Professional Documents
Culture Documents
The Arup Journal Issue 1 2017
The Arup Journal Issue 1 2017
1 2 3
4 5 6
7 8 9
1 Hong Kong Midfield Concourse: Kerun Ip /AAHK; 2 Second Avenue Subway, New York: Arup; 3 Sacred Heart Cathedral, Kericho, Kenya: Arup; 4 Second
Avenue Subway, New York: Ari Burling; 5 Ecological surveying for HS2: Arup; 6 San Francisco Museum of Modern Art: Jeff Goldberg; 7 National Forum of
Music, Wrocaw, Poland: Lucasz Rajchert; 8 Sacred Heart Cathedral, Kericho, Kenya: Edmund Sumner; 9 Hong Kong Midfield Concourse: Kerun Ip /AAHK.
Published Arup,
13 Fitzroy Street,
London W1T 4BQ, UK.
Tel: +44 (0)20 7636 1531
Fax: +44 (0)20 7580 3924
All articles Arup 2017
Issue 1 2017
www.arup.com
1 The Arup Journal 1/2017
Contents
Front cover:
Second Avenue Subway
New York, USA.
Photo: Wade Zimmerman.
Left:
San Francisco Museum of
Modern Art, USA.
Photo: Jeff Goldberg.
(now 1.6 million), the need for a new line to 5 72nd St Station (Heavy Civil) October 2010 January 2014 39
serve the east side of Manhattan was greater 6 72nd St Station (Fit-out) February 2013 January 2017 (final completion planned for October 2017) 47
than ever, particularly as pressure would 7 86th St Station (Utilities) July 2009 November 2011 28
increase with completion of the East Side 8 86th St Station (Heavy Civil) August 2011 December 2014 40
Access Project which would bring riders 9 86th St Station (Fit-out) June 2013 January 2017 (final completion planned for August 2017) 43
from Long Island to Grand Central Terminal. 10 Systems January 2012 January 2017 (final completion planned for November 2017) 60
63rd St /
72nd St Station 86th St Station 96th St Station
Lexington Ave
4.
Phase 1 was divided into ten construction west. Once the SOE walls and deck were
contracts to enable more contractors to installed, work continued below the deck
participate, increase bid competiveness, with traffic and pedestrians travelling above.
permit a better approach to staging, take into
account the different types of work involved, Where the top of rock is high between 92nd
and more readily satisfy federal funding and 93rd Streets, the SOE wall functioned
requirements. The contract for the bored chiefly as support for the decking, and
tunnels was awarded in 2007 to spearhead because it was temporary to construction of
construction (see table at image 3). the permanent 96th Street Station structure,
Construction of the two tunnels and three secant piled walls were installed. Between
new stations meant excavating approximately 93rd and 95th, however, the SOE walls were
5.
446,000 cubic metres of rock and 351,000 constructed in soil consisting of fill, over a
cubic metres of soil. Methods of construction 3m-thick deposit of organics, over sand/silty
included cut-and-cover, drill-and-blast and sand, over varved silt and clay, so reinforced
the use of a tunnel boring machine (TBM). concrete diaphragm walls (called slurry
walls in the USA) were selected and they
The tunnelling contract comprised became permanent walls for 96th Street
construction of the TBM launch box, two Station. The diaphragm walls were excavated
circular shafts at 69th and 72nd Streets, and to a maximum depth of approximately 27.4m
two tunnels from 92nd to 63rd Streets. The and also served as groundwater cut-off walls.
launch box was constructed by cut-and-cover The reinforcement cages were fabricated on
in a section of the tunnel that lay between site and lowered into the slurry wall trenches
92nd and 95th Streets, and the project was using twin-crane tandem lifting.
designed such that the launch box would
become the southern portion of 96th Street TBM tunnels
Station where the rock/soil interface exists. Two approximately 6m-diameter tunnels
were bored to serve as running tunnels
96th Street Station between the stations, with the drive lengths
This station structure was shallow in order to and sequencing arranged to coordinate with
make use of the existing 1970s-built tunnels the award of the station contracts and
to the north, and the launch box which was compress the construction schedule.
6.
situated across the full width of Second
Avenue between 92nd and 95th Streets. The first drive was from the southern end of
The depth of excavation varied between the launch box under the west side of Second and were mostly through strong rock
15.2m and 18.3m below grade, and involved Avenue, proceeding south on a straight (between 34.5 MPa and 82.7 MPa), comprising
removing rock and soil. alignment where it stopped blind-ended after competent gneiss and schist with occasional
2,195m. The machine was then disassembled pegmatite and several fault and shear zones.
The top of rock dips dramatically from 92nd and walked back through the tunnel to the
Street north towards 93rd Street, and is deep launch box and moved over for the drive The design teams initial proposal was for
between 93rd and 95th Streets. This geology under the east side of Second Avenue. From a precast concrete segmental lining as the
fixed the south wall location so that a rock here it proceeded south until 69th Street from permanent tunnel lining, to be installed in the
boring machine could be safely launched. where it bored a curve with a radius of about tailskin of a double-shielded TBM. A request
Relocation of the many utilities was staged 200m, finally holing-through at an existing from local contractors, however, led to a
to allow simultaneous construction of both bellmouth structure under 63rd Street. This cast-in-place concrete lining being designed
the support of excavation (SOE) walls and drive was approximately 2.4km long. The and it was this option that the low bidder
the deck structure, with the deck installed depth of the drives varied from 13.7m to chose. The lining was reinforced with steel
one half at a time: east side of the road, then 25.9m, with a minimum rock cover of 4.6m, fibres, rather than rebar, to facilitate
special track work required to connect 4. Located approximately 25m deep, mostly in
Phase 1 to future Phase 3 tunnels, led to competent gneiss and schist, two tunnels were bored
side-by-side, each approximately 2.5km long.
some challenging cavern configurations.
5. At 96th Street, the slurry wall reinforcement
cages for the cut-and-cover station were lifted to
Above-ground work vertical from a flatbed trailer, then lowered into the
Surface work was restricted to daytime hours wall trenches.
six days per week to reduce disruption to the 6. 96th Street starter tunnel looking south, showing
local community, though underground work TBM guide walls and temporary ventilation.
was allowed 24 hours per day, seven days per 7. Gallery excavation for a future machine room
week, with vibration constraints for blasting. above the pre-bored running tunnels at the south end
The goal of a minimum of four lanes of of 86th Street Station cavern.
traffic was met, and at the same time 8. 86th Street Station cavern excavation showing
pedestrian and emergency access for partially mined section for the top of the cavern
above tunnels already bored.
buildings and sidewalks was maintained at
9. Part-concreted station cavern showing thermo-
a minimum 2.1m width. Ground settlement, plastic waterproofing membrane in the roof.
air quality and other health, safety and
environmental requirements were specified
in the contract.
9.
To further reduce impact on the community,
construction and improve durability, and muck-house enclosures were used over
made use of a thermoplastic sheet access shafts to the mined caverns. These
waterproofing membrane. steel-framed buildings contained gantry
cranes that lifted filled muck bins from the
The connection to the existing stub tunnel, tunnel for loading into trucks at the surface.
south of 72nd Street Station, was developed The protection they provided limited noise
from a combination of TBM tunnels, and dust emission to the street. In addition,
single-track mined tunnels, and two-track when concreting began, deliveries of
caverns. The two tracks at 72nd Street reinforcing mat were lowered into the station
Station are side-by-side; therefore the cavern from the muck houses during the
geometry of the tracks from 63rd Street night, after the surface work restriction
Station must take them from the vertical cut-off, saving time, reducing impact on the
stacked stub tunnel to a horizontal side-by- environment, and minimising inconvenience
side position. This geometry, combined with to the community.
Station design
The mined stations were constructed by
drill-and-blast at a depth of approximately
45m. With the rock being of relatively low
permeability, the decision was made to
design these underground structures as
drained caverns. The groundwater collection
system runs behind the walls and under the
invert, discharging into longitudinal collector
pipes that are gravity-fed to pump stations.
is complemented by blue canopy lighting brickwork faade ties were not always
at street level. The goal was to provide an present, and some faades were leaning.
iconic blue glow to guide riders to the A two-phased approach was taken to
entrances. Of particular note is the 96th stabilise such buildings: temporary repairs
Street Station entrance, designed at the very were carried out to allow the subway
end of the project at the request of the MTA, excavations to continue, while a permanent
which wanted this canopy infused with repair was developed and implemented. The
coloured light. A double strip of bright blue preferred permanent option involved
LEDs was designed to tuck neatly into the building a timber truss within the floor depth,
canopy to achieve this. spanning horizontally to transfer load from
the front faade to the brick side-walls. The
Adjacent buildings truss was designed to withstand wind loads
Station entrances were created within the and leaning effects and it was formed using
sidewalks or inside existing buildings. Where additional timbers twinned to, and strutted
entrances had to be incorporated into older between, the existing joists. To comply with
buildings, jacks were used as temporary the requirements of local preservation 15
supports until the loads could be transferred. organisations, star-shaped plates were used
on the exterior. In addition to above-ground
Protecting all existing buildings from the tie-backs, below-ground tie-backs were 10. 96th Street Station: lifts (elevators) to the
effects of construction, particularly the column-free platform are accessed from the
required in some locations: an external steel mezzanine.
historic brownstones, was a priority. angle just below street level was used along
11. 96th Street Station: cut-and-cover
Newer buildings on piles or deep foundations the full length of the building, then tied back excavation looking south, showing the rock/
were unlikely to suffer from movements into the building by threaded steel rods to soil interface. This was the TBM launch box.
caused by open-cut excavations, but could be side walls and to the central supporting wall 12. Awaiting the first trains to run on the new
affected by vibrations from rock excavation or beam. line on opening night, 31 December 2016.
work: this was accounted for by setting 13. Entrances to 86th Street Station were
construction vibration limits. Older buildings Where necessary, construction methods were designed into the sidewalk.
on masonry rubble, many with heritage adapted to ensure the stability of existing 14. Star-shaped anchor plates were used on
features, needed greater care, and in some buildings. At 96th Street, for example, the the exterior of brownstones along the route:
instances repairs and stabilisation measures ancillary facilities could not be built on the these are historic buildings that were
reinforced with trusses and tie rods to prevent
had to be approved by New York States slurry wall used for most of the station them being damaged by excavations for the
Historic Preservation Office. because of the sensitivity of adjacent new line.
buildings, so a secant pile wall was used 15. The canopy entrance to 96th Street Station
Historical information on some of the brick both as the excavation support and as the is lit with bright blue LEDs to guide riders
buildings was inconclusive. It transpired that permanent basement wall. into the station.
