RAB

PEKERJAAN : PEMBUATAN BAK SENDIMEN INSTALASI PENGOLAHAN AIR LIMBAH


NO URAIAN PEKERJAAN VOLUMSAT HAGA SATUAN TOTAL HARGA
UPAH BAHAN UPAH UPAH
1 PEK.PERSIAPAN
A Pengukuran 1.00 Ls 650000.00 650000.00 0
B Pembersihan lokasi 8.00 m2 27000.00 216000 0
C Pembuatan Bowplank 8.00 m2 35000.00 27000 280000 216000.00
0 0
IPAL .A 0 0
2 Pek Tanah 0 0
D Galian tanah 16.00 m2 70000.00 1120000 0
E Urugan tanah kembali 4.00 m2 50000.00 200000 0
0 0
3 Pek.Beton & Pasangan 0 0
F Besi,Bekesting&Cor Sloof 0 0
Pembesian 96.99 kg 27000.00 10000 2618730 969900.00
Bekesting 11.90 m2 30000.00 80000 357000 952000.00
Pengecoran K 200 0.51 m3 35000.00 490000 17850 249900.00
0 0.00
G Cor Plat lantai 0 0.00
Urugan Pasir 0.80 m3 35000.00 120000 28000 96000.00
Lc 0.40 m3 18000.00 7200 0.00
Pengecoran K 200 0.80 m3 35000.00 890000 28000 712000.00
0 0.00
H Pek, Cor Kolom 0 0.00
Bekesting 14.00 m2 30000.00 80000 420000 1120000.00
Pembesian 114.1 kg 27000.00 11770 3080700 1342957.00
Pengecoran K 200 0.60 m3 35000.00 490000 21000 294000.00
0 0.00
I Pek.Cor Balok 0 0.00
Bekesting 11.90 m2 30000.00 14000 357000 166600.00
Pembesian 96.99 kg 23000.00 10000 2230770 969900.00
Pengecoran K 200 0.51 m3 30000.00 490000 15300 249900.00
0 0.00
J Pek.Plat penutup 0 0.00
Bekisting 8.00 m2 30000.00 80000 240000 640000.00
Pembesian 8" 14.63 kg 25000.00 10000 365750 146300.00
Pengecoran K 200 0.80 m3 30000.00 490000 24000 392000.00
0 0.00
K Pasangan Batu bata 34.00 m2 30000.00 40000 1020000 1360000.00
L Plesteran 44.00 m2 30000.00 36000 1320000 1584000.00
M Acian Waterprof 44.00 m2 30000.00 36000 1320000 1584000.00
N Pasangan Pipa In 4"+acesoris 6.00 m 19000.00 50000 114000 300000.00
16051300.00 13345457.00

RAB
PEKERJAAN : PEMBUATAN BAK SENDIMEN INSTALASI PENGOLAHAN AIR LIMBAH
NO URAIAN PEKERJAAN VOLUMSAT HAGA SATUAN TOTAL HARGA
UPAH BAHAN UPAH BAHAN
O Pemasangan Pipa In 3/4 +asc 30 m1 8000 5000 240000.00 150000.00
P Pembersihan akhir 8.00 m2 27000.00 216000.00 0.00
Q Saringan 1.00 m3 45000.00 7500 45000.00 7500.00
R Pompa Air 1.00 Unit 35000.00 1700000 35000.00 1700000.00
0.00 0.00
IPAL .B 0.00 0.00
4 Pek Tanah 0.00 0.00
A Galian tanah 16.00 m2 80500.00 1288000.00 0.00
B Urugan tanah kembali 4.00 m2 45000.00 180000.00 0.00
0.00 0.00
5 Pek.Beton & Pasangan 0.00 0.00
C Besi,Bekesting&Cor Sloof 0.00 0.00
Pembesian 96.99 kg 27000.00 10000 2618730.00 969900.00
Bekesting 11.90 m2 30000.00 14000 357000.00 166600.00
Pengecoran K 200 0.51 m3 35000.00 490000 17850.00 249900.00
0.00 0.00
D Cor Plat lantai 0.00 0.00
Urugan Pasir 0.80 m3 35000.00 120000 28000.00 96000.00
Lc 0.40 m3 0.00 0.00
Pengecoran K 200 0.80 m3 35000.00 490000 28000.00 392000.00
0.00 0.00
E Pek, Cor Kolom 0.00 0.00
Bekesting 14.00 m2 30000.00 60000 420000.00 840000.00
Pembesian 114.1 kg 27000.00 10000 3080700.00 1141000.00
Pengecoran K 200 0.60 m3 35000.00 890000 21000.00 534000.00
0.00 0.00
F Pek.Cor Balok 0.00 0.00
Bekesting 11.90 m2 30000.00 60000 357000.00 714000.00
Pembesian 96.99 kg 27000.00 10000 2618730.00 969900.00
Pengecoran K 200 0.51 m3 35000.00 490000 17850.00 249900.00
0.00 0.00
G Pek.Plat penutup 0.00 0.00
Bekisting 8.00 m2 30000.00 80000 240000.00 640000.00
Pembesian 8" 14.63 kg 27000.00 10000 395010.00 146300.00
Pengecoran K 200 0.80 m3 35000.00 490000 28000.00 392000.00
0.00
H Pasangan Batu bata 34.00 m2 40000.00 40000 1360000.00 1360000.00
I Plesteran 44.00 m2 30000.00 30000 1320000.00 1320000.00
J Acian Waterprof 44.00 m2 30000.00 36000 1320000.00 1584000.00
K Pasangan Pipa In 4"+acesoris 6.00 m 22000.00 35000 132000.00 210000.00
16363870.00 13833000.00

RAB
PEKERJAAN : PEMBUATAN BAK SENDIMEN INSTALASI PENGOLAHAN AIR LIMBAH
NO URAIAN PEKERJAAN VOLUMSAT HAGA SATUAN TOTAL HARGA
UPAH BAHAN UPAH UPAH

L Pembersihan Akhir 8.00 m2 25000.00 200000.00


M Saringan 1.00 m3 45000.00 75000 45000.00 75000.00

6 Saluran tambahan
A Bongkaran lantai beton 0.25 m3 26000.00 6500.00
B Galian tanah 5.00 m3 80000.00 400000.00
C Pasangan Bata 33.00 m2 30000.00 40000.00 990000.00 1320000.00
D Plesteran 27.50 m2 25000.00 36000.00 687500.00 990000.00
E Acian 27.5 m2 25000.00 36000.00 687500.00 990000.00
F Gril besi penutup(L40,40,4) 25.2 kg 20000.00 11000.00 504000.00 277200.00
G Besi,Bekesting&Cor Sloof 0.00
H Besi 12 1.07 kg 27000.00 10000.00 28890.00 10700.00
I Tutup saluran ke sungai 3.00 m2 40000.00 50000.00 120000.00 150000.00
J Finishing 11.25 m3 20000.00 225000.00 0.00

3894390.00 3812900.00
Sub Total : 36309560.00 30991357.00
Grand Total : 67300917.00
Dibulatkan : Rp 67,300,000.00
Terbilang : Enam puluh juta Tiga ratus ribu rupiah

Catatan : Pemakaian Portland semen @ 50kg sebanyak 98 Zak