Professional Documents
Culture Documents
Continous Quality Control
Continous Quality Control
2005-07
Final Report
Continuous Compaction
Control MnROAD
Demonstration
Technical Report Documentation Page
1. Report No. 2. 3. Recipients Accession No.
MN/RC 2005-07
4. Title and Subtitle 5. Report Date
March 2005
CONTINUOUS COMPACTION 6.
CONTROL MnROAD DEMONSTRATION
7. Author(s) 8. Performing Organization Report No.
D. Lee Petersen
http://www.lrrb.org/PDF/200507.pdf
In September 2004, engineers conducted a Continuous Compaction Control (CCC) demonstration at MnROAD, an
outdoor pavement test facility. Continuous Compaction Control (CCC), also called Intelligent Compaction (IC), is a new
technique in the United States construction market that uses an instrumented compactor to measure soil or asphalt
compaction in real time and adjusts compactive effort accordingly to control the level of compaction. This demonstration
used the BOMAG Compactor and focused on Youngs soil modulus as the soil parameter of interest.
CCC may potentially provide substantial benefits, including improved quality due to more uniform compaction, reduced
compaction costs because effort is applied only where necessary, reduced life-cycle cost due to longer pavement life, and a
stronger relationship between design and construction. State departments of transportation have expressed interest in
exploring this method as a way of meeting quality-assurance requirements within a tight budget environment.
In general, this study found CCC to be an effective quality-control mechanism for soil compaction. However, further
questions arose as a result of the study and certain variables affected the results and measurements, including moisture
content and the use of different measurement tools. Further research is needed to determine the level of uniformity in using
CCC and the extent of reliability in achieving target values when using this method.
Final Report
Prepared by:
D. Lee Petersen
CNA Consulting Engineers
2800 University Avenue, S.E.
Minneapolis, MN 55114
For:
John Siekmeier
Minnesota Department of Transportation
Office of Materials and Road Research
1400 Gervais Avenue Mail Stop 645
Maplewood, MN 55109
March 2005
Published by:
This report represents the results of research conducted by the authors and does not necessarily represent the views
or policies of the Minnesota Department of Transportation. This report does not contain a standard or specified
technique.
The authors and the Minnesota Department of Transportation do not endorse products or manufacturers. Trade or
manufacturers names appear herein solely because they are considered essential to this report.
Continuous Compaction
Control MnROAD
Demonstration
Prepared for:
Minnesota Department of Transportation
and the
Federal Highway Administration
Prepared by:
List of Figures
All Figures are located after Section 5 and the References.
Figure 1Demonstration Test Location at the MnROAD Site
Figure 2Test Section Prior to Excavation
Figure 3Partially Excavated Test Section
Figure 4Four Soils Used in the Demonstration
Figure 5Concept of Stiffness and Modulus Determination from a Compactor Drum Vibration
Figure 6BOMAG Compactor Used in the Demonstration
Figure 7Schematic of BOMAG Variocontrol Technology for Continuous Compaction Control
Figure 8Possible Sequence of Collecting Surface-Covering Compaction Documentation
Figure 9Photos of Companion Testing Devices
Figure 10Typical Plate Load Test Load-Deflection Data
Figure 11Demonstration Site Cross Section
Figure 12Demonstration Site Plan View
Figure 13Example of Surface-Covering Compaction Documentation
Figure 14Example of Exported Data From BCMWin, with Companion Test Points Highlighted
Figure 15Demonstration Site Isometric View
Figure 16DCP Modulus for All Tests
Figure 17DCP Modulus Values as a Function of Depth Limit
Figure 18Companion Density Tests
Figure 19Plate Load Test Values for All Reload Cycles
Figure 20Distribution of Youngs Modulus for Four Principal Test Methods
Figure 21Distribution of Youngs Modulus for Four Principal Test Methods (lognormal distribution)
Figure 22Comparisons Between the BOMAG Data and Other Methods
Figure 23GeoGauge Test Comparison
Figure 24DCP Test Comparison
Figure 25Load-Displacement Data for Plate Load Test, Location 22a
Figure 26Stress Dependency of Modulus Measurements, Location 22
Figure 27Stress Dependency of Modulus Measurements, Location 23
Figure 28Comparison of Optimum to As-Compacted Moisture Content
Figure 29Percent Compaction by Location
Figure 30Comparison of In-Place to Optimum Moisture Content
Figure 31As-Built Section with Selected Modulus Data
Some of the factors upon which soil modulus depends, and which are pertinent for this demonstration,
are:
1. Soil moisture content
2. Soil stress level
3. Stress history
4. Soil age
These dependencies mean that a soil modulus value measured by one method with characteristic size,
stress level and depth of measurement may be different than the value measured by another method.