21.3m
8.5m
21.3m
Air tempering
16. The height of the ancillary sections of The ancillary facilities, built at either end of
tunnel at each end of the new stations is the three completely new stations, were new
higher than the mid-section of the station
to accommodate the fans and associated
to the New York subway and important in Mezzanine occupied zone
silencers for the air-tempering system. terms of passenger comfort and safety: it is
17. During New Yorks hot summer here that water chillers are located to cool air
weather, cool air is delivered to the for an air-tempering system and where fans
platform via the air-tempering system. are housed for controlling smoke in the
18. Computational Fluid Dynamics (CFD) tunnels in the event of a fire. Platform occupied zone
analysis and Subway Environment
Simulation (SES) models were used to The air-tempering system was designed to
ensure the air-tempering system can be
operated cost-effectively.
create comfortable conditions in all seasons
at an acceptable capital and operating cost.
19, 20. The CFD and SES were also used
to develop the fire engineering strategy. Simulation modelling of the thermo and
21. Finished mezzanine-level architectural
aerodynamics determined that winter and
mid-season cooling could be accomplished 18.
fit-out complete.
by using solely the overtrack exhaust designed to direct cool air only where most
system, provided primarily for smoke needed (the platform), with temperatures
evacuation. But in hot summer weather, allowed to rise higher in the mezzanine
operation of the air-tempering system (a more transitory space), and higher still
would be needed to convey cooled air in the train ways.
through ducts onto the platform. The amount
of cooled air required was determined by a The system is novel in New York, where
Computational Fluid Dynamics (CFD) few of the stations feature air cooling
analysis that determined the airflow, and (although the subway cars themselves are
hence heat distribution, caused by the piston air-conditioned), and in the stifling heat that
effect of trains entering and leaving a station. characterises the citys summer weather, it is
As a result, the air-tempering system was a welcome innovation.
19. 21.
Fire engineering location and size of the fire. Ventilation This resulted in cost savings for the MTA
Fan plants, located within the ancillary layouts were optimised based on while also maintaining the coffered ceiling
facilities at both ends of each station, serve considerations of cost, ease of construction, and beam style.
not only that station, but also the tunnels ease of maintenance, complexity of
between stations. These are designed so that operation, reliability, and performance under Fire suppression within the stations was
in a fire emergency, the following will fire conditions. The design demonstrated that provided by means of fire standpipe (stations
happen: the requirements for handling three separate and tunnels), wet pipe sprinklers (various
and distinct emergency conditions in back-of-house spaces), Inergen (in select
Within a station, semi-transverse communication/signalling spaces), and water
ventilation will remove smoke-laden air via stations, tunnels or crossovers could be
served by a single integrated plant, mist sprinkler systems (elevators/escalators
overtrack exhaust at the platform level, and and associated machine rooms, select
via high-level exhaust at the mezzanine eliminating the need for dedicated
ventilation systems. communications and electrical rooms, and
level to maintain tenable paths of egress. under-platform protection). Fire alarm
Within tunnels, fan plants at the two Structural fire engineering methods were systems are designed to enable manual
adjacent stations are configured to develop used to verify that existing partially encased operation in the public areas and automatic
longitudinal airflow sufficient to achieve steel beams at 63rd Street Station did not detection in the back-of-house spaces. The
critical velocity, and at special track require full encasement because they met station public address (PA) system that is used
sections, such as crossovers, means are the two-hour fire resistance rating, and to alert station users in case of emergency is
provided for semi-transverse ventilation to maintained their structural integrity under supplemented by various means of visual
maintain tenability. the design loading specified by the NYCT. notification in the public spaces.
The study investigated the behaviour of each
The design performance was verified of the beam types when exposed to a subway Fire engineering scope was split across
through a combination of computational car fire and a standard fire test exposure. multiple contracts, so coordination among
fluid dynamic and subway environment Two-dimensional finite element modelling the design and construction team was
simulation modelling. Tenability was was performed using the analysis software paramount to ensure delivery of fully
evaluated in relation to timed egress SAFIR. The structural capacity utilisation functioning systems, as well as access to
assessments that considered the potential was analysed using the thermal profile of equipment for future inspection, testing and
availability of egress elements based on the each beam after the prescribed fire exposure. maintenance.
22. 23.
Acoustics
The intelligibility of announcements is
clearly critical within stations and the new
PA system developed for Phase 1 is
noticeably improved compared with others
on the New York subway network. This is
due to a combination of factors, many of
which evolved from an analysis of what was
wrong with existing PA systems: it was
necessary to do this because the new and
existing systems had to be integrated. Using
Arups SoundLab, each part of the
communication signal chain affecting the
overall quality of the announcements was
assessed: from the announcers booth and
the microphone, through amplifiers and
cabling, to the speakers and geometric layout
in the station.
24.
Background noise was clearly one of the
most significant problems, so sound- Vibration that causes the rumbling noise amount of rail vibration transmitted to the
absorbing finishes were integrated into the when trains pull into stations was a problem tunnel invert and buildings above. This was
station form. The most widely used were both below ground and above. So, before considerably more expensive than using
perforated ceramic and metal panels backed Phase 1 was built, site measurements were traditional timber, but the resulting reduction
with a fibreglass core, inset into the concrete. conducted to capture source vibration levels in noise and vibration was significant.
Additional sound-absorbing finishes were from existing lines, and this data was used to
applied at track level to reduce noise from predict potential vibrations from the new line. The PA system is essential to the evacuation
wheels on rails, and also at the ends of stations procedure in case of emergency, so a
to reduce train entry noise at crossovers and Various mitigation schemes were considered high-quality system was specified to meet
switches. Silencers were placed at each end of and the solution chosen was a Low Vibration intelligibility requirements mandated by the
the ventilation system fans: large units that are Trackform (LVT) consisting of individual US National Fire Protection Association
2.5m high, so they had to be designed into the concrete blocks that fasten the track to the (NFPA), with speakers located strategically
ancillary facilities early to ensure there was ground but are separated from the trackform throughout the stations.
space for the rest of the ventilation equipment. concrete by rubber boots, to reduce the
26. 27.
IT, communications and control systems The thermal comfort in the stations is much 22. Rails are fastened to the ground via concrete
Integrating new control systems design into improved by these systems compared with blocks that are separated from the trackform
concrete by rubber boots to mitigate the
an existing operating subway infrastructure, traditional NYCT stations. An added rumbling as trains enter and leave stations.
built by separate independent railway aesthetic value is that the station finishes are 23. Silencers two at either end of each station
companies more than a hundred years ago, not cluttered with multiple conduits and mitigate noise from the ventilation fans.
and adding intermediate updates and service runs. 24. On the platform at 96th Street Station, the
patching, proved both a challenge and an noise-absorbing panels made from ceramic,
opportunity. Pedestrian modelling metal and fibreglass are clearly visible, inset
Intrinsic to the overall design of the stations into the wall.
A SCADA (supervisory control and data was a comprehensive approach to modelling 25. Pedestrian modelling techniques helped
acquisition) system was implemented, using the way people would use them. As this was determine the location of escalators, stairs and
elevators. Here, plenty of space is provided in
technology based on direct digital control the first subway construction project in New a brightly lit transit area that features some of
and programmable logic control, to integrate York for more than 50 years, there were no the artwork that was designed for all stations.
the systems for new station-based heating existing design guidelines for passenger In peak hours, this area is busy as travellers
and ventilation, including the air-tempering movements so in the early days of the ascend and descend between platforms and the
system. Allied to this was a wider rail Phase 1 project (20022003), design street-level entrance/exit.
control system focused on ventilation within parameters and performance metrics were 26. A new seating area and lighting at 63rd
Street Station entrance: pedestrian modelling,
the tunnels (including emergency smoke established with NYCT, many of them new combined with community consultation, helped
management should it be necessary), track to the system. to determine the location of sidewalk
and station drainage, traction power systems, infrastructure.
high and low voltage power systems, and all A model was developed that simulated 3,000 27. The customer service area at 96th Street
station lifts (elevators) and escalators. uptown and downtown train arrival Station, sized to accommodate current
combinations to better understand the effects passenger peak flows, plus future growth.
The entire control systems communication of simultaneously arriving peak-loaded
network design incorporates a system-wide trains. The data was drawn from the existing
IP-based converged network (SONET: Lex Line 4/5/6 trains and it focused on the
Synchronous Optical Networking) that number of entering and exiting passengers
enables control and monitoring of systems at peak times, and the delays that occurred
both locally and remotely, so not only within regularly at Lex Line stations including
stations but also from maintenance facilities, queuing at escalators and stairs, with
emergency response locations, and rail and attenuation to the mezzanine, through the
power control centres, for example. This turnstiles and up through the exits. Where
provides maximum redundancy and, most appropriate, models also included transfer
importantly, reliability for rail operations. passengers and movements.
28.
