Professional Documents
Culture Documents
Riego Por Goteo Ingles
Riego Por Goteo Ingles
MEFADERG
I. introduction
Below is the Methodology Drip Irrigation Easy " MEFADERG " which consists of three parts :
The first is the lifting of general data of the producer and the plot , including : climate, lifting the
plot plane carrying , crop type , soil type and water source. To complete this section 1 presents the
instrument " Fto1 General Information " .
A second part , takes data from irrigation requirements based on climate data ( Eto ) and crop (Kc )
and soil data to establish the irrigation depth and irrigation depth then define net and gross ,
further including the application intensity (Ia) , sector size and flow irrigation sector . The latter is
compared with the flow from the source to analyze the viability of irrigation. For section 2 , above
the instrument is used , " Fto 2 Irrigation Requirements " .
Finally a third part consisting of the hydraulic design of drip irrigation system . For this section 3,
use the instrument , " Fto 3 Design of the pipe " . In this section we estimate the pressure drop in a
simple and practical . This uses four tables that were developed to avoid the complex hydraulic
calculations . The tables are used in the fol lowing way :
Afterward, a flow rate ( l / s) to pass through the pipe, after the table No3 , lies the most
approximate value of the desired flow rate and to the right drop seeks closest to the set value
above using the criterion ( operating Pressure ) x9 % / F ( Chistianssen ) , which is the operating
pressure and chistianssen factor described above. Once located both values in the table, it
searches the corresponding diameter vertically , thereby obtain the piping ro Dia .
The sum of the pressure loss of the distribution pipe (found ) and the pressure loss on the side,
should be less than or equal to 20% of the emitter operating pressure .
Three . For piping designed PVC piping , take into account the length (flat previously raised ) and
the flow of the project , thus , taking as criteria allowable pressure drop , which is 2 % of the length
, and flow of the project these values are located in Table No 3 , this first pair flow project located
in the first column and the right wing is looking drop , once found closest values , we look at the
rior to locate the upper pipe diameter used. Os obtenem thus the diameter of the pipe.
April . Eventually add up to 77% loss of lateral loading and distribution tubing , plus the losses in
the conduit line , the more the operating pressure , the pressure drop over the filter and
fertigation systems . These latter values are obtained from manual tape , filter and device for
fertigation. With these values the pump is selected considering their HQ performance curve .
Thus concludes the design of drip irrigation system , which is added to a bill of materials to buy.
II. target
Extension workers and farmers provide a methodology to facilitate the design of drip irrigation
systems , with the aim of contributing to a better adoption of this technology and enable optimum
use of the facility and promote the operation and maintenance of the system.
A. Target
Involve farmers and technicians in the design process of the irrigation system, working on tasks
such as interviews, description of soil texture in the field, lifting the sketch of the plot and the
capacity of the source.
B. Interviews
Using this technique, there is a dialogue with the farmer (s) or group, in order to understand the
data practices described in Fto 1 General Information:
Step No1, area to irrigate
Step No2, growing interest
Step No3, crop rooting depth
Step No 18, hours that the farmer has to risks
In addition to the interview also know if the farmer (s) or group has or not, experience in growing
and operation of irrigation systems. The latter should be recorded in the space of observations is
under the table format general data collection (Fto1).
C. Field Trip.
This technique will help us achieve:
Soil removal is done with an auger or blade and then made manual texture test, samples may also
be taken for laboratory, in order to make a physical and chemical analysis of the soil.
You can use a 200-liter barrel and then measure the time it fills, to test 5 times to know the
average time in which the container is filled, then the expression:
Q = 200 / t, where:
In the case that the water source is a stream should be the following:
Find a stretch of the creek where the cause is as uniform as possible and for the same most of the
water flow and then:
d) Measure the time a floating object travels the premeasured section, do this 5 times and
averaging time.
Then, suppose that in a stretch of 5 m, the floating object traverse lasted 60 seconds, now we get
the velocity by the expression:
V = L / t, where;
V is the speed in m / s
Then we calculate the cross sectional area of the section of the creek, for this we will:
...
