1) Pneumatic caissons are constructed above ground with formwork and then subsided into the ground by excavating soil from within, causing the caisson to sink under its own weight. 2) As the caisson subsides, compressed air is used to regulate the sinking and keep water out. 3) When the caisson reaches its final depth, it is sealed with concrete to prevent further subsidence.
1) Pneumatic caissons are constructed above ground with formwork and then subsided into the ground by excavating soil from within, causing the caisson to sink under its own weight. 2) As the caisson subsides, compressed air is used to regulate the sinking and keep water out. 3) When the caisson reaches its final depth, it is sealed with concrete to prevent further subsidence.
1) Pneumatic caissons are constructed above ground with formwork and then subsided into the ground by excavating soil from within, causing the caisson to sink under its own weight. 2) As the caisson subsides, compressed air is used to regulate the sinking and keep water out. 3) When the caisson reaches its final depth, it is sealed with concrete to prevent further subsidence.
5.1 Preparation Pneumatic caissons are usually constructed above ground level. Prior to the actual construction, sand bodies are applied upon the ground level and should then be stabilised. The sand bodies form the counter mould of the work chambers. Formwork is put into the sand body on the place of the future entrance to the work chamber to initiate excavation later on. A blinding (werkvloer) with starter bars (stekeinden) is cast on top of the sand body. The starter bars should lateron connect the fill concrete with the structural concrete of the caisson. They should also prevent that parts of the blinding let off during subsidence. 5.2 Caisson construction The cutting edges (eventually prefabricated) and the bottom plate are cast as a whole. Together they form the 'work chamber'. After hardening of the work chamber, the walls and eventually the roof can be cast. This can either be done in one cast. Otherwise the inner walls can be cast before the outer walls and the roof depending on the cooling mechanism used. If freshly cast concrete has been cooled, impermissible shrinkage cracks should not occur in structural parts that are cast onto already hardened parts. To prevent air leakage, joints of timber caissons, which were used in the past, were packed with oakum (uitgeplozen touw). Also the joints of former steel caissons, subjected to air pressure, must be well caulked (waterdicht gemaakt). Nowadays reinforced concrete is commonly used for caissons because it is considered to be the best material for caissons and also to be the most economical. Reinforced concrete caissons, however, also need precautions because the material frequently is not proof against loss of air pressure through the concrete. This can be accomplished by painting the inner surfaces with bituminous or other suitable paint. Special attention should be paid to joints, the number of which should be limited as much as possible. 5.3 Subsidence When the caisson itself is ready, soil can be dug from within this work chamber which causes the caisson to subside into the ground. Nowadays the soil is often removed after it has been mixed with water. In this way it can be removed by suction through a high-pressure tube. Excavation was traditionally done by hand, but nowadays preferably by water canons or sand pumps. Sometimes the air pressure can be used to blow out mud and wet soil through a pipe. The excavated soil is removed by a hydraulic transport system. There should be a basin close to the site where the removed sand-water mixture can be deposited. The caisson is subsided under its weight. This is usually done by gradually building up, which is especially favourable if there will be ballast on top of the caisson anyway in its final stage (like a pier, for example) (see Figure 5-1). Ballast can alternatively be applied inside the caisson. It should be given thought that a heavy dead weight can cause a caisson to subside even before excavation starts, leading to fill of the working chamber (and possibly even the shafts) with soil. If this will happen, bothersome delay is inevitable. It should for this reason be avoided that the caisson is too heavy. Figure 5-1 Measures to improve subsidence of a pneumatic caisson The air in the work chamber has to be kept under compression to prevent ground water from intruding. Compressed air, on the other hand, also functions as an air bag that lifts the caisson. By varying the air pressure, the pressure on the cutting edges can be regulated in order to influence the subsidence and position of the caisson. The pressure in the working chamber is adjusted to balance, or slightly exceed the water pressure at the depth of the cutting edge. To boost sinking, the air pressure is often reduced more considerably when works men are out of the working chamber. The cutting edge must be sufficiently below the inside soil surface to prevent serious loss of air through the soil. The height of the cutting edges can therefore measure up to two metres. If air pressure and excavation near the cutting edges do not sufficiently regulate the subsiding process, a sliding plane of bentonitecan be applied between the caisson wall and soil. An other measure to better control the subsidence process isto project the edges of the work chamber slightly outside the profiles of the structure (this should be considered in advance). Excavation generally occurs aloof of the cutting edges to leave them embedded in soil and thus avoid loss of air. If, however, the subsidence needs correction because the caisson is not kept level, excavation should occur close to the cutting edges where greater subsidence is desired. Eventual obstacles that come across during excavation, like remainders of old structures, can be removed through the air lock. Large obstacles like boulders (zwerfkeien) can be subsided along with the caisson by washingaway the soil beneath them. When the caisson has reached its final depth, it isgenerally sealed with concrete, which means that the work chamber is completely filled up or injected completely with concrete. To prevent the caisson from sinking lower than the desired level before the concrete seal is fulfilling function, the caisson can be propped (gesteund) well from the soil up to the roof. In that case, the caisson roof has to be sufficiently strong. Otherwise, the props will need to be placed under the ribs in the roof. In some cases the caisson is subsided onto previously applied foundation piles to assure fixation. The subsequent stages of pneumatic caisson subsidence are depicted in Figure 5-2. This example comes from the steel caisson which has been used for the river pier of Lambeth Bridge in London. The application of pneumatic is limited to depths up to about 30 m below the free- water surface, because of the high water pressure at these depths. This limitation may sometimes be overcome where it is possible to lower the groundwater level by pumping. This can only be done in case of suitable surface and subsoil conditions. Lowering of the groundwater level can even be accomplished in river or estuary beds if the caisson is surrounded by a cofferdam and an impermeable lay er separates the river bed from the artesian water.
The Modern Bricklayer - A Practical Work on Bricklaying in all its Branches - Volume III: With Special Selections on Tiling and Slating, Specifications Estimating, Etc