Dynamic pedestrian simulation models were reduced travel time and traffic congestion, Authors
developed for Phase 1 and used as a design but also taking into account reductions in David Caiden, Chief Engineer for AAJV, 20072015,
is an Arup Fellow.
tool to optimise elevator, escalator and stair road accidents and emissions, and increased
Craig Covil, Arup Project Director, 20152017.
provision and layout, and also to evaluate productivity. The estimated property value
emergency evacuation scenarios. The models premium is a one-time amount of $4.71 Richard Giffen, Chief Structural Engineer for AAJV
from 2009 to 2016 and Chief Engineer from 2015 to
were extended out at street level to help billion (assuming 10% increase in value 2017, is an Associate Principal at Arup.
ascertain the locations for sidewalk for property within a 0.5 mile radius of the Richard Potter, Chief MEP Engineer for AAJV,
infrastructure such as the lighting and four stations). 20022017.
signage related to the new entrances. The Chu Ho, Chief Geotechnical Engineer for AAJV,
models proved very useful for community But it is about more than numbers because for 20132017.
information meetings during the planning individuals the time savings can contribute to Joe Solway, Lead Acoustics Consultant for AAJV,
stages and during construction. better work/life balance. People living along 20022017.
the route can now ride to many destinations
Summary throughout the city without changing trains. References
Final Environmental Impact Statement:
Selected by the American Society of Civil Along the way, they can enjoy Wi-Fi http://web.mta.info/capital/sas_docs/feis.htm
Engineers as its 2017 Construction availability in stations, artwork by renowned Record of Decision: http://web.mta.info/capital/sas_
Achievement Project of the Year, Phase 1 has contemporary artists (commissioned by the pdf/2004RODwithletter1.pdf
already improved the way people travel MTA, it is the most expansive permanent KPMG (2015) Value of the MTA Capital Program,
around New York. Average weekday public art installation in New Yorks history), Final Report 13 March 2015
ridership, up every month since opening, had fewer stairs (there are more escalators than in Jay Landers, (2017) Second Act Civil Engineering,
reached 176,000 by May 2017, with the trend traditional stations), wider walkways and ENR, April 2017
continuing upwards as commuters discover welcoming bright lighting. It adds up to a Trabold, M., Giffen, R. and Lemus, P. (2016) The Light
the lines benefits. Congestion and related safer and more enjoyable travel environment. at the End of a 40 Year Old Tunnel Retrofitting of an
delays on the Lex decreased over a similar Existing Tunnel as part of The New Second Ave Subway
time frame by 26% overall, and as much as New York State Governor, Andrew M. Project, New York, World Tunneling Congress, San
Francisco, CA
40% during peak morning hours, according Cuomo, said in February 2017, just a few
Tabarra M., Alston J., Potter R. and Abi-Zadeh D.
to MTA statistics. weeks after Phase 1 was opened: The (2006), Integrated Ventilation Systems Design of the
Second Avenue Subway has already become Second Avenue Subway, 12th ISAVVT, BHR Group,
KPMG reported for the MTA that the an integral part of the Upper East Side and Portoroz, Slovenia, July 2006, SBN 1 85598 076-2,
estimated annual benefit of Phase 1 in the the ridership figures show just how important Vol II, pp. 583596
year 2030 (expressed in 2015 dollars) will be this expansion project is to the neighbourhood
Project credits
$265.4 million, the saving based largely on and our economy. Owner: Metropolitan Transportation Authority Capital
Construction (MTACC) and New York City Transit
Authority (NYCT) Prime design consultant: AAJV (joint
venture of AECOM and Arup) Geotechnical engineering
for conceptual and preliminary engineering design, soil
and rock testing: GZA GeoEnvironmental, Inc Abi-Zadeh, Robert Accosta, Kevin Acosta, John Leung, Adela Levy, J Levy, Peter Li, Shawn Li, Danny
Geotechnical engineering for conceptual and Alexander, Katie Alfredo, Jonah Allaben, Jarrod Alston, Lin, Hillary Lobo, Paul Longhurst, Sebastian Lopez,
preliminary design: MRCE Architectural input for Joseph Appleby, Aidan Archer, Chris Ariyaratana, James Lord, Al Lyons, Filip Magda, Tom Maguire,
conceptual and preliminary design: FXFOWLE Architect Stephane Audrin, Peter Ayres, David Balter, Alison Theresa Mahoney, Yazdan Majdi, Swarup Mandal, Chris
Environmental services for conceptual and preliminary Barmas, John Barrot, Alban Bassuet, William Manning, Andrew Marchesin, Glennys Marmolejos,
design: Metcalf & Eddy, Inc. Geotechnical support staff Baumgardner, John Beaumont, Jonathan Ben-Ami, Chris Marrion, Ivan Martynenko, Nazir Mawjee, Chad
and peer review: RIZZO Associates Geotechnical Burkhard Bein, Peter Berry, Rinita Bhadra, Rami Bitar, McArthur, Pat McCafferty, John McCracken, Brian
engineering services: YU & Associates, Inc Ryan Biziorek, Gillian Blake, Justin Bocian, Michael Meacham, Tali Mejicovsky, David Mellon, Alan Merrett,
Environmental impact analysis: AKRF, Inc. Consultant Brandes, Fergal Brennan, Peter Bressington, Cillian Ashraf Metwally, Vahndi Minah, Strachan Mitchell,
construction manager: WSP/Parsons Brinckerhoff Brown, Ian Buckley, Jenny Buckley, E Bury, Lowell Jessica Moeller, Carlos Molina Hutt, Erin Morrow, Wil
Launch box for TBM at 96th Street and tunnels to 63rd Cabangon, Yan Cai, David Caiden, Mellisa Capowski, Nagengast, LJ Nassivera, Barry Nicholls, Peter
Street: S3 Tunnel Constructors, a joint venture of Michael Capuzzi, John Caroll, Carlos Carranza-Torres, Oldroyd, James Olson, Robert Pallman, David Palmer,
Schiavone Construction Co. LLC, Skanska USA Civil, Bob Cather, Bianca Celestin, Eun-Ju Cha, Foram Lynn Pang, Wilfred Patrick, Jennifer Pazdon, Adrian
and J.F. Shea Construction, Inc Heavy civil works for Chaliawala, Peter Chamley, David Charters, Ho-Yan Pena-Iguaran, Nicos Peonides, Daniel Peterson,
96th Street Station: Joint venture of E.E. Cruz & Cheung, Helga Chmielowski, Jonalen Chua, Matt Clark, Richard Petrey, Don Phillips, Sam Plourde, Seth Pollak,
Company Inc. and Tully Construction Co. Inc. James Cohen, Neal Corridore, Anthony Cortez, Craig Richard Potter, Martin Preene, Mark Presswood,
Rehabilitation of 63rd Street Station: Judlau Contracting Covil, Helen Crosby, Casey Curbow, Richard Custer, Richard Prust, Thomas Puttman, Craig Quaglini, Jim
Inc. 72nd Street Station, cavern mining, and connecting Carmen Danescu, Star Davis, Juan De Los Rios, Frank Quiter, Parisa Rajaei, Mahadev Raman, Rene Rieder,
tunnels between 72nd Street and 63rd Street Stations: Del Gigante, Mike Devriendt, Nicola Dobbs, Matt Robb Risani, Eric Rivers, Vicky Rom, Ron Ronacher,
SSK Constructors, a joint venture of Schiavone Dodge, Filipa Duarte, Glenn Edwards, Robert Egan, Jonathan Rose, Sarah Sachs, Stefan Sadokierski, Yet
Construction Co. LLC, J.F. Shea Construction, Inc. and Khlaid Eid, John Elissa, Ed Ellis, Johnson Esho, Sang, Maxim Sankey, Yuvaraj Saravanan, Rob Saunders,
Kiewit 72nd Street Station finishes: Judlau Contracting, Reynaldo Espiritu, Karim Ezzeldin, Steven Fairneny, Jin Yuliya Savelyeva, Kurt Schebel, Ian Schmellick, Nando
Inc. 86th Street Station excavation, utility relocation, Fan, David Farnsworth, Ian Feltham, Chris Fesq, Marc Schmitt, Leni Schwendinger, David Scott, Eric Sekulski,
and road decking: DAnnunzio & Sons, Inc. 86th Street Florestant, Paul Franklin, Marsha Fraser, Frank Sheldon Sherman, Christopher Simon, Duncan Smith,
Station, heavy civil: Joint venture of Skanska USA Civil Freudenberger, Chad Fusco, Eci Garavito-Bruhn, Louis Ernest Smith, Julian Smith, Marsha Smith, Tom Smith,
and Traylor Bros. Inc. 86th Street Station finishes, MEP Gargiulo, Ken Garmson, Marc Gateau, Bethel Gebre, Nik Sokol, Keith Solberg, Marina Solovchuk, Joe
(mechanical, electrical and plumbing), ancillary Graham Gedge, Amirreza Ghasemi, Shaaz Ghouse, Solway, Brian Stacy, Robert Stava, Pascal Steenbakkers,
buildings, and entrances: Joint venture of Schiavone Richard Giffen, John Gill, Ken Goldup, Rico Gomez, Jimmy Su, Nick Suslak, Matt Sykes, Visha Szumarski,
Construction Co. LLC and John P. Picone, Inc. Graham Goymour, Richard Greer, Helga Gregory- Mohammad Tabarra, Chris Taylor, Christopher Taylor,
Systems, track, signal, and traction power: Joint venture Chmielowski, Tom Grimard, Don Guan, Nancy Ian Taylor, Larry Tedford, Maria Theodori, Bob Till,
of L.K. Comstock and Skanska USA Civil lead and Hamilton, Andrew Harrison, Mike Hastings, Paul Neil Towell, Ed Tufton, Andrew Valente, Thomas Van
asbestos surveys and design, support during hazardous Heslop, Stephen Hill, Lucy Hirst, Bruce Hlvana, Chu Puyenbroeck, Aniju Varughese, Sasha Velic, Tony
material investigation and remediation design, and Ho, Trevor Hodgson, Stuart Hodgson, Nicole Hoffmann, Vidago, Tom Wagner, Lorna Walker, Naor Wallach, Kim
environmental and geotechnical survey: Matrix New Robert Hoffmann, Ken Hope, Robert Hsu, Shuang Hu, West, Jacob Wiest, Craig Wiggins, Daniel Wilcoxon,
World Engineering Project management, project George Hummel, Jon Hurt, Peter Ingato, Elisa Iribarne, Patrick Wilfred, Michael Williams, Andrew Wisdom,
controls, design leadership and management, Matt Jackson, David Jacoby, Ernesto Janica, Mateusz Christopher Wood, Eileen Wood, Neill Woodger, Nerik
geotechnical engineering, use of geographic information Jankowiak, Clare Judge, Deepak Kandra, Kai Kang, Yakubov, Stephen Young, Yelena Zolotova.
systems (GIS), tunnelling, civil and structural Mia Kang, Michael Keane, George Keeber, Tony
engineering, MEP, station design and architecture Kelava, Tom Kennedy, Mahmood Khwaja, Daniel Kim, Image credits
including faades and vertical transportation, fire Jonathan King, Kevin Kleyla, Tatiana Kokorina, Jacob 1, 10, 13, 15, 21, 2427 Charles Aydlett; 2, 12, 17, 19,
engineering including ventilation strategy, rail Koshy, Natalia Koupanou, Jaewook Kwon, Hannes 20 Arup; 4, 16, 18 Martin Hall; 6, 11 Ari Burling;
information technology and communications, lighting, Lagger, Iraklis Lampropoulos, Gary Lamonica, Susan 8 Richard Barnes; 5, 7, 9, 14 AAJV; 22, 23 Joe Solway;
pedestrian modelling, acoustics, vibration, security, Lamont, Barbara Lane, Matt Larson, Holly Lattin, Bob 28, 29 Wade Zimmerman.
sustainability, energy consultancy: Arup Davar Lau, Matthew Lawrie, Adrian Lee, Seungwon Lee, Colin
1.