We draw on a blank page horizontal lines and vertical separation of 1cm, this will create grids of
1cm x 1cm, for this we can use a ruler to 30cm. Then the gridded area draw the different depths of
the cross section of the channel and also draw the Achura section, assigned drawing 0.5 m per 1
cm paper. At the base of the section (channel bottom) lines join the depths, to close the
perimeter, as shown in the figure below.
Now, the sectional area is the sum of the four drculas enclosed in the perimeter of the
drawing, which are suitable co n circled numbers. In total there are 10 grid, but four of them are
incomplete, so that instead of two grids 4 grid considered complete, thus we have 8 grids, hence
the expression:
A = 8 grids x 0.25 = 2 m2, where, A is the sectional area m2.
Grids are the pictures within the perimeter of the trapezoid drawn.
2
Factor, 0.25, is in m areas, who rebukes a grid surface.
Finally, previous data we estimate the water velocity, by the formula Q = V x A x 1000, wherein;
To perform the analysis using the tool "Ft General o1.Datos" presented in this section. This
instrument is com posed of a table with 4 columns, being this: Steps, Description, Values,
instrument to use. Other support tools include: tables not G1, G2 No tables, tables No G3, G4
tables not. Support tools are used to solve different steps of the instrument "Fto1. General
Information ".
Don Ramon Sanchez, want to grow sweet pepper (sweet pepper) in sandy loam ground 0.25Mz
located in Concord, Nicaragua. He tends and a well and knows the crop management, but has
never planted under irrigation.
Such data are placed in the Fto 1. General information, which has 18 steps, the instrument is
completed with the help of auxiliary instruments as described in the "Column 4 instrument to use"
every step of the main instrument. Below is the instrument, the sample data and auxiliary data
from instruments (tables not G1, G2 No tables, tables No G3, G4 tables not.)
Table No G-4: crop coefficient Kc as a crop alg.
A. Target
Estimate with farmers (as) crop water requirements and how to apply water to maintain proper
humidity levels in the soil for optimum crop growth.
This section presents the instrument "Fto2 irrigation requirements", used to organize the data and
passes to step to the calculations, in order to meet the required flow, irrigation time, irrigation
interval and laminae. These data will be used for the hydraulic design and will Necesar ios for
system operation.
The data come from the instrument to process "Fto1 General Information", which was previously
completed and is described in s ection 1 of this manual.
Now, in the first column of the instrument, "Fto2 Irrigation Requirements" describes the 10 steps,
then in the second column describes the calculations and formulas to be used, in the third column
are placed the results in each step and the fourth shows the origin of each data to be used and the
calculation procedures.
Below is step by step process to implement the instrument, and thus have a better understanding
of each step and each calculation of the instrument.
Step No. 1
ETc = ETo x Kc
For our example data are from the instrument "Fto1 General Information" Step No8, Eto =
6mm/da and Step No9, Kc = 1. With these data it processes the resulting formula:
...
Obtained that the requirement is 6mm/da for growing pepper, the data that is located in Step
No1, the Fto2.
Step No. 2
Because drip irrigation will, we must now adjust the dampening to drip irrigation, drip called
evapotranspiration (Etg), which is made by the formula:
With this method of irrigation is moistened only 50% of the surface of the culture, this is known as
percentage area irrigated (PAR). For our example, applying the formula we obtain:
Etg = 6 x 0.50 = 3mm/da, this data is recorded in Step No. 2, the Fto 2.
Step No. 3
As plants take water from the soil, water requirements will be applied through irrigation, so it is
necessary to calculate the depth of water to be applied to the soil. Now we calculate the irrigation
sheet (Lr) depending on soil type and depth of crop roots, whose relationships are expressed by
the following formula:
The values of field capacity (FC) and permanent wilting point (PMP) come from Fto 1 and
correspond to Steps No6 and No7 whose values are 10% and 4% respectively in our case. Also the
values of root depth (D) and bulk density (Da) Fto1 come from, and are shown in Steps No3 and
No5, with values of Pr = 50cm and Da = 1.4gr/ml, respectively.
