5. During a project, earned value analysis is performed, resulting in the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

CV: +120,000; SV: +100,000

CV: +100,000; SV: +120,000

CV: -100,000; SV: -120,000


CV: -120,000; SV: -100,000

See references Marked for review

6. A project manager spent some days to create a multi-page document, which he called project
charter. The document should have been issued by the project sponsor. The sponsor found the
document outsized and asked for a condensed document.

Which of the following is usually not an element of the project charter?


The authority level of the project manager
Detailed control account and work package descriptions

The business need that the project was undertaken to address

High-level risks