1. The main concert hall at the National Introduction Opened in September 2015, the NFM
Forum of Music is designed using The National Forum of Music (NFM), a new integrates a 1,800-seat symphonic concert
coupled volume acoustics to prioritise
both clarity and reverberence. performing arts centre in Wrocaw, Poland, hall and three smaller, flexible concert
2. A distinctive building within
is garnering widespread acclaim for the venues. As the acoustics and theatre
Wrocaws old town, the concept for world-class acoustics of its four concert designers, Arups scope included visioning,
the NMF was devised by Kurylowicz spaces. The project is a cornerstone of the programming, site selection, construction
& Associates. citys economic development strategy and cost modelling, pre-architectural acoustic
3. The measured background noise a catalyst for the vibrancy and remarkably and theatre concept development, strategic
levels of this chart show how the N1 fast growth of Wrocaws musical business case development and operations
criterion is the measure of the most
ambitious acoustic environments.
community, which provides a variety of planning, architect selection support, and
events and educational opportunities for traditional design and construction
local residents. For its work on the project, responsibilities. In addition, the firm was
Arup was awarded a commemorative medal construction engineer for the project, and
recognising the firms contribution to the provided post-commissioning artistic
cultural life of the city. operations support during the NFMs first year.
Construction cost
Recent projects worldwide have
demonstrated how cost management is 2.
particularly challenging in major concert hall
developments, with projects often delivered Quiet spaces Octave band background noise level
very considerably over budget. As part of Acoustic intimacy was a key goal of the 80
Arups strategic advisory service, the firm project and the team agreed from the outset
undertook a robust cost-modelling process that the starting point was a silent concert
70
technical concepts was an important part of the threshold of hearing published in 1964:
the decision-making process, recognising D.W. Robinson and L.S. Whittle, The
50
PNC55
Sound level (dB)
that these spaces were both the leading Loudness of Octave-Bands of Noise, PNC50
the City of Wrocaw, with the robustness of air supply through specially designed seat
PNC25
the initial modelling enabling them to pedestals in the concert hall and careful 10
NFM PNC20
require the design and construction teams to design and layout of the mechanical and
PNC15
the NFM was delivered at a construction Structural isolation of the large concert hall
Octave band centre frequency (Hz)
3.
cost fully in line with the initial estimates. from the surrounding building through a
series of natural rubber and steel composite
Design challenges pads was also necessary to ensure that no
The technical design of the concert halls external vibrations cause audible disturbance
meant developing auditoria that would within.
accommodate the facilitys eleven resident
ensembles and seven resident festivals Airborne noise isolation planning required
without acoustical or operational two massive layers of concrete construction
compromise, as well as achieve an aspiration separated by airspace between the hall and
for the large concert hall to be acclaimed any source of noise, while all entrances were
internationally for a uniquely recognisable isolated by sound and light lock vestibules.
sound signature. Combined with the limited
budget, these challenges necessitated The three smaller performance spaces in the
innovative, refined and efficient design facility were likewise isolated so that all
solutions. spaces could be used simultaneously for
recording, rehearsal or performance.
12
4
10
5
10 11
11
3
6 clarity and reverberence: two attributes
1 2 9 that naturally sit at opposite ends of the
8
spectrum. The couplings of these volumes
are controlled via motorised concrete panels
(or doors) for lateral acoustics control
1 Stage reduction lift 4 Acoustic canopy reflectors 7 Technical attic 10 Production lighting and sound chambers as well as the canopy reflectors
2 Stage extension lift 5 Acoustic control chamber doors 8 Base building isolation 11 Control booth
above. Arup has unique global expertise in
3 Chorus wagon and lift 6 Orchestra platform 9 Underfloor air supply 12 Followspot booth
coupled volume concert halls.
20
10
Z 0
-10
20
-20
-20 0
Y
0
X -20
20
7. 8. 9.
the location and coverage of the cloth space, and yet for the audience the feeling Project credits
systems, and the materiality, macro and is one of intimacy. Client: City of Wrocaw Architect: APAKA/Kuryowicz
& Associates Performing arts design and planning:
micro shaping of the hall. The technical Arup Ed Arenius, Alex Colodner, Adam Foxwell, Tateo
concept was developed during pre-design, Dr Konsendiak concluded: We chose Arup Nakajima, Michael Parella, Leonard Roussel Business
and subsequently further developed with the for the amazing track record they have in and operations planning, IMG Artists Arup Ian
project architects. concert hall design around the world and Smallbone, Eleanor Hope, Geoff Street Cost modelling:
Davis Langdon, Ethan Burrows. Construction engineer:
theyve delivered a fantastic facility for us. Arup Katarzyna Andrzejewska, Marcin Babinski,
Summary Theyve been a great partner in this project. Malgorzata Ferdek, Michal Janicki, Andrzej Kamler,
The result of a 12-year client advisory Lukasz Knapczyk, Piotr Napiorkowski, Jan
relationship with the City of Wrocaw, the Authors
Zabierzewski.
NMF opened in time for the citys year as Ed Arenius, Associate Principal in the New York office,
Image credits
European Capital of Culture in 2016. co-led auditorium design and facility planning.
1, 2, 8 Lukasz Rajchert (NFM archives);
Kelsey Eichhorn is Senior Communications and 3, 4, 5, 6, 7, 9 Arup.
Paul McCreesh, founder and director of Storytelling Specialist in the New York office.
the Gabrieli Consort which performs Tateo Nakajima is Director/Principal, arts, culture and
internationally, said of the new venue: entertainment, New York and London. He was Project
one feels immediately a great warmth in Director and co-led the auditorium design and facility
planning
the sound and a natural balance in the large
Ethiopia
South Sudan
Somalia
Uganda
Kenya
Kericho
Democratic
East African Rift
Republic of
the Congo
Tanzania
Mozambique
Zambia
Madagascar
2. 3.
Context complete and deliver the building through with a design life of 100 years, during which
Kericho is in the heartland of Kenyas to completion, with specific inputs to the time an earthquake may well occur. The
tea-growing industry, 250 miles north-west fair-faced concrete construction, and study was conducted by collecting existing
of Nairobi, high in the Rift Valley. The acoustics and lighting commissioning. geological, tectonic and seismological data,
plantations attract workers from miles Skilled local artisans were involved in reviewing published seismic hazard studies
around, making it a diverse community that developing artworks in and around the and performing deterministic seismic hazard
has experienced some political and civil cathedral, including a natural-stone wall analysis (DSHA) of the site.
unrest in recent years. Church is a source mosaic designed by artist John Clark.
of unity, so the Roman Catholic Diocese The DSHA was used to compute the hazard
of Kericho decided to replace its existing Working in a seismic zone level. A median peak ground acceleration
building with a new and bigger cathedral Located close to the eastern branches of the (PGA) of 0.2g was estimated using the
that would seat a congregation of up to East African Rift System (EARS), Kericho is maximum possible magnitude earthquake
1,500 people. in a seismically and volcanically active zone. on the rift, and, on the basis of the study,
The geology of the site is largely volcanic in a bedrock PGA of 0.2g with a return period
Bishop Emmanuel Okombo wanted a origin. A thin layer of topsoil less than of 475 years was recommended as a
building that was spacious and airy, with 200mm thick overlies a band of red clay that moderately conservative value appropriate
surrounding gardens that could is about 20m thick. Beneath the clay is to progress engineering design. A brief view
accommodate additional worshippers on weathered phonolite tuff (a volcanic rock) of other geo-hazards was undertaken and the
special occasions. John McAslan + Partners of unknown depth. The red clay is potential for liquefaction, shakedown
were appointed as the architects and approximately 80% clay and 20% sand. settlement and slope instability was
McAslan invited Arup to help them develop considered to be low.
the design. Buildings in Kenya are typically built to
comply with a code of practice that dates The desk study was linked to a paper Arup
The resulting building is approximately back to 1973: a document that contains was developing to bridge the gap between
1,375m2, and up to 25m high, tapering reasonable seismic design advice in broad the existing Kenyan code of practice and
down to 10m at the entrance. The ceiling of terms, but was not well suited to a large, more recent and comprehensive seismic
concrete arched frames is interspersed with unusual structure such as the cathedral design standards, which would be applicable
timber ribs and the inclined roof is clad and, at more than 40 years old, no longer to all future projects in the region. This paper
with locally made clay tiles. Its base is clad reflective of current seismic engineering was published at the 2014 European
in the most durable of local stones: Nairobi practice. Conference on Earthquake Engineering and
blue stone. Seismology and may be incorporated in a
A seismic hazard desk study was carried out, National Annex to the relevant Eurocodes
Arup provided civil, structural, building therefore, to establish seismic design criteria that are currently under development in
physics, acoustics and lighting consultancy appropriate to the Kericho site. This was Kenya.
to develop the design of the building, then regarded as essential because the cathedral
supported Kenyan engineering firms to will be a building of cultural significance,
14.