This data is shown in Step No3 Fto2 and expresses the amount of water required to reach field
capacity (CC) required to initiate the first irrigation of a crop. Subsequently determined successive
irrigation
irrigation interval, pay back lost moisture and preventing moisture reserves reach exhaustion.
This concept gives rise to net irrigation (Ln), which sheet is used for restoring soil moisture. Such
restitution humidity equals a fraction of the irrigation requirement (Lr) can be defined as the
moisture necessary for the restoration of water a crop is consumed in a certain period of time.
Thus only allowed a certain percentage depletion of irrigation depth (Lr), and when grown
vegetables should be between 15% and 25%.
Ln = Etg x Ir
In Step No2 of this format is presented dropper evapotranspiration, Etg = 3mm/da and the Fto 2
Step No13, find the watering interval, Ir = 2 days. With these values we estimate:
Ln = 3 mm / day x 2 days = 6 mm.
Thus the net irrigation depth (Ln) is 6mm, which is sufficient moisture for 2 days consumption of
the crop. Note that 6mm is about 15% of the irrigation requirement (Lr).
Because when applied irrigation leaks, which are due to irrigation efficiency (Ef) for drip irrigation
systems is to set this value Ef = 0.90. With this data we adjust the net irrigation depth (Ln), by
calculating the gross irrigation depth considering the losses das System by the expression:
Lb = Ln / Ef.
The value for net irrigation in our ca se is according to the formula above:
Lb = 6mm/0.90 = 6.6mm.
This is the value of the water layer to apply e have the soil by irrigation, in order to restore the
capacity of the same field.
At this time know the irrigation raw sheet ( Lb) , whose value indicates the moisture necessary to
restore moisture and consumed by the growing environmental factors over a period of time.
However such sheet is applied through the watering system , so we need to know the intensity of
the application ( Ia) , which data is given in mm / hour).
Ia = qe / ( dlxde ) where QE is the flow in l / h which is applied in a superpi , which is defined by the
distance between lateral (dl) multiplied by distance between emitters (de) .
The data flow of the issuer ( qe = 1 L / h ) is purchased from Step No16 Fto1 also have Steps
therein No14 and No15 , of dond and obtain the distance between lateral ( dl = 1.5 m) and the
distance between transmitters ( from = 0.3m ) respectively in our case.
Thereby calculate: Ia = 1 / ( 1.5x0.3 ) = 2.2 mm / hour. This means that our system apply foil 2.2
mm per hour of operation gives ca .
7 . Run Time (T ) .
Now , to operate the system need to know the time required to apply the gross depth of irrigation
( Lb ) and med iante makes the expression:
T = Lb / Ia, in this way is calculated ;
T = 6.6/2.2 = 3 , from which it is concluded that the raw sheet irrigation apply in 3 hours, since the
system will provide Ia = 2.2 mm / hour. As the watering interval ( Ir) is 2 days , watering is repeated
every two days , to restore the water consumed by the crop and environmental factors that
period.
Now we know the gross depth of irrigation ( Lb ) that r equires the ground to meet the crop , we
also know the time ( T) we need to apply it and how often ( Ir) must practice irrigation operation
restore moisture. Also know what time and the farmer has to make watering operations
.However, unknown to the surface of the irrigation sector . A portion of lot area we want water in
a given period is called irrigation sector , and the number of sectors depends on the time that we
have to implement irrigation and amount of water available at a certain time to what we call flow
rate ( Q ) , a value that is expressed in L / hour, L / s or m3/hr .
In large irrigation projects with plenty of water availability, the number of irrigation sectors ,
depend only or available Fall Time ( td ) for irrigation operations .
So for example, if we have 6 hours per day to irrigate and water them every two days , we will
have 12 hours in total to water the whole lot. Then calculate the number of sectors of irrigation is
done with the expression.
