Professional Documents
Culture Documents
Levelling
Levelling
OBJECTIVES
1) To find the elevation of given point with respect to some assumed reference line called
datum.
2) To establish point at required elevation respect to datum.
3) To determine and check the vertical stability of the points with respect to reference
points (benchmarks) in its immediate vicinity.
PROBLEM STATEMENT
An open area within the car park beside of Civil Engineering Faculty UITM Shah Alam, is
required to be surveyed by levelling method to transfer height from BM to determine heights
of all stations using levelling instrument. Each group need to transfer the heights to six
stations with closed loop. The error size for the levelling work should be 5 . All data
has to be recorded according to Survey Regulations by Jabatan Ukur dan Pemetaan Malaysia
(JUPEM). The reference BM is at the stairs beside the lift in block A of Civil Engineering
Faculty with 40.000 m MSL.
APPARATUS
1) Automatic Level including Tripod.
2) Levelling staff (2 units).
3) Tape
4) Staff Bubble
5) Pegs and hammer (if necessary)
PROCEDURE
1) Two peg test was carried out before the task to confirm the instrument was fit to be
used for the levelling work.
2) The levelling work was initially commenced with the level-staff sited on the
Benchmark (BM) having RL 40 m. The next level staff was sited about 20 m from
BM.
3) The instrument was then positioned and temporarily was adjusted between the two
staff and readings was taken. For first staff, the readings was recorded as back sight
whereas second staff was recorded as fore sight. If staff was located between these two
readings , the readings are recorded as intermediate sight.
4) The instrument was then shifted to the next point and temporarily adjusted but staff
noted as fore sight from the first reading was not shifted and the reading was recorded
as back sight. Staff from BM was shifted to another point and was noted as CP
(Change Point) about 20 m apart from the previous point and the reading was recorded
as fore sight.
5) Steps 3 and 4 was repeated until staff was sited on one of the control points. (Note :
the nearest control point was determined from the closed transverse)
6) Then, steps 3 and 4 was again repeated until the last CP was sited on the BM forming
a closed loop. Then, the procedure was repeated.
RESULTS:
PEG TEST:
A1 = 1.1967m B1 = 1.1272m D1= 15.12m
A2 = 1.3236m B2 = 1.1862m D2 = 14.92m
( 2 2 )( 1 )
Peg Test =
1 +2
( 1.32361.1862)( 1.12721.1967)
=
15.12+14.92
= 0.0023 rad/mm
CALCULATION:
A) To obtain the Height of Collimation of station 1 to 6 before applying correction:
Based on the table in result:
Station 1:
R/F = FS Station 1 BS Station 6
= 2.0446 0.6632
= -1.3814
Station 2:
R/F= FS Station 2 BS Station 1
= 1.7065 0.7681
= -0.9384
Station 3:
R/F= FS Station 3 BS Station 2
= 1.4870 1.3188
= - 0.1682
Station 4:
R/F= FS Station 4 BS Station 3
= 1.6790 1.1611
= - 0.5179
Station 5:
R/F= FS Station 5 BS Station 4
= 0.8900 2.0227
= +1.1327
Station 6:
R/F= FS Station 6 BS Station B
= 1.8908 0.2535
= - 1.6373
Allowable Error = 5
= 512
=0.017m
Error = Total Fore Sight Total Back Sight
= 16.1858 16.1813
= 0.0045m
First station (B) correction = Error / Total Station
= 0.0045/ 12
=0.0004
Increment 0.004 is proceed to apply correction to next station until the last station and the last
correction to last station should be 0.0045
To obtain Final Reduced Level for station 1 to 6 and TBM:
Station 1:
FRL = RL Station 1 + 0.00012
= 34.7662 + 0.0012
= 34.7674
Station 2:
FRL = RL Station 2 + 0.0015
= 33.8278 + 0.0015
= 33.8293
Station 3:
FRL = RL Station 3 + 0.0019
= 33.6596 + 0.0019
= 33.6615
Station 4:
FRL = RL Station 4 + 0.0023
= 33.1417 + 0.0023
= 33.1440
Station 5:
FRL = RL Station 5 + 0.0027
= 34.2744 + 0.0027
= 34.2771
Station 6:
FRL = RL Station 6 + 0.0008
= 36.1476 + 0.0008
= 36.1484
Station TBM:
FRL= RL TBM + 0.0045
=39.9955
=40.0000
DISCUSSION
During the levelling works was done, instrumental errors occur where the bubble is not set up
on the centre of the spherical level. This effect the scale of the automatic level cause the
reading is not accurate. Telescope is not at right angles to the vertical axis can effect the
readings of the relative height. Sometimes, movement of staff from position when changing
level station cause the distance between two points changed which cause this error to be
happen. So the person whom be holding the staff rods need to remain on its position during
backsight and foresights reading were taken. Moreover, parallax error occur when the day was
so hot which cause chaotic refraction of light. If this happen, we need to shorten the length of
shots and keep the measurement about 1m above ground. It is advisable to avoid doing
levelling works during noon hours.
CONCLUSION:
From this levelling experiment we can obtain the reduced level of a point or place. For this
experiment the value of reduced level can only be obtain if the allowable error for total back
sight and fore sight is acceptable if it is not accepted it is probably due to error as state in
discussion, thus the experiment need to be repeated. For this particular experiment the
reduced level for station 1 to 6 is obtain by closed loop. We can also conclude by levelling we
can achieve the objective of our experiment.