Professional Documents
Culture Documents
Goal Sub-Purpose 1 Output 1.1 Activity 1.1A Sub-Activity 1.1aa Sub-Activity 1.1ab
Goal Sub-Purpose 1 Output 1.1 Activity 1.1A Sub-Activity 1.1aa Sub-Activity 1.1ab
The progress should cascade from Activity, its corresponding output, the resulting sub-purpose and
ultimately goal. This can be expressed in percentages e.g Activity X is 50% complete based on the
completed sub-activities, output y is 60% complete based on the completed activities, sub-purpose z is
70% complete based on the completed outputs, and the overall project goal progress is 70%.
Goal
Sub-Purpose 1
Output 1.1
Activity 1.1A
Sub-activity 1.1Aa Planned Start date, actual end date,
Planned budget, actual budget, report
Sub-activity 1.1Ab
I am thinking of using a tracker module with programs, programstages, tracked entities e.t.c. However,
your additional inputs is most welcome.