Refer to Sections 3.9.4 through 3.9.6 for an assessment of these dependencies for this demonstration
project.
(See www.mrr.dot.state.mn.us/research/MnROAD_Project/MnROADProject.asp)
The demonstration site at MnROAD was on the low volume road test loop, adjacent to test section 53,
as illustrated in Figure 1. The test section was available for the CCC demonstration due to a planned
reconstruction after a culvert pipe test, shown in Figure 2. Approximately 200 feet of the test loop was
excavated about 7 or 8 feet deep and 25 feet wide, shown in Figure 3.
2.1.2 Materials
Four soils, shown in Figure 4, were used to construct the foundation of the road. A Mn/DOT classified
loamy sand (Proctors 1 and 3), which was cut from the excavation and stockpiled onsite, was used for
the lower fill material. Pockets of SP sand (Proctor 2) were sparsely scattered throughout the onsite
material. Three inch minus railroad ballast (no Proctor) was used on top of this in an attempt to stiffen
the fill. More loamy sand (Proctor 4) was brought in from offsite and placed over the railroad ballast.
Then crushed granite (Proctor 5) was used for the aggregate base. The crushed granite met Mn/DOT
class 6 gradation requirements. Material description is as follows:
Figure 16 illustrates the variation in soil modulus, computed using the DCP, as a function of soil type
and depth. Like most DCP data from stress dependent unbound materials, the results from this
demonstration show strength increase with depth. Modulus values at 1 foot below surface are typically
two to four times the values from the first, near-surface blow. The data seems to naturally divide into
three groups: below, between and above two heavy lines shown in Figure 16. Below the lower line,
3.5 GeoGauge
Two, 3 or 4 Geogauge measurements were taken at each companion test location. The number of
GeoGauge measurements depended upon the repeatability of the data. Additional measurements were
taken if initial readings were variable. Table 6 summarizes the individual and average test results.
Statistical summaries of the GeoGauge data, and comparisons with other companion tests, are in
Section 3.9 Comparisons and Correlations.
Table 6Summary of GeoGauge Modulus Data
Location E Geo 1 E Geo 2 E Geo 3 E Geo 4 E Geo Avg
(Mpa)
1 79 82 - - 81
2 62 63 - - 62
3 83 76 79 - 79
4 19 30 31 - 30
5 49 40 48 50 49
6 72 69 72 - 71
7 37 38 - - 38
8 50 51 - - 50
9 45 47 47 - 46
10 54 59 60 - 58
11 90 90 - - 90
12 120 121 - - 120
13 101 102 - - 102
14 89 77 87 - 84
15 103 111 118 - 111
16 98 101 100 - 100
17 69 69 - - 69
18 43 44 - - 43
19 59 60 60 - 60
20 51 49 - - 50
21 55 48 52 - 52
22 45 45 - - 45
23 50 47 51 - 49
Figure 20 compares the histograms for the four test methods. The plots include the equivalent normal
distribution for comparison with the actual histograms. Although no statistical tests were conducted, a
normal distribution seems to fit the LWD and GeoGauge data fairly well. In contrast, the BOMAG and
DCP data seem to be truncated on the left or low modulus side, and skewed to the right or high
modulus side. Hence, the statistical values listed in Table 11 may not fairly represent the data for the
BOMAG and DCP tests.