16. 17.
19. 20.
Summary The Civic Trust, which organises Europes Caroline Ray was the Project Director, and she is a
Sacred Heart Cathedral was consecrated in longest-established built environment structural engineer. Working from Arup, Botswana, and
later in Kenya, Caroline delivered Arups input to the
May 2015. The service was led by the awards for projects that provide cultural, site phase of the project.
Archbishop of Kenya, and attended by the social, economic or environmental benefit,
Nuncio to Kenya and South Sudan, several presented one of its 2017 Special Awards to Project credits
bishops, and a congregation of thousands of the Kericho Cathedral team. In addition, the Client: Roman Catholic Diocese of Kericho Architect:
John McAslan + Partners Executive architect: Triad
people from miles around, who packed into project was a winner in the Surface Design Architects Ltd QS: Barker and Barton Electrical and
the building, the grounds and surrounding Awards (light and interior surface) and mechanical engineering: EAMS Structural engineering:
streets. Choirs from neighbouring areas received the Judges Special Award at the Arup and Eng Plan Building physics (natural
joined together to lead the singing. British Construction Industry Awards 2016. ventilation), lighting, acoustics, sustainability advice:
Arup Main contractor: Esteel Construction Ltd
Furniture design and entrance doors: Studio Propilis
The cathedral is exceptional in the way it Most importantly, however, the Diocese of Stained glass and artworks: John Clark, Glasspainter.
has been delivered in a relatively remote Kericho has gained the cathedral it wanted to
Arup Pavlina Akritas, Francesco Anselmo, James
region. The international and local teams help serve and unify its congregation into the Beer, Junko Inomoto, Alison Gallagher, Edward Hoare,
have worked well together to harness best long-term future. Unoda July, Jacob Knight, Ziggy Lubkowski, Boster
practice in seismic engineering, structural Matenga, Olise Mhone, Rohit Manudhane, Caroline
design, natural ventilation, acoustics and Ray, Sam Wise.
Authors
lighting, while at the same time respecting James Beer is a Senior Consultant. He guided the sound Image credits
the local environment and the needs of system commissioning. 1, 2, 17, 20, 21 Edmund Sumner; 3, 5, 6, 7, 13 Martin
church and community. The quality is Katherine Coates, Associate Director, Infrastructure, Hall / Arup; 412, 15, 18 Arup; 14, 16 John Clark;
notable, with local teams demonstrating has been instrumental in developing Arups knowledge 19 Tim Vaulkhard / Triad.
outstanding skill in delivering a structure of seismic design criteria in East Africa.
larger and more complex than they would Edward Hoare was the Project Manager and lead
structural engineer.
usually work on, to an exceptionally high
standard. Jacob Knight is an Associate with the firm. He is a
mechanical engineer and building physicist.
1.
Location Introduction tight urban site the new building rises out
California, USA At San Francisco Museum of Modern Art of a relatively small footprint, its frontage
(SFMOMA), a dramatic expansion to the just 25m wide, then broadens, higher up, to
existing building reimagines the gallery create space for artworks, events,
Authors experience and provides a new gateway into conservation and administration. Other
Denis Blount Joshua Cushner Star Davis the city. It seeks to engage local conditions facilities include two multipurpose
Raj Patel Eric Rivers Leonie van Ginkel and communities, thus realising the performance spaces, the White Box Theatre
museums goal of being a welcoming centre and the Wattis Theatre.
for arts education and an important public
space for the Bay area. Arup provided fully integrated services in
acoustics, audiovisual and theatre consulting;
The new expansion runs contiguously along lighting and daylighting design; faade
the back of the existing building, allowing consulting; pedestrian and people flow,
for a seamless integration of the two including MassMotion simulations. This
structures that doubles the exhibition space article focuses on the work Arup did for
while also expanding the un-ticketed gallery SFMOMA, in collaboration with Snhetta,
areas and outdoor public spaces. And it is EHDD Architects and other partners.
part of a design that makes the most of a
The faade
The faade undoubtedly makes a statement
on the skyline. What is less evident is the
material from which it is made. Although
white stone comes to mind, the building
billows outwards, like a ships sail, in a
shape that conveys lightness and flexibility.
This is because, working with the
international architecture firm Snhetta, and
composite materials specialists Kreysler &
Associates, Arup developed the faade using
glass fibre-reinforced plastic (GFRP) panels 2.
affixed to a curtain wall system. These panels,
which are lighter than precast concrete, glass
fibre-reinforced concrete (GFRC) or stone, Studies conducted during the early stages of 1. The faade of SFMOMA is embedded
enabled a sculpturally complex approach. the project assessed the suitability of various with light-reflecting silicate crystals.
And the bow-shaped eastern faade materials to achieve the free-formed panels 2. Streaks of electric light encourage
that would become the ripples of the east passers-by to enter the building, as well
comprises 700 of the uniquely shaped as being part of a strategy to guide the
panels, embedded with silicate crystals, faade. The geometry of the wall did not flow of visitors around SFMOMA.
hence the stone-like appearance. allow for any repetition, and with this in
mind the design team recommended the use
With budget consideration a major driver of GFRP as an alternative to GFRC.
throughout the project, material and system
selection was critical to success. The design The lay-up process of GFRP provided
teams challenge was to find an effective, flexibility in the geometry and allowed the
elegant, yet cost-effective solution that moulds to be easily fabricated out of
would create the desired complex geometry styrofoam. Sand mixed into the gel coat
in combination with large floor-to-floor helped achieve the architectural aesthetic of
spans at the gallery levels. a cementitious finish, while allowing for a
flexible fabrication process and lightweight
solution. Using GFRP panels, rather than
In all these spaces the coves serve multiple density, less than a quarter of that provided
functions: lighting, acoustic, life safety, and in galleries with similarly soaring ceilings.
mechanical systems are incorporated and
seamlessly integrated within the forms. This innovative energy-saving solution
allowed for reduced circuiting, and was
An important journey through the gallery awarded a LEED point for design
spaces is the city gallery that runs along the innovation. The museums commitment to
north-east end of the building across all LEED was essential to this design idea being
floors. Here, an open stairwell and many successfully employed and adapted.
large picture windows provide views to the
city and the balance of daylight and electric Acoustics and AV
lighting has been finely tuned to meet art The acoustic design for the public areas
conservation requirements, together with a creates comfortable spaces for quiet
level of brightness and contrast which contemplation. Gallery spaces include
naturally guides visitors through the space. sculpted glass fibre-reinforced gypsum
(GFRG) panels that scatter both light and
The design of any gallery space must sound to avoid harsh reflections that may
balance many priorities because exhibitions otherwise detract from a comfortable
10.
are constantly changing. With this in mind, viewing experience. In the high-density
and ceiling heights in the SFMOMA entry area, strategically located sound-
expansion ranging between approximately absorbing finishes control the build-up of 100mm-thick sound-absorbing ceiling
5m and 10m, the lighting allowance for the noise from visitors, helping to keep the panels that reduce reverberance, improving
track is typically designed to provide the ticketing experience calm and comfortable. audio fidelity, especially in the lower/bass
capacity to light any object, in any place. The amount of sound absorption required frequencies
was determined using proprietary acoustic
High ceiling heights require higher-power models based on the architecture and sound-isolating floor, ceilings and walls
lighting to deliver the same quantity of light. anticipated occupancy. designed to contain sound and avoid
Yet the team designed a solution that could disturbing neighbouring spaces
provide maximum flexibility without In the large column-free gallery spaces where low-noise heating, ventilation and air-
requiring excessive power. Their solution, the museum can vary configurations using conditioning (HVAC) systems to improve
which required multidisciplinary temporary walls, it was necessary to address the detail and dynamic range of audio content.
collaboration and a customised programming the issue of sound transmission between
of the relay panels at each floor, was a track adjacent exhibition areas, because some of Outside the building, the acoustic impact of
load limiting solution, monitored floor by the museums exhibits, particularly for media the new expansion on the surrounding urban
floor. Typically, track limiting is done within arts, feature sound and video. It was also environment is minimal. Site noise levels
the gallery space, with a physical device important to create the ideal sound were benchmarked over a 24-hour period
attached to individual runs of track. environment for these exhibits, so the media and whisper-quiet fans for the cooling
Programming the track limiting to be done at arts acoustics, tailored for audio reproduction towers, and attenuation packages for relief
the panel achieves much lower lighting power and sound isolation, include: fans, were specified.
11.
0.02 sec 0.15 sec 0.20 sec 0.23 sec 0.25 sec 0.30 sec 0.38 sec 0.45 sec 0.53 sec 0.60 sec 0.68 sec 0.75 sec
dB
-1
-2
-3
-4
-6
-9
-12
-15
-21
-27
-
-27
-21
-15 0.75 sec
-12
-1
-9
0.15 sec 0.30 sec 0.45 sec 0.60 sec
Time Segment Stretched x2
-6
-4
-3
-2
12.
Acoustic signature
The long stairs connecting the galleries Usual rules of acoustic design suggest
exhibit a natural flutter echo giving each adding sound-absorbing material to
stair a unique acoustic signature, which is neutralise these artifacts, but the team
activated by the sounds made by visitors: decided to retain them to create additional
footsteps and whispers, for example. engagement and tell a story around design
In essence, each sound creates a unique and multi-sensory experience of spaces.
sonic artwork. This acoustic signature can
be specifically activated by artists should
they choose.