Sectors = 6 hours x 2 days / 3 hours = 4 sectors , which means that according to our available time
and the run time must divide the batch in 4 irrigation sectors of equal size.
For our example , we want to water a lot with an area of 1mz , therefore: Sector Area : 1/4 = 0.25
acres, which multiplied x 7000 = 1,750 m2 , as shown in Step No8 instrument " Fto2 irrigation
Requirements " .
This means that on the first day will be irrigated two sections of 1,750 m 2 each, three hours of
irrigation applied in each sector and the second day will water the other 2 sectors to complete the
batch of irrigation (Figure No1 ) . The hydraulic design will be based on the size of the ego ri sector
10 . Small irrigation areas with limited water resources.
In small irrigation with limited water resources, the question is rather: how much water I can
surface with the water I have ?
Therefore, we need to know how many liters of water (volume ) we get in time ( T hours) we have
for irrigation , according to a known flow rate , which could be a dug well or spring . To determine
the volume employ the following formula: Vol x 3600 x = Q T, the volume is expressed in liters , Q
in L / sec. and T in hours.
In the case of our example the run time is T = 3 hours, and if we assume a flow rate of 0.5 L
hypothetical / s , we have:
Now we need to know the area that can be rega r with the previous volume , for which we use the
formula: Area = Vol / Lb ;
As we know volume 5,400 liters . and Step No5 Instrument " Fto2 irrigation requirements ," we
find the sheet br irrigation uta ( Lb = 6.6mm ) , we have:
Area = 5,400 / 6.6 = 818 m 2, which is the area of the sector that can be watered with this flow in 3
hours of watering .
Knowing this fact ( area of sector ) decide pray the few sectors agricult want to handle in a day and
thus know the total area that can be irrigated. In the case of the example, the farmer decides to 6
hours a day watering , so that two sectors can irrigate 818 m 2 each. The next day you can water
at the same time other two sectors of equal area , which could irrigate a maximum of 4 sectors of
818 m with an interval of two days irrigation , the irrigation der interval value is in Step 13 , the
Instrument " Fto1 General Information " .
In small irrigation systems often get first available volume and then estimate the surface irrigation
sector , but in larger systems we first estimate the number of sectors and from this value calculate
the surface irrigation sector therefore need to estimate the volume of water required to irrigate
each sector.
Q = Vol / ( Tx3600 ), where Q is flow rate in L / s , and Vol is volume in liters , T is time in hours .
This value represents the flow needed to supply a irrigation sector and from which the pipeline
will be sized to utiliz ar .
With this example we used the instrument " Fto 2 Irrigation Requirements " and is presented
below:
A. Objectives
Farmers (as) actively participate in the design process hydraulic irrigation network , knowing the
process and the design criteria for calculating the diameter and length of the pipes that make up
the irrigation system .
B. Pipe design .
For calculating the piping design tool is presented " FTO3 Piping Design " , which consists of 7
tablets ( F -3-1 : General, F-3 -2: Design
Lateral, F- 3-3 : Distribution Design PVC Pipe , F- 3-4 : Driving PVC Pipe , F- 3-5 : Losses in the head ,
F- 3-6 : Total manometric head ) in which organizes all the
information as follows : In the first column "Steps " presents the numbering of the process , the
second called " Description " describes the name of the calculation , the third called " Values "
shows the space to locate results and the fourth called " Instruments for Use " describes the origin
of the data and process calcul or .
1. F -3-1 : Overall
The first table named , F- 3-1 General , serves to sort the data from the instruments " Fto1 General
Information " and " REQUIRED Fto2 irrigation treatments " presented in sections 1 and 2 of this
manual. It aims to bring together in a single instrument all the data necessary for the design ,
which are located from step No 1 , to step No7 . Upon completion of the instrument F -3-1 , there
are two steps required whose values calculated , following described :
a) Number of issuers .
