Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

SSP-MRTC-UNGW-PACKAGE C-OVPR REV00 3 Month Rolling Programme(10.2017~12.

2017) 29-Sep-17

Activity ID Activity Name Remaining Start Finish Qtr 4, 2017 Qtr 1, 2018
Duration
Sep Oct Nov Dec Jan
SSP-MRTC-UNGW-PACKAGE C-OVPR REV00
SSP-MRTC-UNGW-PA 274 09-May-17 A 28-Jun-18

MILESTONES 64 27-Sep-17 30-Nov-17

UGPCML0000 Project Start Date 0 27-Sep-17


UGPCML0010 BM North Station Base Slab 0 30-Nov-17*
UGPCML0020 External Wall/Headwall for Northern Drive TBMs Launch 0 31-Oct-17*
UGPCML0030 Allow for Launching and initial drive of north drive-start 0 30-Nov-17*

BANDAR MALAYSIA NORTH STATION 134 09-May-17 A 08-Feb-18

SITE PREPARATION 34 13-Aug-17 A 31-Oct-17


UGPCNSP0100 [BMN] Site Establishment C 34 13-Aug-17 A 31-Oct-17 [BMN] Site Establishment C
PRELIMINARIES 15 16-Oct-17 31-Oct-17
DEMOLITION WORKS 15 16-Oct-17 31-Oct-17
UGPCNDE0020 [BMN][SB] Demolition Works at South Side GL15-28 15 16-Oct-17 31-Oct-17 [BMN][SB] Demolition Works at South Side GL15-28
UTILITIES RELOCATION 10 21-Oct-17 31-Oct-17
UGPCNUR0020 [BMN][SB] Utilities Relocation at South Side GL15-28 10 21-Oct-17 31-Oct-17 [BMN][SB] Utilities Relocation at South Side GL15-28
RETAINING WALL 100 31-Oct-17 08-Feb-18
STATION BOX 100 31-Oct-17 08-Feb-18
UGPCNRW0030 [BMN][SB] Install SBP at South Side GL 15-25 75 31-Oct-17 14-Jan-18 [BM
UGPCNRW0040 [BMN][SB] Install SBP at South Side GL 25-28 35 30-Dec-17 03-Feb-18
UGPCNRW0080 [BMN][SB] Grouting at South Side GL15-25 80 20-Nov-17 08-Feb-18
EXCAVATION WORKS 83 09-May-17 A 19-Dec-17
NORTH SIDE(1-7) 22 12-Jul-17 A 19-Oct-17
UGPCNEW0050 [BMN][SB] Install GAL3 4 12-Jul-17 A 01-Oct-17 [BMN][SB] Install GAL3
UGPCNEW0060 [BMN][SB] Excavate to Soffit of Concourse Level (Incl. RB &GA insa 8 01-Aug-17 A 05-Oct-17 [BMN][SB] Excavate to Soffit of Concourse Level (Incl. RB &GA insallation)
UGPCNEW0070 [BMN][SB] Excavate to Final Excavation Level (Incl. RB &GA installa 22 13-Aug-17 A 19-Oct-17 [BMN][SB] Excavate to Final Excavation Level (Incl. RB &GA installation)
CENTRE(7-11) 83 09-May-17 A 19-Dec-17
UGPCNEW0090 [BMN][SB] Install GAL1 0 09-May-17 A 27-Sep-17 [BMN][SB] Install GAL1
UGPCNEW0100 [BMN][SB] Excavate to 1m Below GAL2 6 17-Jun-17 A 03-Oct-17 [BMN][SB] Excavate to 1m Below GAL2
UGPCNEW0110 [BMN][SB] Install GAL2 8 29-Jun-17 A 06-Oct-17 [BMN][SB] Install GAL2
UGPCNEW0120 [BMN][SB] Excavate to 1m Below GAL3 15 03-Aug-17 A 18-Oct-17 [BMN][SB] Excavate to 1m Below GAL3
UGPCNEW0140 [BMN][SB] Install GAL3 18 07-Aug-17 A 21-Oct-17 [BMN][SB] Install GAL3
UGPCNEW0150 [BMN][SB] Excavate to 1m Below GAL4 12 24-Oct-17 05-Nov-17 [BMN][SB] Excavate to 1m Below GAL4
UGPCNEW0160 [BMN][SB] Install GAL4 8 01-Nov-17 09-Nov-17 [BMN][SB] Install GAL4
UGPCNEW0162 [BMN][SB] Excavate to Final Excavation Level (Incl. RB installation) 40 09-Nov-17 19-Dec-17 [BMN][SB] Excavate to Final Excav
RC STRUCTURE 61 30-Sep-17 30-Nov-17
NORTH SIDE 31 30-Sep-17 31-Oct-17
GL0-2B BASE SLAB 10 30-Sep-17 10-Oct-17
UGPCNRC0000 [BMN][SB] Cast Base Slab (Including Earth Mat) 10 30-Sep-17 10-Oct-17 [BMN][SB] Cast Base Slab (Including Earth Mat)
GL0-2 REMAINING S
STRUCTURE 21 10-Oct-17 31-Oct-17
UGPCNRC0010 [BMN][SB] Cast Base External Wall for Launching 21 10-Oct-17 31-Oct-17 [BMN][SB] Cast Base External Wall for Launching
CENTRE 51 10-Oct-17 30-Nov-17
GL2B-10 BASE SLAB 51 10-Oct-17 30-Nov-17
UGPCNRC0110 [BMN][SB] Cast Base Slab (Including Earth Mat) 51 10-Oct-17 30-Nov-17 [BMN][SB] Cast Base Slab (Including Earth Mat)