The Wattis and White Box Theatres acoustic bleed that may contain art with The expansion project features what is
The Wattis Theatre at SFMOMA, the particular conservation needs. This space believed to be the largest architectural GFRP
well-known cinema within the original Botta fosters works that call for continuous action faade application in the USA. Architecture
building, was completely renovated as part over long periods of time, or live pieces and engineering were carefully coordinated,
of the expansion project. The Arup-led rooted in intimate audience-performer options explored, and appropriate materials
design includes architecturally integrated exchange and group dynamics. selected to inform the development of the
acoustic features that both recreate the GFRP panels. By leveraging modern
acoustics of the original theatre, and support Arup collaborated with Snhetta on the materials, the team delivered a faade that
an active architecture system that can initial design of the room to integrate the has all the elegance of a natural material,
electronically alter the acoustics of the room theatrical, acoustics and lighting design such as stone, yet offers significant further
for different performance types. The ability needs, part of the White Box fit-out with benefits, particularly in terms of
to vary room acoustics at the push of a architect EHDD. The fixed technical grid, sustainability and cost-effectiveness.
button enables the museum to present a wide control room, and audio-visual and theatrical
range of events. infrastructure designed by Arup, support a Lighting, acoustics, audio-visual and theatre
wide variety of performances, installations, planning strategies that maximise flexibility
The White Box Theatre is an entirely new board meetings and rotating artworks. and minimise power use are also seamlessly
space for live performance, accommodating integrated into the architecture, and the
theatre-in-the-round configurations, multi- Summary MassMotion analysis provides SFMOMA
screen projections and special installations. SFMOMAs distinctive and, in this case, with insight into how the museum will
It means that for the first time SFMOMA has it is probably fair to say, iconic new manage visitor footfall up to 20 years into
the full range of flexibility and infrastructure expansion is innovative not only in its the future. The expansion of SFMOMA will
necessary for performance-based work, appearance but also in the design and undoubtedly influence similar projects, its
allowing artists to explore movement and engineering that underpin the effectiveness outcome having set new benchmarks in
film in new ways. The design of this space of its galleries and performance spaces. several aspects of museum design.
provides support for performances that are Arup worked consultatively across the entire
suited neither to the separation of a project, providing specific expertise in
proscenium stage, nor to a gallery with particular disciplines.
Project credits
Client: SFMOMA Architects: Snhetta, international
architecture firm based in New York, Oslo and San
Francisco, and EHDD Faade: Kreysler & Associates
and Arup Arups New York team supporting Snhetta
was led by Denis Blount and Raj Patel. Arups San
Francisco team supporting EHDD was led by Joshua
Cushner and Fiona Gillan. Arup Sammy Aglipay,
Denis Blount, Joe Chapman, Karine Charlebois,
Clarissa Cruz, Joshua Cushner, Star Davis, Fiona
Gillan, Clara Hie, Stephanie Hillegas, Carla Jaynes,
Jerrod Kennard, Christine Lee, Rok Lee, Trent Lethco,
Toby Lewis, Jack Lim, Matt Mahon, Shane Myrbeck, Lj
Nassivera, Raj Patel, Eric Rivers, Jacinda Ross, Cesar
Sanchez, Markus Schulte, Ricky Shum, Brian Stacy,
Nathan Stroud, Leonie van Ginkel, Felix Weber,
Robert Young.
Image credits
1 Iwan Baan; 2, 3, 9, 10, 13, 14 Snhetta/Jeff Goldberg/
Esto; 4 Felix Weber; 5, 6 Kreysler & Associates;
7, 8, 11, 12 Arup.
14.
Introduction This article focuses largely on the role of design engineering, this project began back
Hong Kong International Airport (HKIA) is BIM in developing the MFC. in 2010 when BIM usage was less well-
one of the worlds busiest, connected to established. The advantages of BIM became
more than 190 destinations through more The project evident as the project progressed, resulting
than 1,000 daily flights. To meet future The new five-level MFC with a total floor in better coordination between disciplines
demand and strengthen Hong Kongs area of 105,000m features an architectural and earlier identification of clashes, or
competitiveness as a regional and style that complements Terminal 1. Its large, design issues that required rectification.
international aviation hub, further expansion open-span steel truss roof, high headroom
was necessary. The Airport Authority Hong and extensive use of glass create a sense The JV, in conjunction with architect Aedas
Kong (AAHK) tendered the detailed design of light and space. Passenger access to and sub-consultant Atkins, deployed
of Phase 1 of its Midfield Development Terminal 1 is via an extension of the existing multiple software platforms to deliver the
project in 2010, a project that was completed automated people mover (APM) system. optimum solution. A variety of 3D design
in December 2015. software was used; for example, Autodesk
The MFC adds 19 contact aircraft parking Navisworks as a common platform for
Located to the west of Terminal 1, between stands, two of which can accommodate showing and assessing information in 3D
the two runways, the midfield was the last Code F aircraft, such as the Airbus A380, and helping to advance the complex 3D
piece of land on the airport island available significantly expanding the airports capacity geometry design of the curved roof of the
for large-scale development. A core part of enabling it to serve in excess of 10 million concourse.
this expansion comprised the design and additional passengers per year.
construction of the Midfield Concourse In addition, a robust BIM workflow was
(MFC). Arup, in joint venture with Mott Within the detail design JV, Arups scope defined, describing how the various software
MacDonald, was selected to provide full included structure, faade, sustainability, from Bentley, Autodesk and others would be
multidisciplinary design and construction airport systems, APM, baggage handling used, exchanged and integrated, and where
support. system, MEP (mechanical and electrical conversions to other formats would be
engineering and plumbing), fire, acoustics, required. The software integration enhanced
Building Information Modelling (BIM) was specialist lighting and logistics planning. project-wide collaboration allowing rapid
an important key to the success of this information exchange and helping to
project and the way BIM was used resulted BIM overview significantly improve inter-disciplinary
in awards from both Autodesk and Bentley, The MFC was one of the AAHKs first major coordination, resolving clashes and other
key providers of software to architecture, BIM projects. Although BIM is increasingly issues well in advance of construction.
engineering and construction professionals. regarded as a standard facet of integrated
Architect
input (Rhino)
Geometry Structural
centrelines model (GSA)
Update to
Design
architect model
optimisation
base on optimised
structural design
Analysis
Analysis
results
4. 5.
7. 8.
The design team recommended orientation and lifts; and on-demand walkways that
along the north-south axis to avoid large reduce energy consumption when not in use. System
solar gain from the south and used LED lighting with ultra-low energy
parametric optimisation analysis to develop consumption, coupled with daylight and Seawater Potable Condensate Rainwater
the distinctive shape of the building. Glazing occupancy sensors. Arups lighting team
(from T1) water water
the west faade was minimised to reduce Materials that were regionally sourced
heat gain, and it was covered by an overhang (within 800km of the site), recycled, or
with shading devices. On both faades, renewable wherever possible. More than Black Grey
high-performance glazing was used to reflect 20% of materials came largely from South water water
more than 40% of solar heat. In the roof, China, Taiwan and Hong Kong. More than
north-facing skylights bring in diffuse 50% of the timber used came from 9.
natural light to reduce the need for artificial renewable sources certified by the Forest
lighting during the day. Stewardship Council. More than 60% of
the construction waste was recycled.
Active and renewable design measures Furthermore, MFC was designed for
adopted to reduce energy consumption flexibility so that the space could be
include: adapted and changed in the future, if
required, with minimal structural works and
Water-cooled air conditioning with re-strengthening.
high-efficiency chillers: the cooled air, Grey water from restrooms and kitchens, 4. Structural BIM model with roof geometry.
provided to the MFC via binnacles, sinks as well as rainwater and condensate water,
from the top of the binnacles to form a 5. Parametric structure model.
collected, treated, and used as makeup 6. Concept of Skylight, with its eyelid-shaped
blanket above the floor, enabling efficient water for the cooling towers. Other cover.
local cooling for occupied areas rather than measures include low-water consumption
the entire space. 7. Location of the Midfield Concourse at HKIA.
fittings and sensors for taps. 8. Ultra-low energy LED lighting, coupled with
More than 1,200m of integrated daylight and occupancy sensors, illuminate the
photovoltaic panels on the skylight MFC won the Grand Award in New MFC: the super low-glare optics were developed
structure. Buildings Completed Projects category in specifically for this project.
Hong Kongs Green Building Awards, 2016. 9. A comprehensive strategy to minimise water use.
Fixed ground power for parked aircraft to
reduce reliance on auxiliary power units;
regenerative power from the APM system
Project credits Ricky Li, Sasa Li, Vivian Li, Rick Liu, Shirley Liu, Andy 10. Hong Kongs first communications-
Client: Airport Authority, Hong Kong (AAHK) Detail Lo, Franky Lo, Ivan Lo, Norman Lo, Mingchun Luo, based train control (CBTC) overlay project
design consultant: Arup and Mott MacDonald; Ross Lyons, Carlos Ma, Phillip Ma, Raymond Ma, uses data to control speed on the APM and
Arup Pavlina Akritas, Ming Au-yeung, Jeng Ang, Michele Mak, Andrew Mole, James Musgrave, Derek thus increase capacity.
Francesco Anselmo, Raymond Au, Gerry Banks, Raquel Ng, Kenneth Ng, Nick Ng, Simon Ng, Trevor Ng, 11, 12. For the extension of the upgraded
Brito Dias, Stuart Bull, Noah Burwell, Vicente Cabrera, William Ng, Ryan Ngai, Vincent Ngai, Jessica APM, new trains were specified.
Mark Cameron, Anne Carnall, Alice Chan, Alvin Chan, Pawlowski, Ray Pang, Simon Pearce, Simon Pickard,
Che-cheong Chan, Henry Chan, Isaac Chan, Jimmy Cynthia Poon, Mark Richardson, Thomas Richardson, 13. BIM was used to verify the route of a
Chan, Karissa Chan, Li-san Chan, Man-him Chan, Renee Ren, Jonathan Roberts, Kin-pui Shum, new strategy for airport systems cable
Raymond Chan, Roy Chan, Simon Chan, Spencer Chan, Christopher Simon, Dicky Siu, Ho-kwan So, Mark containment: the cable support system was
Jason Chen, Harold Cheng, Ping-mun Cheng, Durand Stapley, Mary Sung, Mark Swift, Fiona Sykes, Osward relocated to make way for the new APM
Cheung, Eric Cheung, Evelyn Cheung, Vincent Chiu, Tang, Ian Taylor, Chris Tidball, Alex To, Nicholas To, platform.
Michael Chow, Carrie Chu, Celsius Chung, Clement Michael Tomordy, Peter Thompson, Jimmy Tong, 14. The new APM platform.