Estimated number of emitters by formul a: No emitters = Ll / from , where ( Ll ) is the lateral length
and (de) is the distance between transmitters . Thus, for our example we have: No = 48/0.30 = 160
emitters per lateral irrigation emitters .
b ) Number of sides.
Also one must calculate the number of sides of irrigation, which is done with the expression : No
Sides = Ld / dl , where ( Ld ) is the pipe length
distribution (dl) is the distance between side . Therefore, according to the example : No = 17/1.5 =
11 emitters irrigation side .
The instrument F -3-2 , intended to facilitate the calculation d lateral design irrigation . It describes
the operations, provides space for results and lists the procedures to be used . Also mentions
where to find the data to be used in the formulas , indicating whether they are in a manual pr
oduct in a table or required to obtain an arithmetic operation .
a) operating pressure .
Is the operating pressure of the drip tape , which usually ranges between 0.5 and 1 atm . , This
value is sought in the manufacturer's manual tape we previously selected based on soil type and
crop. In our case the tape is : Ty - tape , TSX 508-30-340 , the operating pressure is 5 mca, or about
0.5 atm .
This value is also obtained from manual tape manufacturer selected for the case study is 16mm .
c ) Design criteria .
Cr = Po x 0.20 , where
0.20 , is the pressure factor which allows the variation of the flow in the irrigation sector is 10 %
relative to the average flow .
In our example : Cr = 5mca x 0.20 = 1 mca . The design criterion expresses the maximum tolerable
pressure drop in the area of r iego , whose components are the sides ( drip tape ) and the
distribution pipe , also known as lateral slide . This implies that the sum of the pressure loss in the
lateral and in the distribution pipe must be less than or equal to the criterion set , as the present
example is 1mca .
However, the lateral design criterion (CRL) which is based on 55% of the value of the design
criteria ( Cr) should occur at the sides ( drip tape ) and the remaining 45 % must take place in the
pipe distribution and consequently gives the expression for the lateral design criterion (CRL) :
Par calculate this value , we need two pieces of information , the flow of the issuer and the length
of the lateral (tape). The first piece is in the instr ument "F - 3-1 , Step No. 3 " which is tape -tape
Ty , TSX 508-30-340 model whose emitter flow is 1 L / h . The following data is in the instrument "F
- 3-1 , Steps No 6 " , whose value is 48 m .
Then look at the table No1 " Hlf pressure drop ( mca ) x underground drip tape " and found in line
Ty -Tape TSX 508-30-340 , the flow is ( q = 1.02 L / h ) ; later, in the column to the right are the
lengths , where we seek the value 48m . If the value is not exact , we chose nearest 50m in this
case , to the right of this value is the data flow of the tape, which in this instance is Q = 170 L / h.
Thus we obtain the result of the "F - 3-2 , Step No 5 " .
Always in Table No. 1, with the result of Step No 5 , Q = 170 L / s , will be looking at the row
corresponding to flow above and then in the last column , we find the value of lost load, which for
the example is : hfl = 0.1406 mca, this value is compared with the design criteria ateral ( Crl )
Whereas the value of lost load is ateral mca hfl = 0.1406 , a result that is less than the lateral
criterion expressed as ; 0.1406 < 0.55 , we conclude that the pressure drop on the side are
satisfactory for design.
But if the criterion is not met , re- perform the procedure with the same length reducing or
increasing the dia meter of the tape. Fig.No2 arrangement , halved lateral length or tape ,
increases twice the number of connections to the distribution pipe , while maintaining the same
flow to the irrigation sector . Hydraulically is benefic ioso because lower lateral length corresponds
to lower pressure losses , the greater the number of connections in the distribution pipe creates
less pressure drop therein.
Hfl , is the pressure drop ( MCA ) on the side, the value of the example is hfl = 0.1406 mca .
Z = 0, is the slope of the land ( m ) , our case the terrain is flat .
