Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

G+5 Building...

Project Start 02-Oct-17


Report Date 18-Oct-17 12:48 Project Finish 10-Jul-18

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

Enterprise All Initiatives


RB222 Five STorey
BES11 FIVE ST BUILD
BES11.GG5 G+5 Building
BES11.GG5.GG5 G+5 Building
BES11.GG5.GG5 Excavation
A1950 Site Clearance 1 1 0% 20-Oct-17 20-Oct-17 SS.Site Supervisor
A1960 Machine clearance 1 1 0% 23-Oct-17 23-Oct-17 SS.Site Supervisor
A1970 Hand Tools Excavation 1 1 0% 24-Oct-17 24-Oct-17 SS.Site Supervisor
A1940 Site survey 2 2 0% 18-Oct-17* 19-Oct-17 SS.Site Supervisor

Subtotal 5 5 18-Oct-17 24-Oct-17

BES11.GG5.GG5 SubStructure
A1980 Levelling 1 1 0% 25-Oct-17 25-Oct-17 SS.Site Supervisor
A1990 Shuttering foundation 1 1 0% 26-Oct-17 26-Oct-17 MZ.Mazdoor
A2000 Reinforcement for foundation and 1 1 0% 26-Oct-17 26-Oct-17 SS.Site Supervisor
column
A2010 Concreting 1 1 0% 27-Oct-17 27-Oct-17 MS.Mason
A2030 De-shuttering 1 1 0% 03-Nov-17 03-Nov-17 MZ.Mazdoor
A2040 Fill around foundation 1 1 0% 03-Nov-17 03-Nov-17 SS.Site Supervisor
A2020 Curing 4 4 0% 30-Oct-17 02-Nov-17 MZ.Mazdoor

Subtotal 8 8 25-Oct-17 03-Nov-17

BES11.GG5.GG5 SuperStructure
BES11.GG5.GGround Floor
BES11.GGSkeletal Works
A2060 Plinth beam concreting 1 1 0% 08-Nov-17 08-Nov-17 MS.Mason
A2070 Plinth beam deshuttering 1 1 0% 09-Nov-17 09-Nov-17 MS.Mason
A2100 Column concreting 1 1 0% 20-Nov-17 20-Nov-17 MS.Mason
A2130 Beam concreting and deshuttering 1 1 0% 29-Nov-17 29-Nov-17 MS.Mason

A2160 Concreting of slabs 1 1 0% 12-Dec-17 12-Dec-17 MS.Mason


A2050 Plinth beam shuttering and 2 2 0% 06-Nov-17 07-Nov-17 SS.Site Supervisor
reinforcement
A2090 Column reinforcement and 2 2 0% 16-Nov-17 17-Nov-17 SS.Site Supervisor
shuttering
A2120 Beam reinforcement and 2 2 0% 27-Nov-17 28-Nov-17 SS.Site Supervisor
shuttering
A2150 REinforcement and shuttering of 2 2 0% 08-Dec-17 11-Dec-17 SS.Site Supervisor
slabs
A2080 Curing 4 4 0% 10-Nov-17 15-Nov-17 MZ.Mazdoor
A2110 Column deshuttering and curing 4 4 0% 21-Nov-17 24-Nov-17 MZ.Mazdoor
A2170 Deshuttering and curing of slabs 5 5 0% 13-Dec-17 19-Dec-17 MZ.Mazdoor
A2140 Curing of beams 6 6 0% 30-Nov-17 07-Dec-17 MZ.Mazdoor

Subtotal 32 32 06-Nov-17 19-Dec-17

BES11.GGWall masonry,door and window


A2190 Brick wall or concrete blocks 5 5 0% 20-Dec-17 26-Dec-17 MS.Mason
A2180 Door and window frames 6 6 0% 27-Nov-17 04-Dec-17 MS.Mason

Subtotal 22 22 27-Nov-17 26-Dec-17

Subtotal 37 37 06-Nov-17 26-Dec-17

BES11.GG5.GFirst Floor
BES11.GGSkeletal Works
A2210 Concreting of column 1 1 0% 22-Dec-17 22-Dec-17 MS.Mason
A2240 Concreting of beam 1 1 0% 03-Jan-18 03-Jan-18 MS.Mason
A2270 Concreting of slab 1 1 0% 15-Jan-18 15-Jan-18 MS.Mason

Page 1 of 4
G+5 Building... Project Start 02-Oct-17
Report Date 18-Oct-17 12:48 Project Finish 10-Jul-18