Chung, Ricky Chung, Andrew Cowell, Jim Daly, Man-him Tong, Sherine Tsang, Vincent Tse, Mark
Mohammed Danish, Bernard Dason, Reynaldo De Turner, Tony Vidago, Aura Wang, Johannes Wirtz,
Guzman, Daniel Duan, Matt Ellis, Anthony Fan, Daniel Wong, Dicky Wong, Edwin Wong, Emily Wong,
Chauncey Fan, Pengcheng Feng, Raymond Fok, Hilton Wong, Jacky Wong, Jonathan Wong, Ken Wong,
Siu-man Fong, Ronald Fung, Charlie Green, Patrick Raymond Wong, Sai-kee Wong, Steve Wong, William
Hanggi, Mark Hayman, Kenneth Ho, Lawrence Ho, Wong, Zoe Wong, Patrick Wu, Glen Xie, Dong-lei Xu,
Wing Ho, Kenneth Hon, Marco Huang, Henry Hui, John Jimmy Yam, Keji Yao, Raymond Yau, Tak-cheong Yau,
Hui, Emily Hung, Lewis Hwoi, Jeff Ip, Grammy Jiang, Shelley Ye, Anna Yeung, David Yeung, Ronald Yeung,
Soo Jin, Gigi Kam, Ming-chan Kang, David Keast, Rumin Yin, Bernadette Yip, Charmaine Yip, Grace Yip,
Ricky Kwan, Chris Kwok, Patsy Kwok, Karen Lai, Otto Jess Yip, Kevin Yip, Kim Yong, David Yu, Yuki Yu, Jessy
Lai, Florence Lam, Jack Lam, Joe Lam, Larry Lam, Zhang, Jian-xin Zhang, Li-ping Zheng.
Mai-yin Lam, Penny Lam, Andy Lau, Carol Lau, David
Lau, Hilary Lau, Tony Lau, Joey Law, Angus Lee, Image credits
Frieda Lee, Jason Lee, John Lee, Kam-tim Lee, Manson 1, 11 KerunIP / AAHK; 2, 3, 4 AAHK; 5 Arup / Martin
Lee, Siu-yuen Lee, Benny Leung, Gary Leung, Gavin Hall; 6 MAJV / Arup / Martin Hall; 7, 8, 14 Marcel
Leung, Patrick Leung, Wai-ho Leung, Joyce Li, Lam; 9, 10, 12, 13 Arup.
Authors
Paul Johnson Colin Stewart
Introduction consultation, were a prerequisite to preparing then Minister for Transport. It was at this
Construction of HS2, Phase1, is now what was the largest and most complex hybrid point that Arup was engaged to undertake
underway after the High Speed Rail (London Bill ever presented to Parliament. The resulting the initial studies for a new line, the
West Midlands) Bill gained Royal Assent legislation permits construction of Phase 1, locations it might serve, and the routes that
in February and the main works civil the London to Birmingham stretch, of a line could be followed.
engineering contracts were awarded in July. that will be extended further north, to Leeds
It will be Britains second high-speed rail and Manchester, in Phase 2. Developing HS1
line providing a new transport backbone Arups appointments to HS2 contracts,
for the country with the potential to The seeds of HS2 were sown in 2001, when particularly in the early feasibility phase,
regenerate cities and provide new Arup undertook a study for the Government are largely due to its pivotal role in route
opportunities for communities. By delivering into the potential for a high-speed link from selection for the CTRL. Dubbed the Arup
extra rail capacity and connectivity, it will London to the north. This was in the years route, this high-speed link from London to
ease congestion on the existing network and after Arup developed the route for HS1, the mainland Europe, first mooted in the late
unlock opportunities for economic growth. Channel Tunnel Rail Link (CTRL), which 1980s, also provided high-speed local
opened in 2007. However, it was not until commuter services and opened up
Extensive planning, design, and environmental 2009 that High Speed Two (HS2) Ltd was brownfield sites for homes and commercial
studies, which informed both the route formed as a result of a review of the UK rail property, thus creating jobs and associated
selection and wide-ranging stakeholder network instigated by Lord Adonis, who was economic growth. Derelict land in areas
Nottingham
Derby
Why a hybrid Bill?
M1
Major infrastructure projects of
strategic national importance fall
Lichfield M42 outside the UKs standard planning
Tamworth
procedures and require their own Act
of Parliament, attained via the Bill
Nuneaton
HS2 line process.
Bedworth
Existing rail
Birmingham Coventry
M6 Motorway Public Bills (the most usual) change
M42 Kenilworth the law as it applies to the general
Warwick population.
W
es
tC
oa
Private Bills change the law as it
M5 st
M
ain applies to specific individuals or
Banbury
Li
ne organisations.
M1
Milton Keynes
Ch
ilte Hybrid Bills are for legislation that
affects both public and private
rn
Ra
ilw Luton
ay
s Aylesbury interests. A hybrid Bill was the
mechanism the Government chose
M40
to obtain planning permission and
M25
acquire the land to construct HS2.
High Wycombe
Marylebone
Euston Subsequent phases of HS2 will
M4 London
require separate legislation.
2.
Bedworth
M6
Coventry
Kenilworth
Warwick
M40
Royal Leamington Spa
4. 5.
Phase 1 route feasibility: 20092011 high-speed line to follow, and furthermore, also, and this assessment was done in
Key outputs at this stage were to identify the route around High Wycombe had been parallel with the route studies, the key
feasible combinations of speed, journey developed up to the motorway boundary. finding being that the large footprint required
time, engineering complexity, environmental Whichever route was adopted would for 400m-long trains made few choices
impact and cost, in order to make the essentially require the crossing of the immediately apparent.
business case for a track optimised for Chiltern Hills, an Area of Outstanding
speeds of up to 360kph, with an alignment Natural Beauty. Further north on approach to Nevertheless, by mid-2010, Arup had
future-proofed for up to 400kph. Previous Birmingham, the three major conurbations gathered enough data to draw geometrically
studies had drawn only highly indicative of Stratford-upon-Avon, Warwick and correct route and station options, then create
lines on very small-scale plans, with broad Coventry straddle the various corridors. a node-link diagram to allow a process of
arrowheads pointing to desired destinations. Coupled with this were the hundreds of paired comparisons against the major
During the feasibility process, genuine environmental constraints which were comparison headings. This process led to
400kph alignments were drawn to determine illustrated on a measles map showing how three major routing choices:
whether previously suggested concepts could hard it would be to thread the route though
be designed and engineered. Operating up to and minimise the impact. More than 70 route Route 2: along the M40 corridor
18 trains per hour at speeds up to 400kph has options and segments were considered. Route 3: a central route through
yet to be achieved anywhere in the world, Buckinghamshire, Oxfordshire and
yet infrastructure proposals made in the Furthermore, studies were undertaken to see Warwickshire, to a triangular junction
feasibility study had to meet this challenge. how a 300kph solution would differ from a east of Birmingham, then into central
400kph route and how viable that might be. Birmingham, and out northwards through
The brief from HS2 Ltd specified that The outcome showed that in terms of Staffordshire, to join the West Coast Main
options following transport corridors, which weaving around environmental and property Line, near Lichfield
were already in developed areas, should be constraints, little could be achieved because
included. This raised many issues. Following such routes only shifted challenges from Route 4: largely parallel to, but not actually
the M1 corridor, which runs north, and then Place A to Place B. In addition, a 300kph adjacent to, the M1.
west along the M45 corridor constrained the route would cost almost as much as a
options for linking to the northern cities of 400kph route to build (approximately 8% These potential routes that either followed
the UK. The alternative M40 corridor had cheaper), insufficient to offset the long-term the line of an existing transport corridor, or
been developed as a gently curving economic disadvantage of a lower-speed were on land that could accommodate long,
alignment, but with curves too tight for a line. Station options had to be considered straight sections of track (such as the now
Public consultation
HS2 Ltd, supported by the design team, the
EOC and the EIAs, consulted with the public
8. in many and varied ways: through
presentations, individual and group meetings,
8. Arup SoundLab was used during multi-party forums, public exhibitions, the
consultations to enable members of the internet, and via online media, for example.
public and government ministers to listen to In all these forms of consultation, the
auralisations of the noise impact of the
railway and the effects of mitigation. visualisations and sound demonstrations
9. An animated aerial visualisation was
developed by Arup using its 3D visualisation
produced for public consultation and to techniques, and SoundLab technology,
assist the Select Committee in their proved an immensely valuable asset.
deliberations. This image is a typical
snapshot of the route: near the small village Using SoundLab it was possible to generate
of Quainton, Buckinghamshire, it shows
mitigation including balancing ponds which verified demonstrations of how HS2 might
are used to collect surface water prior to sound at various locations along the route,
controlled discharge to local watercourses. then present this to local stakeholders
neutrally, to allow them to make up their own
minds about the impact. As part of this
process, SoundLab was used to demonstrate
the effect of noise reduction measures: more
than 75% of the surface sections of HS2 have
Access road
Balancing ponds
Engineering earthworks Overbridge Landscape mitigation planting
9.
10. 11.
Design and engineering Euston Station and regeneration become a 21st century terminus that creates
Developing the route options and Euston is currently the fifth-busiest rail value in the immediate environs and gives
preliminary design demanded innovative terminus in London serving the West Coast rise to regeneration opportunities. Arup
technical analyses and detailed planning. Of Mainline to the north of England and influenced, guided and advised on the design
particular note are the following topics, each Scotland, and regional services north of of the station, and the plan for the
of which is discussed further in the London. With extensive connections to surrounding area. This meant leading a
remainder of this article: London Underground, the second-largest bus multidisciplinary team of specialist
station in London, and plans for a station for engineers, architects, planners and
Euston Station: designing a high-speed Crossrail 2 running east to west across the consultants and working closely with HS2
station to operate within a busy city, it has the potential to provide the Ltd to foster a collaborative environment
conventional rail station connectivity needed for the new HS2 with other partners on the project. The
Aerodynamic assessment of tunnels London terminus. outcome is a plan for the staged delivery of
Euston to match the joint service level
At station approaches, designing state-of- The design and construction challenge requirements of both HS2 and the existing
the-art acceleration/deceleration tracks to relates to the tight urban fabric surrounding conventional railway.
enable trains to leave and join the HS2 line the station. Redevelopment will require
Managing the Rayleigh wave phenomenon acquisition of adjacent properties and The projected increase in the number of
significant work, above and below ground, trains and passengers to be accommodated
Curzon Street Station: parametric to connect it into the existing transport through Phases 1 and 2 is significant and
modelling for the proposed roof network to create an integrated multi-modal delivery has been planned accordingly
Washwood Heath: selecting the site for the transport interchange for trains, buses, taxis, (see image 11):
rolling stock maintenance depot cycles and pedestrians, with links to the busy
nearby Kings Cross and St Pancras Stations The initial Stage A station will be constructed
Future-proofing: a plan for developing the complex. alongside the existing station and scheduled
links to Phase 2. to open for service in December 2026, as
How 4D models benefited the Employers The vision that Arup, with Grimshaw and part of HS2 Phase 1, with six platforms.