Like this: Hlo = 0.1406 + 5 + 0.77X 0 = 5.11 mca, value that is located in F- 3-2 , Step
Fig No 1 fig No 2
Q = 1.04 L / s Driving
Q = 1.04 L / s
distribution
Q = 0.52L / s
Q00.52L / s
L = 17m
L = 17m
Lateral or tape
Lateral or tape
Q = 170 L / h
Q = 85 L / h ,
L = 48m
L = 24m
This instrument seeks to facilitate the calculations for the design of the distribution pipe and like
previous instruments , has a description of the steps , calculation result space for ado and
description of instruments used for the calculations.
This design criterion distribution pipe " Crd " , is obtained by subtracting the design criteria ( Cr) ,
the value of the loss of the lateral decarga ( hfl ), obtaining the following expression :
Cr is design criterion .
We obtain :
Q = No Side x Ql / 3600 .
where ;
No sides are the sides of the irrigation sector . For example 11 side (F-3 -
1: General , step No 9 )
Ql is the flow rate (L / h) or lateral irrigation drip tape . For example, 170 L / h
c) Christianssen (F).
This value is a factor that estimates the effect of multiple discharge outlets in the distribution pipe
because of the connected side , that gradually causes the inlet flow in the pipe is reduced as this
progresses along thereof, the side -fed irrigation so that the end of the pipe the flow is only a
fraction of the initial flow .
The coefficient value is in the table No5 called Christianssen F values , which depends on the
number of lateral them (n ) connected and hydraulic regime ( m ), which for polyethylene (PE ) is
1.75 , for PVC is 1.80 and aluminum is 1.90.
For our example the number of side ntramos gluing it in the instrument F- 3-2 , Step No. 9 , whose
value is n = 11; also be used as PVC pipe , the hydraulic regime is m = 1.80. With these two data we
are located on the first column and look for the value 11 , then right locate the column m = 1.80 ,
at the intersection of the row with the column mentioned Christianssen find the value , which in
our example is F = 0.404 , and placed in the instrument F- 3-3 , Step No3 .
d ) Estimation of J unit loss
In this case the design criteria of the distribution pipe (Crd ) equals the pressure drop in the
distribution pipe ( Hfg ) , ie the data of step 1 No F -3-3 is the value of loss load distribution pipe as
shown below.
After Chistianssen factor as we know it is in F- 3-3 No3 step in our example is F = 0.404 , we
estimate the pressure drop per meter J , value to be used to estimate the diameter of the pipe.
Thus the pressure drop per meter ( J ) is given by the expression: J = HFD / L / F where ;
HFD is the pressure drop along the distribution pipe , which for our example mca HFD = 0.8594 .
The diameter of the pipe will be looking at the table No 3 , for which the flow rate using step # 5,
F- 3-2 and the pressure drop per meter ( J ) , a finding that is in step no 4 (F-3 -3). In our example
the diameter of 1 inch ue f with Q = 0.50 L / s and J = 0.0213mca .
Step above refers to the pressure drop per meter of pipe (J) which in our example J = 0.0213mca ,
and occurs with a diameter of 1 inch PVC pipe with a flow of 0.50 L / s, is now needed knowing the
pressure drop ( Hfd ) across the path of the pipeline, for which we must know the length of the
pipeline, data whose value is of 17m and is in the F-3 -1, Step No 6.
Hfd = J x L , where ;
Hfd = 0.0213 x 17 = 0.3621 meters head . This value is located in the F- 3-3 ,
g ) Pressure drop distribution pipe taken into account the lateral outlets Hfd ' .
Now it will be necessary to multiply carg loss to the value of Christiansen, Step No. 3, F-3 -3 (F =
0.404 ) , and thus obtain the value of the load loss Hfd ' , the expression is : hfd '= Hfd x F , where
Hfd ( mca ) is the loss of load , F , is the value Christianse ; now , applying the formula to our
example, we get:
Hfd '= 0.3621 x 0.404 = 0.1463 mca, value that is located in the F-3 -3, No7 .
Finally, the result Hfd '= 0.1463 mca, compared to 0.8594 mca design criteria , because the
pressure drop of the distribution pipe is less than the criterion set , 0.1463 < 0.8584 , this result is
accepted. However if not accepted , it starts the process again by changing the diameter of the
pipe to a larger diameter.