Table 12Statistical Measures for the Four Principal Methods (Lognormal Distribution)
Method Average Standard Coefficient of
(MPa) Deviation Variation
(MPa)
BOMAG Compactor 28.3 3.0 11%
LWD 45.4 2.1 5%
GeoGauge 62.9 1.4 2%
DCP (top 6 inches) 33.1 1.9 6%
Table 12 lists the statistical measures for lognormal distributions, and Figure 21 shows the histograms
and lognormal distributions. The lognormal distributions seem to match all data fairly well.
The histograms and statistical measures all indicate that the modulus values from the four methods are
different. The BOMAG data has a wider range and is clustered toward lower values. GeoGauge data
tends to be larger than the other methods, while the LWD and DCP data is intermediate between the
BOMAG and GeoGauge.
3.9.2 Correlations Between BOMAG Data and Companion Tests
Figure 22 illustrates the relationships between BOMAG data and the other tests on a point by point
basis. The upper left graphs shows all data, and the other three are BOMAG vs. LWD, BOMAG vs.
GeoGauge and BOMAG vs. DCP, respectively. The graphs show little correlation between the BOMAG
data and the other test methods. There are several reasons for this result:
1. The depth and stress dependency of soil modulus. Depth and stress dependency is addressed
in Section 3.9.4.
2. The heterogeneity of the soils used precludes correlations. Soil heterogeneity may affect
correlations because the BOMAG senses the properties of a large volume of soil, while the
companion tests are clustered near the surface in a small area in the middle of the drum.
3.9.3 Correlations Between Companion Tests
Correlations between companion tests were also investigated. Figure 23 shows correlations between
the GeoGauge, and BOMAG, LWD and DCP. The correlation coefficients are small, except for the
GeoGauge-DCP plot in the lower right of the figure. In this graph, two outliers (high DCP for GeoGauge
4 Conclusions
4.1 Conclusions Related to the Site, Materials and Procedures
1. The MNROAD facility provides substantial resources that facilitate demonstration projects.
2. Pre-demonstration weather conditions, specifically heavy rainfall, impacted the
demonstration by raising the moisture content of the test soils.
3. The scattered funding sources and limited budget impacted the demonstration in several
ways:
a. The soils came from several sources and were heterogeneous.
b. Soil placement was irregular.
c. The schedule was short and fixed, which did not allow time to reduce the moisture
content.
d. There was no equipment available to work the soil to reduce the moisture content.
4. In order to better achieve the demonstration objectives, the demonstration should have been
conducted with under better conditions. The demonstration was conducted under conditions
near the limit of normal construction practice. No compaction technology performs well
under such conditions.
5. Overall procedures and coordination were excellent, except as noted in the following
section.
5 Recommendations
5.1 Recommendations Specific to the Demonstration
1. Research and implementation activities for continuous compaction control should be
continued
2. Future research and construction projects should initially be done with more uniform soils
and moisture contents
3. Demonstrations on actual trunk highway construction projects should be performed
Figure 4
Identify
Define Identify
Define Locations
Project on Locations
Project for QC/QA
PC on for QC/QA
PC Tests
Tests
Transfer to Conduct
Transfer to
BOMAG Conduct
QC/QA
BOMAG
Compactor QC/QA
Tests
Compactor Tests
Conduct
Conduct&
Compaction Transfer to
Companion &
Compaction Transfer
MnDOT to
Companion
Tests MnDOT
Tests
End
Transfer to
Transfer
PC to
PC
Figure 8
Humboldt Geogauge
Troxler 3430 Nuclear Density Gauge Plate Load Test Equipment Loadman
Figure 9
120
100
Modulus (MPa)
80
60
40
20
0
0 5 10 15 20 25
Track Length (m)
Figure 14
Example of Exported Data From BCMWin, with Companion Test Points Highlighted
90
80
70
60
Modulus (MPa)
50
40
30
20
10
0
3 4 5 6 7
Depth Limit (inches)
Figure 17
140
135
130
125
120
115
110
105
100
100 110 120 130 140 150