Requirements Design process HS2 Ltd, worked to develop is that it must
Station X
12.
13. 14.
The Stage B1 station will be constructed High speed also means that sonic booms for running such a service and an innovative
within the curtilage of the existing station arising from pressure waves inside the approach was required. Arup developed
(platforms 1418) taking advantage of the tunnels can be emitted from the tunnel models to examine what could be done.
reduction in conventional services resulting portals. These can be prevented by providing
from migration of services and passengers a perforated entrance region (porous portal) At a speed of 400kph, and with trains
to HS2. This will open in December 2033 to limit the build-up of pressure when the following each other at three-minute
as part of Phase 2. train enters the tunnel. As the entry speed intervals, there is a physical gap of 20km
will be so high, HS2 tunnels will require between trains. So it is critical that the
The completion of Euston with renewal of
exceptionally effective porous portals which infrastructure design enables stopping trains
the existing station (13 platforms) will
will be delivered through a novel tapered to decelerate enough to leave the main line,
follow as Stage B2 (outside the Phase 2
design developed by Arup in collaboration and accelerate enough to join later in a
Act works).
with Professor Alan Vardy of the University subsequent gap, without disruption to flow.
of Dundee. The design has been validated The scenario is shown in image 13, where
Aerodynamic assessment of tunnels
and optimised through 1:25 scale model Train 1, which needs to stop, can begin to
Trains will run through tunnels on HS2
testing, leading to definition of the portal slow down on the main line until the
at higher speeds than anywhere else in the
length and geometry for the project. headway reduces to two minutes, the
world. This will mean unprecedented
minimum possible without impeding the
challenges relating to air pressures in the
Station approaches progress of the non-stopping Train 2. By
tunnels, sudden changes of which may
The number of stations on a high-speed rail point X, Train 1 is still travelling at 230kph,
cause discomfort or injury to passengers.
route affects both the running speed and but it now has to move out of the way of
Using specialised aerodynamic analysis
capacity. In order to maximise both, trains Train 2, and a set of points capable of
software, Arup quantified the trade-offs
that need to call at an intermediate station operating at 230kph is needed. Train 1 then
between increasing tunnel sizes (leading to
must do so without impeding the passage of needs a further 2.02.5km to stop, so its
higher construction cost), versus specifying
non-stopping trains running at full speed. deceleration lane is quite lengthy. The same
rolling stock with greater pressure-tightness
The HS2 design speed of 400kph is the first in principle applies to trains departing from the
(which can limit choice of suppliers and/or
the world, so there was no existing blueprint station as they accelerate to full speed.
increase cost).
to increase confidence in all aspects of the Authors Bennett, Nicholas Berg, Harry Betts, Olly Bewes, Megha
planning, design and construction of the Paul Johnson, Arup Fellow, was Arup Global Bhavsar, Ian Biddlecombe, Rachel Birrell, Alys Black,
Environmental Leader and Head of Environment for Kim Blackmore, Robert Blair, Sue Blanch, Max Blatiak,
works, in order to inform the Invitation to Rail Link Engineering on HS1, and Project Director of Rosalind Blewitt, Jessica Boath, Simon Bone, John
Tender (ITT) documents for the main civil the EOC on HS2 Phase 1. Border, John Bourke, Paul Bourke, Emily Bowden-Eyre,
works, Early Contractor Involvement (ECI) Colin Stewart is Global Rail Leader. He was the initial Daniel Boyce, Alistair Boyce, Richard Boyd, Ian
contracts, and the next stage of design Technical Director for HS1, and has led all Arup HS2 Braithwaite, Ross Bramley, Hal Bransby, Grainne
Breen, Simon Brimble, Sam Brizzell, Dave Brogan, Luke
procurement for the stations. The ERD also work from 2009 to 2017.
Brotherton, Claire Brown, Richard Brown, Tansin
furthered the process of mitigating effects on Brown, Carol Brownridge, Chris Bruce, Alex Bryson,
Project credits
the environment. Arup developed 4D models Client: High Speed 2 (HS2) Ltd Project owner: Justin Buchanan, Cem Budak, Michael Bull, Chris
to help HS2 Ltd better understand the Department for Transport, UK Partners: AECOM, Burgess, Jody Burley, Lindsay Burt, Diane Burt,
construction sequence and therefore better Grimshaw, Wilkinson Eyre, Costain, Corderoy Route Jonathan Burton, Ian Burwood, Stephen Bussell, Mark
location and alignment, transport planning, Buttimer, Mike Byrne, Yan Cai, Alison Caldwell, Simon
explain it to stakeholders. In some instances Camm, Rory Canavan, Jamie Cardoso, Matt Carlson,
requirements management, bridges, tunnels,
this helped to remove or lessen objections to geotechnical engineering and earthworks strategy, rail Jenny Carrington, Stephen Carter, Phil Carter, Ross
the scheme. engineering and systems, highway design, flood and Carter, Seb Cartmell, Mersade Cartwright, Luke Casey,
drainage, cost management, station planning and design, Roberto Castagnari, Sarah Cauldwell, Ringo Chan,
Summary architecture, landscape design, acoustics, aerodynamics, Drew Chapman, Deirdre Chapman, Tim Chapman,
operational planning, construction planning, risk Steph Chapman, Steve Chapple, Odetta Charles, Wayne
Developing the design, environmental Charles, Riz Chattha, Vululami Chauke, Danielle Chen,
management, GIS, visualisation, stakeholder
assessment, and mitigation measures and engagement and consultation, environmental impact and Alex Chen, Man-Yiu Cheuk, Noble Chigwedere, Annie
preparing the Bill submission have assessment: Arup Musa Abbass, Muhammad Choi, Paul Clark, Andrew Clarke, Chris Clarke, Phill
undoubtedly enhanced and extended learning Abdullah, Melody Ablola, Roman Acha Valls, Obie Clay, Harry Clements, Tom Clifford, Scott Clyne, Brian
Achigbu, George Acuna, Lisette Adams, Paul Adams, Coles, Adrian Collings, Jaki Collison, Mike Colman,
from HS1. It has clearly strengthened David Connolly, Steven Cook, Danny Cooley, Antony
Jenny Adams, Ekpes Akpanudoh, Thomas Aldridge,
knowledge and understanding of how to Steve Allen, Eloise Allsop, Mohammed Al-Sharif, Cooper, Jackie Corbett, Tom Corke, Nathalie
develop high-speed rail links in settings that Richard Ames, Daniel Amir Siassipour, Lucy Anderson, Cornilleau, Riccardo Corti, Noel Cotter, Jeremie
are new to the concept. Sachin Anshuman, Matt Antrobus, Fernando Aparicio Coullon, Tian Coulsting, Peter Court, Ben Cox, Tim
Banere, Tom Armour, Andrew Armstrong, Mike Ashford, Cresswell, Kevin Cressy, Mike Crick, Jamie Crispin,
Linn Aspinall, Ben Aston, Oliver Atack, Clive Aubrey, Livvy Cropper, Paul Cruise, Wilma Cruz, Sebastian
Arup is proud to have been a key part of this Cumpatescu, George Cusworth, Artur Czarnecki, Harry
Mark Ayers, Chris Ayerst, Chris Baines, Bob Baker,
project so far, and looks forward to the Chris Baker, Ian Bakewell, Andrew Bamforth, Jorge Dade, Paola Dalla Valle, David Dallison, Edgars
construction and opening of HS2 as a Barbeito, Paul Barlow, Alison Barmas, Daniel Barnes, Damlics, Rob Davies, Paul Davies, Helen Davis, Ian
user-friendly and visionary transport system Oliver Barnett, Mat Barnett, Imelda Barry, Bonnie Davis, Matthew Davis, Reem Dawood, Ken Day,
Richard De Cani, Milagros De La Cruz Gonz, Brian De
that, as a result of its speed, will change how Bartlett, Souman Barua, Marynet Bassily, Adriani
Mello, Vinicius De Siqueira, Alan Dean, Balduino Del
people choose to travel and where they live Bastouni, Alan Beadle, Faye Beaman, Joseph Bearne,
Anne Bearne, Claire Beedle, Chris Bellingham, Principe, John Dell, Mike Devriendt, Kiran Dharni,
and work. Jonathan Ben-Ami, Rosie Bendix, Lee Bennett, Stephen Jessica Dias, Simon Dicken, Paul Dickens, Tim Dixon,
1 2 3
4 5 6
7 8 9
1 Hong Kong Midfield Concourse: Kerun Ip /AAHK; 2 Second Avenue Subway, New York: Arup; 3 Sacred Heart Cathedral, Kericho, Kenya: Arup; 4 Second
Avenue Subway, New York: Ari Burling; 5 Ecological surveying for HS2: Arup; 6 San Francisco Museum of Modern Art: Jeff Goldberg; 7 National Forum of
Music, Wrocaw, Poland: Lucasz Rajchert; 8 Sacred Heart Cathedral, Kericho, Kenya: Edmund Sumner; 9 Hong Kong Midfield Concourse: Kerun Ip /AAHK.
Published by Arup,
13 Fitzroy Street,
London W1T 4BQ, UK.
Issue 1 2017
www.arup.com