BANDAR MALAYSIA SOUTH STATION&CRO2 274 29-Aug-17 A 28-Jun-18

SITE PREPARATION 15 29-Aug-17 A 12-Oct-17


UGPCSSP0002 [BMS.CRO] Drainage 15 29-Aug-17 A 12-Oct-17 [BMS.CRO] Drainage
UGPCSSP0031 [BMS] Silt Trap 10 29-Aug-17 A 07-Oct-17 [BMS] Silt Trap
UGPCSSP0050 [BMS] Toilet Setup 3 29-Aug-17 A 30-Sep-17 [BMS] Toilet Setup
PRELIMINARIES 64 27-Sep-17 30-Nov-17
DEMOLITION WORKS 10 27-Sep-17 07-Oct-17
UGPCSDE0000 [BMS][SB] Demolition Works 10 27-Sep-17 07-Oct-17 [BMS][SB] Demolition Works
UTILITIES RELOCATION 10 27-Sep-17 07-Oct-17

Actual Work Critical Remaining Work Page 1 of 2 NAN YANG TUNNEL ENGINEERING SDN. BHD.
Remaining Work Milestone
SSP-MRTC-UNGW-PACKAGE C-OVPR REV00 3 Month Rolling Programme(10.2017~12.2017) 29-Sep-17

Activity ID Activity Name Remaining Start Finish Qtr 4, 2017 Qtr 1, 2018
Duration
Sep Oct Nov Dec Jan
UGPCSUR0000 [BMS][SB] Utilities Relocation(Water Main & TNB Power Cables) 10 27-Sep-17 07-Oct-17 [BMS][SB] Utilities Relocation(Water Main & TNB Power Cables)
TENDER AND MOBILIZATION
MOBILIZA 64 27-Sep-17 30-Nov-17
UGPCSTM0000 [BMS][CRO]Mobilization&Temporary Facilities 64 27-Sep-17 30-Nov-17 [BMS][CRO]Mobilization&Temporary Facilities
RETAINING WALL 274 27-Sep-17 28-Jun-18
STATION BOX 141 27-Sep-17 15-Feb-18
UGPCSRW0002 [BMS][SB] Diaphragm Wall Trail Panel 28 05-Oct-17 02-Nov-17 [BMS][SB] Diaphragm Wall Trail Panel
UGPCSRW0003 [BMS][SB] SI For GL08-GL01 25 27-Sep-17 22-Oct-17 [BMS][SB] SI For GL08-GL01
UGPCSRW0004 [BMS][SB] SI For GL16-GL08 30 22-Oct-17 21-Nov-17 [BMS][SB] SI For GL16-GL08
UGPCSRW0005 [BMS][SB] SI For GL24-GL16 30 21-Nov-17 21-Dec-17 [BMS][SB] SI For GL24-GL16
UGPCSRW0007 [BMS][SB] Guide Wall For GL08-GL01 30 20-Oct-17 19-Nov-17 [BMS][SB] Guide Wall For GL08-GL01
UGPCSRW0008 [BMS][SB] Guide Wall For GL16-GL08 30 19-Nov-17 19-Dec-17 [BMS][SB] Guide Wall For GL16-G
UGPCSRW0009 [BMS][SB] Guide Wall For GL24-GL16 30 19-Dec-17 18-Jan-18
UGPCSRW0010 [BMS][SB] Diaphragm Wall GL08-GL01 45 02-Nov-17 17-Dec-17 [BMS][SB] Diaphragm Wall GL08-GL
UGPCSRW0011 [BMS][SB] Diaphragm Wall GL16-GL08 60 17-Dec-17 15-Feb-18
UGPCSRW0013 [BMS][SB] Capping Beam For GL08-GL01 50 22-Nov-17 11-Jan-18 [BMS][
UGPCSRW0016 [BMS][SB] Grouting Works For GL08-GL06 60 19-Nov-17 18-Jan-18
CROSSOVER 251 20-Oct-17 28-Jun-18
UGPCSRW0024 [BMS][CRO] SI For X18-X1 60 20-Oct-17 19-Dec-17 [BMS][CRO] SI For X18-X1
UGPCSRW0026 [BMS][CRO] Guide Wall For X18-X1 60 19-Nov-17 18-Jan-18
UGPCSRW0030 [BMS][CRO] Diaphragm Wall X18-X1 189 30-Nov-17 07-Jun-18
UGPCSRW0040 [BMS][CRO] Capping Beam X18-X1 180 30-Dec-17 28-Jun-18
ADITS/ENTRANCES 120 02-Nov-17 02-Mar-18
ENTRANCE A & VENT STRUCTURE A 120 02-Nov-17 02-Mar-18
UGPCSRW0060 [BMS][ENTA&VA] Trail Pile 40 02-Nov-17 12-Dec-17 [BMS][ENTA&VA] Trail Pile
UGPCSRW0070 [BMS][ENTA&VA] Install SBP&Grouting 80 12-Dec-17 02-Mar-18
ENTRANCE B & VENT
VEN STRUCTURE B 80 05-Dec-17 23-Feb-18
UGPCSRW0080 [BMS][ENTB&VB] Install SBP&Grouting 80 05-Dec-17 23-Feb-18

