Professional Documents
Culture Documents
Rock Excavation and Disposal - MST
Rock Excavation and Disposal - MST
Rock Excavation and Disposal - MST
PART 1 - GENERAL
1.01 DESCRIPTION:
A. Remove and dispose of rock and furnish acceptable material for backfill in place of
excavated rock as indicated.
1.03 SUBMITTALS:
1. For each kind of blasting agents and explosives to be used, submit the perchlorate
content provided by the suppliers and/or manufacturers. The Contractor has to
obtain written permission from the Concerned Authority and CM/CS to use
perchlorate-containing explosive products.
2. Keep and submit to CM/CS and at time specified by CM/CS, an accurate record of
each blast showing general location of blast, depth and number of drillholes, kind
and quantity of explosive used, kind and number and interval of delay periods used,
and other data required for a complete record.
(NTS: If blast monitoring is required, the following seven paragraphs are a guide, consult
with Geotechnical Engineer.)
C. Employ an approved, independent, vibration/blasting consultant to conduct test blasting
prior to production blasting, to devise suitable blasting procedures for production
blasting, and to monitor production blasting. Require the vibration/blasting consultant to
be a Professional Engineer and to have a minimum of 10 years experience as a
vibration/blasting consultant. Prior to starting the work, submit the name of the
vibration/blasting consultant to the CM/CS.
D. Test blast to develop control procedures for production blasting so that no disturbance or
damage shall be done to utilities, equipment, buildings, or structures.
E. Based on the results of test blasting, have the vibration blasting consultant develop a
suitable blasting program and distance-quantity of explosive tables for the production
blasting. Submit the blasting program and distance-quantity tables to the CM/CS 21 days
prior to commencement of production blasting. Conduct production blasting operations
in accordance with the blasting program.
A. Keep explosives on the site only in such quantity as needed for work under way and only
during time as being used. Notify CM/CS at least 24 hours in advance of intention to
store and use explosives. Store explosives in a secure manner and separate from all tools.
Store caps or detonators safely at a point over 100 ft (30 m) distant from explosives.
Promptly remove from premises remaining material when need for explosives has ended.
C. Conduct operations involving explosives with all possible care to avoid injury to persons
and property. Do blasting only with such quantities and strengths of explosives and in
such manner as will break rock approximately to intended lines and grades, leaving rock
not to be excavated in an unshattered condition. Avoid excessive cracking of rock upon
or against which any structure will be built. Prevent injury to existing pipes, structures
and property above or below ground. Cover rock with logs or mats, or both. Give
sufficient warning to persons in vicinity of work before a charge is exploded.
PART 2 - PRODUCTS
A. To the extent practical, the Contract shall avoid the use of perchlorate-containing
explosive products when surface or groundwater can be affected.
PART 3 - EXECUTION
3.01 PROCEDURE:
A. Excavate rock in pipe trenches to no less than 6 in. (15 cm) below the proposed invert of
the pipe. Backfill trench, before pipe is laid, to correct subgrade. Use thoroughly
compacted, suitable material or, when so specified or indicated on drawings, same
material as required for bedding pipe. Furnish and place at no additional compensation.
B. Fill excess excavation below elevation of the top of bedding, cradle, or envelope when in
pipe trenches with material of same type and placed and compacted in same manner as
specified for bedding, cradle, or envelope.
D. Drill and blast a single line of holes in vertical face of rock at end of trench, when
shattering rock at ends of pipe or elsewhere as indicated. Provide minimum depth
drillholes of 4 ft. (1.2 m) and maximum spacing of 18 in. (45 cm) centers. Use sufficient
explosive to shatter rock for future excavation. Complete shattering before any pipe or
fitting is placed within 50 ft (15 m) of rock to be shattered.
2. Take reasonable steps to prevent and address misfires: In cases where explosives
or blasting agents are washed or removed for a borehole following a misfire,
reasonable efforts should be made to collect and properly manage or dispose of
perchlorate-containing materials.
F. Remove shattered rock. If rock below normal depth is shattered due to drilling or
blasting operations of Contractor and CM/CS considers such shattered rock to be unfit for
foundations, remove it and backfill excavation with concrete as required, except that in
pipe trenches, use screened gravel for backfill. Do such removal and backfilling at no
additional compensation.
G. Remove dirt and loose rock, as directed, from designated areas and clean surface of rock
thoroughly, using steam to melt snow and ice, if necessary. Remove water in
depressions, so that whole surface of designated area can be inspected to determine
whether seams or other defects exist.
H. Rough surfaces of rock foundations sufficiently to bond well with masonry and
embankments to be built thereon and, if required, cut to rough benches or steps.
I. Remove from the rock surface to remain all vegetation, dirt, sand, clay, boulders, scale,
excessively cracked rock, loose fragments, ice, snow, and other objectionable substances.
Use picking, barring, wedging, streams of water under sufficient pressure, stiff brushes,
hammers, steam jets, and other effective means to accomplish this cleaning, and remove
free water left on the surface of rock. Perform all of above before any masonry or
embankment is built on or against rock.
1. Do not use pieces of rock larger than permitted under subsection "Backfilling Pipe
Trenches" of Section 02210. Rock may be crushed to the gradation required for
backfill.
2. Do not allow rock quantities used in backfill in any location to result in formation
of voids.
L. Backfill with material obtained from outside sources at no additional compensation, when
material suitable for backfilling is not available in sufficient quantity from other
excavations.
END OF SECTION