Dry Density Determ ined by Sand Cone (pcf)
Figure 18
2.0 2.0
Frequency
Frequency
1.0 1.0
0.0 0.0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
Figure 19
7 7
6 6
5 5
4 4
3 3
2 2
1 1
0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
7 7
6 6
5 5
4 4
3 3
2 2
1 1
0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Figure 20
7 7
6 6
5 5
4 4
3 3
2 2
1 1
0 0
0.001 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0.001 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
7 7
6 6
5 5
4 4
3 3
2 2
1 1
0 0
0.001 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0.001 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Figure 21
Distribution of Youngs Modulus for Four Principal Test Methods (compared to lognormal distribution)
Modulus (MPa)
90 90
80 80
70 70
60 60
50 50
40
40
30
30
20
20
10
10
0
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Evib (MPa)
Evib (MPa)
Modulus (MPa)
90 90
80 80
70 70
60 60
50 50
40 40
30 30
20 20
10 10
0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
Evib (MPa) Evib (MPa)
GeoGauge DCP
Figure 22
y = -0.1008x + 62.774
80 80
R2 = 0.0062
70 70
60 60
y = -0.66x + 90.789
50 50
R2 = 0.1492
40 40
30 30
20 20
10 10
0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
GeoGauge Modulus (MPa) GeoGauge Modulus (MPa)
140 140
130 130
120 120
110 110
100 100
DCP Modulus (MPa)
80 80
70 70
60 60
50 50
40 y = 0.42x + 13.15 40
10 10
0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
Figure 23
80 80
y = 0.1492x + 40.429
70 70
R2 = 0.0074
60 60
50 50
40 40
30 30
20 20
10 10
0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
DCP Modulus (MPa) DCP Modulus (MPa)
150 150
140 140
130 130
y = 0.4279x + 49.41
120 120
R2 = 0.1786
110 110
100 100
90 90
80 80
y = 0.9281x + 33.638
70 70
R2 = 0.3623
60 60
50 50
40 40
30 30
20 20
10 10
0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
DCP Modulus (MPa) DCP Modulus (MPa)
Figure 24
500
400
Load (lb)
300
200
100
0
0 0.005 0.01 0.015 0.02 0.025 0.03 0.035 0.04
Displacement (inches)
Figure 25
250 Compactor
225
200
y = 0.3254x + 36.39
175 6" to 18"
Modulus (MPa)
R2 = 0.795
150
125
100
75
50
25
0
0 100 200 300 400 500 600 700
Stress (kPa)
Figure 26
250 Compactor
225
200
y = 0.4075x + 48.728
6" to 18"
175 R2 = 0.8288
Modulus (MPa)
150
125
100
75
50
25
0
0 100 200 300 400 500 600 700
Stress (kPa)
Figure 27
9
8
7
6
5
4
3
2
1
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Test Num ber
Figure 28
105%
Percent Compaction
100%
95%
90%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Test Num ber
Figure 29
90 90
80 80
70 70
60 60
50 50
40 40
30 30
20 20
10 10
0 0
-10 -5 0 5 10 -10 -5 0 5 10
Diffe re nce in M e as ure d M ois tur e Conte nt from Optim um (%) Diffe re nce in M e as ure d M ois tur e Conte nt from Optim um (%)
140 140
130 130
120 120
110 110
GeoGauge Modulus (MPa)
100 100
Figure 30
17,18,19
Yes
Legend
Date
Lift #
ASTM Soil Type, MnDOT Soil Type, Proctor Number
Lane#
Test Numbers
Paper Record of Bomag Data
Electronic Record of Bomag Data
Note: Shading indicates that soil was placed in the coresponding Lane and Lift
1. RB = Railroad Ballast
2. CL6 = Class 6
Figure A.1
Guide
Figure A.2
Figure A.3
Figure A.4
Figure A.5
Figure A.6
Figure A.7
Figure A.8
Figure A.9
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.1
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.2
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.3
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.4
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.5
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.6
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
`
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.7
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.8
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.9
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.10
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Figure B.17
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381
Modulus (MPa)
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
0 0
1 25
2 51
3 76
4 102
5 127
6 152
Depth (mm)
Depth (in)
7 178
8 203
9 229
10 254
11 279
12 305
13 330
14 356
15 381