Professional Documents
Culture Documents
Risk Register PDF
Risk Register PDF
Project ID Number
REGION/PROJECT: Bay Tunnel PROJECT RISK REGISTER Prepared By: Bob Mues
Award: $215,294,530 - NTP: 4/1/2010
CONTRACTOR: MJC-JV Prepared Date: 10/8/2010
Unforeseen ground Interface Control of the Although this Assure Contractor submittals
conditions between between San tunnel (vertical/ subsurface discontinuity are in on schedule and Mues, Bob 1/1/2013 7/5/2013 Proposed
the Franciscan Antonio horizontal) Wong, 0 - Contractor is well defined in the properly reviewed and
003 Technical Tunnel Open 3/1/2013 7/5/2013 4 - Likely 3 - Moderate 0 0 0 0 0 0 0 Mitigate
Formation and San Formation alignment Johanna Risk GBR, assure that approved.with any
Assist Contractor
Antonio Formation (softer ground) between the San Contractor's EPB TBM other special measures Mues, Bob 1/1/2013 7/5/2013 Proposed
interface. and Franciscan Antonio design includes a needed.
Formation Formation and suitable guidance
Additional
CM/SFPUC 9 FTE @
hyperbaric $150.00/hr = Assure that the
interventions $10,800/day and CS 8 Contractor has planned
Hitting unforseen FTE @ $100/hr =
needed to to perform maintenance
Franciscan $6,400 + office @ Assure Contractor submittals
change interventions prior to
Formation in Differing site Wong, $100/day = $6,500/day are in on schedule and
004 Technical Tunnel cutterhead; Open 7/12/2011 3/12/2013 2 - Unlikely 3 - Moderate 3 - Moderate 10 15 20 673,000 1,009,500 1,346,000
. Total daily cost =
Mitigate each reach with Mues, Bob 1/1/2013 7/5/2013 Proposed
reaches not conditions. Johanna properly reviewed and
productivity loss; $17,300. Add for loss geotechnical data
surveyed in the approved.
TBM not of productivity using "gaps"; assure that
GBR $50,000 per day X the
designed for back-up equipment and
additional days to
great lengths of supplies are available.
accomplish the work.
hard ground.
CM QA Inspectors to verify
that Contractor has tested
the water, and has a test
Worker health & plan in place to continually Hogan, Tom 3/1/2013 12/31/2013 Proposed
safety concerns test and manage the water
if contaminated throughout the Newark shaft
groundwater not installation work.
Gravel lenses
handled Verification by ECM,
across site QA Inspectors assure that
appropriately. EIs, and QA Inspectors
causing greater the shaft is sealed to avoid
Handling of Contractor may that Contractor has its
infiltration or contaminated water from
contaminated be required to plan, permits, disposal
existing interfering with the tunnel
groundwater/soil at shut-down 0 - Contractor site, and resources for
009 Safety Newark contaminant Contractor Open 3/1/2013 12/31/2013 5 - Frequent
Risk
3 - Moderate 0 0 0 0 0 0 0 Contractor Risk Mitigate completion and installation of
Newarks shaft site dewatering this contaminated water Hogan, Tom 3/1/2013 12/31/2013 Proposed
plume has the final lining pipe into the
in excess of amount operation (and in place prior to
different tunnel and shaft, and the
specified. not be allowed commencement of the
constituents or surface pipe
to discharge by Newark Shaft
higher installation/connection to the
USD) if installation.
concentrations. existing BDPL1.
contaminants
not properly
On-going verification that
treated prior to
Contractor meets
disposal.
requirements of their Union Peterson,
3/1/2013 12/31/2013 Proposed
Sanitary District discharge Megan
permit with dewatering
operation.
Require expanded
engineering controls for
Mues, Bob 7/1/2010 5/15/2015 Active
sound attenuation
(mufflers/enclosures of loud
Contractor's Monitor site work to
Resident equipment).
failure to comply Potential work identify problem before Require increased distance
complaints, and (if possible) from sound Mues, Bob 7/1/2010 5/15/2015 Active
with noise and stoppage until recognized by the
irritation, with Ravenswoo 0 - Contractor source or sound walls (if
013 Community vibration code complaints are Contractor Open 7/1/2010 5/15/2015 3 - Possible
Risk
2 - Minor 0 0 0 0 0 0 0 Contractor Risk Mitigate public; provide
construction noise, d required).
requirements, or addressed and proactive outreach to
dust, lighting, Remove/change out the
if compliant, mitigated. community of upcoming Mues, Bob 7/1/2010 5/15/2015 Active
vibration, etc. source or noise emitter.
public irritation. activities.
Provide on-going updates to
Kerby,
community via mailers, door 7/1/2010 5/15/2015 Active
Christina
hangers, blog of activities.
Excessive TBM
CM/SFPUC 9 FTE @ Check to increase spare part
head, face $150.00/hr = inventory once condition is Mues, Bob 7/12/2011 9/12/2013 Proposed
chamber, cutter, $10,800/day and CS 8
FTE @ $100/hr =
verified.
Different and screw
$6,400 + office @ Assure that there are
More abrasive subsurface conveyor wear
Wong, $100/day = $6,500/day adequate spare parts
CM/SFPUC 9 FTE @
$150.00/hr =
Terms of
$10,800/day and CS 8
Subsurface Agreement not FTE @ $100/hr =
Easement is not acceptable to $6,400 + office @
Cannot start Work with property Finalize Agreement with Property
obtained from parties; Board Wong, $100/day = $6,500/day
022 Management Tunnel tunnel Open 9/20/2010 6/30/2011 2 - Unlikely 5 - Catastrophic 5 - Catastrophic 21 60 120 240 1,488,000 2,976,000 5,952,000 + Standby Costs @ Avoid owners and City Owners. Submit Agenda Item to Morelli, Brian 9/20/2010 30-Jun-11 Active
Cargill, SamTrans, of Supervisors Johanna the Board of Supervisors
excavation. $7,500/day = Attorney.
and Mid Peninsula reject purchase $14,000/day. Total
Open Space District. of subsurface Daily Rate =
easement. $24,800/day. Standby
costs include
equipment, security,
CM/SFPUC 9 FTE @
$150.00/hr = Check on-going monitoring of
$10,800/day and CS 8 BDPLs and check that data is Hnat, Steve 8/1/2010 5/15/2015 Active
BDPLs will require Assure Contractor installs and consistent with no movement.
FTE @ $100/hr =
owner repair, which monitors survey monuments
$6,400 + office @
Temporary site
facilities may be
damaged. May
have to re-
excavate shaft
Wong, Implementation of
025 Safety Earthquake (Major) Bay Tunnel Act of God and portions of Open 8/5/2010 3/2/2015 1 - Rare 5 - Catastrophic 5 - Catastrophic 15 0 0 0 0 0 0 Contractor Risk Accept
Johanna Safety Plan.
the tunnel to re-
access. Integrity
of shaft and
tunnel possisbly
compromised.