ESP Start Up

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

Tanjung Jati B Training

PRECIPITATOR START-UP
OVERVIEW
PRECIPITATOR START-UP

Tanjung Jati B Training


P.T. Central Java Power
Tanjung Jati B Units 1 & 2

2 x 660MW (net)

Boiler Precipitator FGD Absorber


Tanjung Jati B Training
Precipitator
Start-up

The information provided in this training presentation


is for discussion purposes only and is not intended to
be used for equipment operation.

Always refer to the appropriate plant procedures and


the equipment suppliers Operation & Maintenance
Manuals.

Tanjung Jati B Training


Precipitator
Start-up

Check all maintenance access doors

The bolted plate type doors installed on the high


voltage bus system between the transformers and
roof platform are not key interlocked.

A visual check should be made to insure that all of


these doors are in place and properly bolted down
with the danger signs clearly visible.

Tanjung Jati B Training


Precipitator
Start-up

BUS DUCT
BOLTED DOOR

HIGH VOLTAGE
SOURCE

UNIT-1
TRANSFORMER
RECTIFIERS

Tanjung Jati B Training


Precipitator
Start-up

Close and lock all access doors

Follow the sequence established by the Safety Key


Interlock System. All doors should be closed
tightly and locked.

Tanjung Jati B Training


Precipitator
Start-up

Remove all safety grounding devices

If the precipitator has been opened for inspection


or maintenance, grounding cables will need to be
removed.

Using the insulated pole (Hot Stick) remove the


clamp from the high voltage system. Remove the
welding connection from the receptacle mounted
on the casing.

Close and lock the doors.

Tanjung Jati B Training


Precipitator
Start-up

Return T/R Ground Switches to On position

With the interlock keys obtained by locking the


designated grounding doors, turn the T/R set
grounding switches to their normal operating
HV position.

Tanjung Jati B Training


Precipitator Overview
Start-up

GND - GROUND
HV - HIGH VOLTAGE

KEY LOCKS

TRANSFORMER-RECTIFIER
HIGH VOLTAGE SWITCH

Tanjung Jati B Training


Precipitator
Start-up

Prepare to energize T/R controls

As the final step in returning the Key Interlock


system to its normal operating position, interlock
keys from the T/R grounding switch are inserted
in the individual T/R control panels.

Tanjung Jati B Training


Precipitator
Start-up

Energize Hopper and Support Insulator Heaters

The heaters are to be energized at least eight (8)


hours before starting the Precipitator.

Energize all of the Rapper Systems prior to initial fire

Even though the T/R sets are not energized, the


rapping systems should be in operation whenever
gas is flowing through the Precipitator.

Tanjung Jati B Training


Precipitator
Start-up

Start the Ash System

Energize T/R Sets & Prepare to increase system


Voltage

Since condensation within the precipitator can result


in the deposition of sticky or wet deposits which will
be difficult to remove and can lead to corrosion,
energizing the precipitator should be delayed until
the flue gas temperature reaches a minimum of
132oC (270oF).

Tanjung Jati B Training


Precipitator
Start-up

Energize T/R Sets

With the controller set for zero volts output,


energize the unit. Bring the T/R primary voltage
up slowly.

When the output reaches approximately 25


KVDC, see that both primary and secondary
currents are registering on their respective
meters.

Tanjung Jati B Training


Precipitator
Start-up

Primary Voltage

Primary Current

Secondary Voltage

Secondary Current

T/R SET CONTROLLER METERS

Tanjung Jati B Training


Precipitator
Start-up

Energize T/R Sets

If either current does not register, or if they are


excessive, de-energize the system using the proper
interlock procedures for personnel safety. Check for
an open or shorted condition in the precipitator
system. Rectify the problem, then start again.

Tanjung Jati B Training


Precipitator
Start-up

Energize T/R Sets

Set the under-voltage trip level at the desired


point and record the time it takes the controller
to trip off line. (Commissioning Phase Only).

Let the unit run at 25 KVDC for thirty minutes.

Tanjung Jati B Training


Precipitator
Start-up

Energize T/R Sets

After the T/R has run at the reduced voltage level for
thirty (30) minutes, increase the input until the unit
reaches rated voltage or current, whichever comes
first.

DO NOT EXCEED EITHER THE RATED VOLTAGES


OR RATED CURRENTS OF THE T/R SET.

Tanjung Jati B Training


Precipitator
Start-up

Primary Voltage

Primary Current

Secondary Voltage

Secondary Current

T/R SET CONTROLLER METERS

Tanjung Jati B Training


Precipitator
Start-up

For a detailed list of Precautions when operating,


starting up and shutting down T/R Controllers,
consult NWLs Operation & Maintenance Manuals.

Tanjung Jati B Training


OVERVIEW
PRECIPITATOR START-UP
(END)

Tanjung Jati B Training