This instrument "Table F-3-4", helps to design pipelines. It describes step by step the results and
the means or aids to use.
This is obtained from the sketch or plan of the plot which in our case is 30 m. This value is located
in F-3-4, Step No 1.
Step No 2.
It is considered that the allowable pressure drop in the pipe line must be equal or less than 2% of
the length of the pipe or the speed is less than 2.5 m / s. Thus the pressure drop in the pipe line
will be:
Crc hfc X = L, where;
L (m) is the length of the pipe. For our case is 30 m.
Crc is design criteria driving pipe, whose value is 2% or 0.02.
hfc is the pressure drop of the drop pipe.
Substituting for our example,
hfc = 30 x 0.02 = 0.6 m, and the value is located in the F-3-4, Step No 2.
Now we must find the head loss (J) in one meter of pipe, which is done with the following
expression:
J = hfc / L where;
J, is the pressure loss in piping 1M.
hfc is the pressure drop along the pipe, in the example is 0.6mca .
L is the length of the pipe, is in this case 30m .
J = 0.60/30 = 0.02 mca, this value is located in step # 3.
Step No. 4
Now , supported by the instrument table No 3a, finds the approximate value of the design flow ,
which is an instrument Fto No 2 , step # 10, the case of the example is , Q = 1.07 L / s , then the
first column of the table No 3a, select the flow rate in the example is 1.0 L / s , then right on the
line look for the value of lost load using the data from step No 3 , F- 3-4 , which in the example is J
= 0.02mca , from there , on the top of the column found the Dia ro of tunera , that our case
corresponds to PVC pipe 1 "with this diameter , the unit-load loss is 0.0116 J = mca / m , which
is the closest value to J = 0.02mca , which is the allowable pressure drop in the pipeline. This value
of the diameter PVC 1 " , is located in the F- 3-4 , Step No4 .
Step No5 .
Estimating the pressure drop is achieved with the expression : Hfc = J x L , where ;
J is pressure drop per meter , step No. 4, F -3-4 , load loss corresponding to the diameter and flow
rate, which in the example is 0.0116 mca / m for a flow rate of 1 l / s and a diameter of PVC 1 "
L is the length of the intake pipe , which in our case is 30m and the data is in No1 step of this
instrument ( F- 3-4 ) .
It turns out that replacing:
The value of the load loss Hfc , No5 step F -3-4 , compares and drinks to be less or equal to the
allowable loss , step # 2, F -3-4 , in the example the pressure drop was 0.348mca ( No5 step of this
instrument) and is less than the criterion whose value is 0.6mca ( No2 step of this ), so : 0.348 <0.6
, the result is satisfactory according to the criteria , which signific the diameter PVC 1 " is
suitable for driving.
g ) Required pressure at the exit of the head, F- 3-4 , Step No7
This value comes from the accessory manual , in our case a filter rings, operating pressure 2 mca .
The datose located in the F- 3-5 , Step No 1.
Similar to the above , the operating pressure is in the manual of the device , which in our case is a
venturi injector for operation whose pressure is 5mca . The data is placed in F- 3-5 , Step No 2.
The losses in valves are in Table No. 6, however, to know the value of them , we place the value of
No2 step design flow , F , 3-1 , in the first column of the table , which in our example is Q = 1.07 L /
s , then locate the group of columns that make up the type of valve area , which in our case is erta
compu valve , then in that area we move to the right on the row selected flow , to find the
diameter of the valve, which in our case is 1 " . The resulting from this operation is the load
loss value Ha = 0003. mca . This data is placed in the F- 3-5 , Step # 3.
The loss in the irrigation head is the sum of local losses of the various accessories that make it up,
which in this case are: filter, venturi injector valve. The resulting value is mca Hoc = 7.00 3 and
represents the head loss in the sprinkler head .