DESA WATER PARK PORTAL&U TROUGH 160 26-Jul-17 A 06-Mar-18

SITE PREPARATION 15 15-Sep-17 A 12-Oct-17


UGPCPSP0050 [DEWP] Site Rest Area Setup 15 15-Sep-17 A 12-Oct-17 [DEWP] Site Rest Area Setup
PRELIMINARIES 40 26-Jul-17 A 06-Nov-17
UTILITIES RELOCATION 25 26-Jul-17 A 22-Oct-17
UGPCPUR0000 [DEWP] Utilities Relocation(Sewerage, Water Main, Telecommunica 25 26-Jul-17 A 22-Oct-17 [DEWP] Utilities Relocation(Sewerage, Water Main, Telecommunication Cables & TNB Power Cables)
PREPARATION FOR PIL
PILLING WORKS 40 25-Sep-17 A 06-Nov-17
UGPCPPR0010 [DEWP] Sheet Pile(zone 4) 3 25-Sep-17 A 30-Sep-17 [DEWP] Sheet Pile(zone 4)
UGPCPPR0015 [DEWP] Sheet Pile(zone1/2) 12 30-Sep-17 12-Oct-17 [DEWP] Sheet Pile(zone1/2)
UGPCPPR0020 [DEWP] Slope Triming and Platform Construction 40 27-Sep-17 06-Nov-17 [DEWP] Slope Triming and Platform Construction
RETAINING WALL 145 12-Oct-17 06-Mar-18
RETRIEVAL SHAFT 105 12-Oct-17 25-Jan-18
UGPCPRE0000 [DEWP] Install SBP at RHS(zone 1) 30 16-Nov-17 16-Dec-17 [DEWP] Install SBP at RHS(zone 1)
UGPCPRE0010 [DEWP] RHS RC Wall(zone 1) 40 16-Dec-17 25-Jan-18
UGPCPRE0030 [DEWP] Install SBP at LHS(zone 1) 50 12-Oct-17 01-Dec-17 [DEWP] Install SBP at LHS(zone 1)
UGPCPRE0040 [DEWP] LHS RC Wall(zone 1) 20 01-Dec-17 21-Dec-17 [DEWP] LHS RC Wall(zone 1)
CUT&COVER SECTION 135 22-Oct-17 06-Mar-18
UGPCPRE0050 [C&C] Install CBP at RHS(zone4) 25 22-Oct-17 16-Nov-17 [C&C] Install CBP at RHS(zone4)
UGPCPRE0060 [C&C] Install SBP at RHS(zone4) 40 01-Dec-17 10-Jan-18 [C&C] In
UGPCPRE0070 [C&C] Install SBP at RHS(zone2) 80 16-Dec-17 06-Mar-18
UGPCPRE0092 [C&C] RHS RC Wall(zone4 for CBP) 40 16-Nov-17 26-Dec-17 [C&C] RHS RC Wall(zone

Actual Work Critical Remaining Work Page 2 of 2 NAN YANG TUNNEL ENGINEERING SDN. BHD.
Remaining Work Milestone

You might also like