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A2200 Reinforcement and shutering of 2 2 0% 20-Dec-17 21-Dec-17 SS.Site Supervisor


column
A2230 Reinforcement and shuttering of 2 2 0% 01-Jan-18 02-Jan-18 SS.Site Supervisor
beam
A2260 Reinforcement and shuttering of 2 2 0% 11-Jan-18 12-Jan-18 SS.Site Supervisor
slab
A2220 Deshuttering and curing of column 5 5 0% 25-Dec-17 29-Dec-17 MZ.Mazdoor

A2250 Deshuttering and curing of beam 5 5 0% 04-Jan-18 10-Jan-18 MZ.Mazdoor


A2280 Deshuttering and curing of slab 5 5 0% 16-Jan-18 22-Jan-18 MZ.Mazdoor

Subtotal 24 24 20-Dec-17 22-Jan-18

BES11.GGWall masonry,door and window


A2290 Door and window frame 5 5 0% 01-Jan-18 05-Jan-18 MS.Mason
A2300 Brick or concrete blocks 5 5 0% 23-Jan-18 29-Jan-18 MS.Mason

Subtotal 21 21 01-Jan-18 29-Jan-18

Subtotal 29 29 20-Dec-17 29-Jan-18

BES11.GG5.GSecond Floor
BES11.GGSkeletal Works
A2320 Concreting of column 1 1 0% 25-Jan-18 25-Jan-18 MS.Mason
A2350 Concreting of beam 1 1 0% 06-Feb-18 06-Feb-18 MS.Mason
A2380 Concreting of slab 1 1 0% 16-Feb-18 16-Feb-18 MS.Mason
A2310 Reinforcement and shutering of 2 2 0% 23-Jan-18 24-Jan-18 SS.Site Supervisor
column
A2340 Reinforcement and shuttering of 2 2 0% 02-Feb-18 05-Feb-18 SS.Site Supervisor
beam
A2370 Reinforcement and shuttering of 2 2 0% 14-Feb-18 15-Feb-18 SS.Site Supervisor
slab
A2330 Deshuttering and curing of column 5 5 0% 26-Jan-18 01-Feb-18 MZ.Mazdoor

A2360 Deshuttering and curing of beam 5 5 0% 07-Feb-18 13-Feb-18 MZ.Mazdoor


A2390 Deshuttering and curing of slab 6 6 0% 19-Feb-18 26-Feb-18 MZ.Mazdoor

Subtotal 25 25 23-Jan-18 26-Feb-18

BES11.GGWall masonry,door and window


A2400 Door and window frames 6 6 0% 02-Feb-18 09-Feb-18 MS.Mason
A2410 Brick wall or concrete blocks 6 6 0% 27-Feb-18 06-Mar-18 MS.Mason

Subtotal 23 23 02-Feb-18 06-Mar-18

Subtotal 31 31 23-Jan-18 06-Mar-18

BES11.GG5.GThird Floor
BES11.GGSkeletal Works
A2430 Concreting of column 1 1 0% 01-Mar-18 01-Mar-18 MS.Mason
A2460 Concreting of beam 1 1 0% 13-Mar-18 13-Mar-18 MS.Mason
A2490 Concreting of slab 1 1 0% 23-Mar-18 23-Mar-18 MS.Mason
A2420 Reinforcement and shutering of 2 2 0% 27-Feb-18 28-Feb-18 SS.Site Supervisor
column
A2450 Reinforcement and shuttering of 2 2 0% 09-Mar-18 12-Mar-18 SS.Site Supervisor
beam
A2480 Reinforcement and shuttering of 2 2 0% 21-Mar-18 22-Mar-18 SS.Site Supervisor
slab
A2440 Deshuttering and curing of column 5 5 0% 02-Mar-18 08-Mar-18 MZ.Mazdoor

A2470 Deshuttering and curing of beam 5 5 0% 14-Mar-18 20-Mar-18 MZ.Mazdoor


A2500 Deshuttering and curing of slab 5 5 0% 26-Mar-18 30-Mar-18 MZ.Mazdoor

Subtotal 24 24 27-Feb-18 30-Mar-18

Page 2 of 4
G+5 Building... Project Start 02-Oct-17
Report Date 18-Oct-17 12:48 Project Finish 10-Jul-18

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

BES11.GGWall masonry,door and window


A2510 Door and window frames 5 5 0% 09-Mar-18 15-Mar-18 MS.Mason
A2520 Brick wall or concrete blocks 5 5 0% 02-Apr-18 06-Apr-18 MS.Mason