Finally estimated pressure at the inlet of sprinkler head , which is done with the expression:
In our case according to the sketch , the length of the pump to the head is 10m and we will
network segment with PVC pipe 1 "for the pipe will pass a flow of 1.07 L / s according , see the
F-3 -1, Step No2 .
Since we know the flow and diameter , now b uscamos the value of the pressure drop in Table 3a
No , locating in column flow, No2 step , F- 2-1 , with approximate value in our case 1 L / s , then
look for the diameter , step No 4 , F- 3-4 , which in our ejemp it is 1 " , from which results a value
of J = 0.0116 unit loss mca / m .
J , pressure drop per meter ( mca ) , Step No1, F- 3-6 . In our case , J = 0.00116 mca / m
L is the pipe length (m). See sketch , in our case is 10m .
solving :
Hf1 = 0.0116 x 10 = 0.116 mca, this value we place on the F- 3-6 , Step No2 .
c) 3 . Total head .
Hc = the pressure required at the inlet of the head, step No 5 , F- 3-5 , which in our case is 12,573
mca
Hf1 = is drop the head pump , No2 step , F- 3 to 6 , in our case 0.116mca .
Z = 0 m, is the level difference .
Thus calculating: Hm = 12.573 + 0.116 = 12.689 +0 mca, approximately 12.69mca .
7 . Pump Selection F-3 -7.
This picture is the last of the instrument FTO3 , and tr ties to help select a pump , this will use the
Step No 2 , F- 3-1 , which is the flow rate ( 1.07 L / sec . ) The result is placed in step No. 1, F- 3-7 .
The total pressure , step No. 3, F- 3-6 , which in our case is ( 12.69 mca ) , is located in step No. 2,
F- 3-7 .
With these data we analyze the HQ curve present in the pump manual . In our case was a
centrifugal pump model HONDA WX10K1 laptop with suction and outlet diameter of 1 " . Notethat
for the flow rate of 1 L / s is 27 meters head pressure about 38 PSI , which indica that the pump
should be operated at half throttle or look for a smaller one. If not fertirriega height will be 7.7
meters head gauge with the same pump that produces pressure 2 L / s , so it could irrigate twice
the area w hile not fertilize .
Curva H-Q
Fto No 3: PIPING DESIGN
F-3-1: General
Q = 0.52 l/s;
ajustado a 0.50
J=0.1251
Valor encontrado
en la tabla 3a:
Dimetro = 1
Pulgada,
Cuando J=0.0213
6 Prdida de carga en la Hfd= 0.0213 x EL valor (J) del Paso 4, se multiplica por
tubera de distribucin. 17m =0.3621mca la longitud de la tubera paso 7 F-3-1 y
Hfd= J x L (m) as se obtiene la prdida de carga de
tubera de distribucin.
7 Prdida de carga en la Hfl=0.3621 El Paso 6 (Hfd) y el Paso 3 (F) del
tubera de distribucin x0.404= 0.1462 presente cuadro se multiplican.
tomado en cuenta las mca
salidas de laterales
Hfd(mca) = Hfd x F
(Christiansen)
8 Evaluacin del Paso 0.1462 < 0.8584 El valor Hflpaso no 6 del presente
Aceptado instrumento debe ser igual o menor al
criterio de diseo de la tubera de
distribucin, paso no 1 del este
instrumento.
9 Presin en el origen de Hdo = 5.11 + 0.77 Hlo, dato que se encuentra en el
la tunera de distribucin. x 0.1462 = 5.22 instrumento F-3-2, paso No8. Y Hfd se
Hdo=Hlo+0.77xhfd+- mca. encuentra en presente instrumento paso
dZ/2 no 7.
2 Prdida de carga desde la Hf1 = 0.0116 x Prdida unitaria (J) Paso No1
bomba al cabezal (Hf1). 10 = 0.116 mca del presente instrumento y
plano con longitudes de
Hf1= J x L tuneras.
2 Altura manomtrica total (mca) 12.69 Este dato esten Paso 3 del
cuadro F-3-6