 Feasibility
The schedule must be feasible, that means that the sum of activities can be done in the
indicated or planned time period. This poses a demand on availability of tools, materials,
budgets and human resources, the latter with the right competencies, experience, and training.
And, less obvious, necessary information has to be available. A feedback loop into the
integrated project schedule enables management to see if resources are available when
required with respective quality/quantity.
Having made a feasible schedule, it can now be optimized by reviewing blocks of activities and
opportunities for load levelling.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
If in the end a mismatch exists between the targeted and projected timing and if the options for
optimization have been exploited, a review must be made where an injection of additional
resources and funds can make an effective contribution in closing the gap.
6.2 Logistics
An outcome of the commissioning schedule is a list of requirements to make the schedule
feasible. These requirements relate to timely availability of things like, engineering and
construction completion, human resources, materials, temporary facilities, transport equipment,
etc. All these items together present a complex logistics challenge. This will be organized and
managed as an issue in its own right by the Project Management. Contractor and Company
representatives will manage this reviewing.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
8.0 REQUIREMENTS FOR THE EPC CONTRACTOR
This is taken from Part IV Chapter 5
The Contractor shall take the level 1 C&SU logic developed by the Company prior to EPC
contract award. The contractor shall prepare a C&SU Plan development procedure, containing
the following:
Timeline for schedule development, including systemization
Process unit integration plan
Level of detail provided to resource, equipment and material load the plan
Schedule for updates
Software requirements
Timing
The Contractor shall commence the systemization process within 3 months of contract
award, and shall present the initial individual process units C&SU schedule within six
months of contact award. This shall include critical path analysis, and risk mitigation for
these critical paths.
Nine months after the contract award, the Contractor shall have fully loaded the C&SU plan
with resources, material and equipment.
One year after contract award the complete project integrated level three C&SU plan shall
be issued for approval by Company
The plan shall be updated on a monthly basis after approval, together with full resource and
material loading
Others:
The systemization of the process units shall be approved by the Company.
This schedule shall be updated by the contactor at each revision of the PEFS
The Contractor shall dedicate resources for C&SU planning from contract award through to
start-up.
The Contractor shall include start-up planning activities in the plan, under the direction of
the Company.
Changes to the C&SU plan that affect the RFSU dates shall be issued to the Company for
approval.
The plan shall include all vendor requirements, including vendor visits.
The plan shall be fully aligned with the system pre-commissioning, commissioning and
start-up procedures developed by the contactor and Company.
A procedure shall be defined by the Contractor on the identification of systems.
It is required that the Contractor shall determine during the engineering phase the division of
the Project into systems and the extent of these systems with agreement of the Company.
Typically the start-up focal points for the units together with the day (shift) supervisors will play
an important role, since they will provide previous experience with similar units.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
Contractors Commissioning and Operations personnel shall, under the direction of a project
engineer and together with Companys process and start-up process representatives, use
approved for design flow schemes to identify systems and the sequence in which they will be
started..
System limits and numbers shall be added to the PFS / PEFS using CAD systems. This will
enable the production of single system drawings and the addition of system boundary markers
to the piping data sheets with again links to other data bases i.e. instrument, electrical, civil
such that the compilation of components up to process/utility system level can easily be seen.
The use by all staff concerned in the engineering and execution teams of a single source of
information gives large benefits when assessing progress, assessing what/if scenarios and
using commissioning and start-up logic/schedule to steer the construction progress and
priorities.
Contractor shall be responsible for:
The establishment and agreement with the Company of the index and definition of all
systems and preparation of the blank completion manuals in the home office.
The timely submission of completed documentation during the site phase.
The compilation, final submission and distribution of the system completion manuals.
Contractor shall develop a procedure defining the main links between the systemization and
other tools as well as deliverables per system. The index and definition of the systems shall be
used in construction planning so that scheduling of construction completion is synchronized
with commissioning activities.
The developed integrated planning shall be used as an interface management tool for
managing the following:
Interface with other parts of the project
Interface with engineering and construction
Interface with existing facilities
Interface with normal operation
Work process for preparation of detailed C&SU procedures
Work process for reporting
Work process for scope definition
Entire work process by delivering control tools
Microsoft Visio or equivalent has to be used as the software tool to develop the logic, which
in turn forms the basis of the C&SU schedule. Deviations from this shall be agreed with the
Company.
A common planning tool shall be used for scheduling (Primavera, or equivalent, as agreed with
Company).
The design centres teams and the central planning group exchange durations and data on a
regular basis and in the early implementation phase alignment and calculation of the total
schedule shall be done on a less frequent basis (say every week). Once the implementation
phase gets into construction the updates will become frequent and assessments shall start on
what/if scenarios etc. Finally during commissioning and start-up the updating process should
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
almost be live, so normally 3 times per day (at the end of each shift) the schedule should be
updated and distributed. A detailed communication and alignment schedule shall be developed
by Contractor.
The Contractor shall assign dedicated planning resources from the project to develop the
C&SU plan. The Contractor shall agree the overall design (structures and databases) of the
integrated plan with company prior to its development to ensure that it complies with
Companys requirements.
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
9.0 APPENDICES
Appendix 1
Completion & Start-up Hierarchy / Systemisation Breakdown
The scheme mentioned in section 1.0 above applies to the following completion and start-up
hierarchy / systemisation breakdown except that Acceptance of Work will only occur in
accordance with the Agreement and at Project Phase level.
Pearl GTL
Project
Complex
Phases
Plants
Units
Start-up
Blocks
Sytems
Eng. By: M.W.KELLOGG LIMITED MWKL Project no.: 5821 Unit no.: 0000
Location: QATAR Plant: Qatar GTL Shell Project no.: HP3000/84/QAT
C:\dmautop\temp\T-13377420_F001.doc
Eng. By:
Location:
QATAR
Appendix 2
C:\dmautop\temp\T-13377420_F001.doc
Asset Breakdown Relevance for Execution
M.W.KELLOGG LIMITED
High Level
Anticipated Operating
Example Area
INTERNATIONAL B.V.
quantities
eng proc constr pre-com com handover SU norm ops Manual
Sheet: 21 of 21
Doc no.: T-13.377.420
Shell Project no.: HP3000/84/QAT
E
Rev