Subtotal 21 21 09-Mar-18 06-Apr-18

Subtotal 29 29 27-Feb-18 06-Apr-18

BES11.GG5.GFourth Floor
BES11.GGSkeletal Works
A2560 Concreting of column 1 1 0% 04-Apr-18 04-Apr-18 MS.Mason
A2590 Concreting of beam 1 1 0% 16-Apr-18 16-Apr-18 MS.Mason
A2620 Concreting of slab 1 1 0% 26-Apr-18 26-Apr-18 MS.Mason
A2550 Reinforcement and shutering of 2 2 0% 02-Apr-18 03-Apr-18 SS.Site Supervisor
column
A2580 Reinforcement and shuttering of 2 2 0% 12-Apr-18 13-Apr-18 SS.Site Supervisor
beam
A2610 Reinforcement and shuttering of 2 2 0% 24-Apr-18 25-Apr-18 SS.Site Supervisor
slab
A2570 Deshuttering and curing of column 5 5 0% 05-Apr-18 11-Apr-18 MZ.Mazdoor

A2600 Deshuttering and curing of beam 5 5 0% 17-Apr-18 23-Apr-18 MZ.Mazdoor


A2630 Deshuttering and curing of slab 5 5 0% 27-Apr-18 03-May-18 MZ.Mazdoor

Subtotal 24 24 02-Apr-18 03-May-18

BES11.GGWall masonry,door and window


A2530 Door and window frames 5 5 0% 12-Apr-18 18-Apr-18 MS.Mason
A2540 Brick wall or concrete blocks 5 5 0% 04-May-18 10-May-18 MS.Mason

Subtotal 21 21 12-Apr-18 10-May-18

Subtotal 29 29 02-Apr-18 10-May-18

BES11.GG5.GFifth Floor
BES11.GGSkeletal Works
A2670 Concreting of column 1 1 0% 08-May-18 08-May-18 MS.Mason
A2700 Concreting of beam 1 1 0% 18-May-18 18-May-18 MS.Mason
A2660 Reinforcement and shutering of 2 2 0% 04-May-18 07-May-18 SS.Site Supervisor
column
A2690 Reinforcement and shuttering of 2 2 0% 16-May-18 17-May-18 SS.Site Supervisor
beam
A2680 Deshuttering and curing of column 5 5 0% 09-May-18 15-May-18 MZ.Mazdoor

A2710 Deshuttering and curing of beam 5 5 0% 21-May-18 25-May-18 MZ.Mazdoor

Subtotal 16 16 04-May-18 25-May-18

BES11.GGWall masonry,door and window


A2640 Door and window frames 4 4 0% 16-May-18 21-May-18 MS.Mason
A2650 Brick wall or concrete blocks 7 7 0% 22-May-18 30-May-18 MS.Mason

Subtotal 11 11 16-May-18 30-May-18

Subtotal 19 19 04-May-18 30-May-18

BES11.GG5.GRoof
A2730 Insulation and testing 4 4 0% 05-Jun-18 08-Jun-18 MS.Mason
A2740 Tile roof 4 4 0% 11-Jun-18 14-Jun-18 MS.Mason
A2770 Install gutters 4 4 0% 15-Jun-18 20-Jun-18 MS.Mason
A2760 Install wood member 5 5 0% 15-Jun-18 21-Jun-18 MS.Mason
A2720 Cast concrete 6 6 0% 28-May-18 04-Jun-18 SS.Site Supervisor

Page 3 of 4
G+5 Building... Project Start 02-Oct-17
Report Date 18-Oct-17 12:48 Project Finish 10-Jul-18

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A2750 Install steel frames 7 7 0% 15-Jun-18 25-Jun-18 SS.Site Supervisor

Subtotal 21 21 28-May-18 25-Jun-18

Subtotal 166 166 06-Nov-17 25-Jun-18

BES11.GG5.GG5 Finishing
A2790 Carpentry works 5 5 0% 08-Jun-18 14-Jun-18 C.Carpenter
A2800 Insulation and plastering 5 5 0% 15-Jun-18 21-Jun-18 MS.Mason
A2780 Electrical wirings 6 6 0% 31-May-18 07-Jun-18 E.Electrician
A2810 Inner wall painting 6 6 0% 22-Jun-18 29-Jun-18 MZ.Mazdoor
A2820 External painting and coating 7 7 0% 02-Jul-18 10-Jul-18 MZ.Mazdoor

Subtotal 29 29 31-May-18 10-Jul-18

Subtotal 190 190 18-Oct-17 10-Jul-18

Subtotal 190 190 18-Oct-17 10-Jul-18

Subtotal 190 190 18-Oct-17 10-Jul-18

Subtotal 190 190 18-Oct-17 10-Jul-18

Subtotal 190 190 18-Oct-17 10-Jul-18

Total 190 190 18-Oct-17 10-Jul-18

Page 4 of 4

You might also like