EIU Renewable Report PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

A report by The Economist Intelligence Unit

POWER UP
Delivering Renewable
Energy in Africa

Commissioned by:
Power Up: Delivering renewable energy in Africa

Contents
Glossary of terms 2

About this research  3

Executive summary 4

Key findings  6

Powering African renewables 8

Greening African power: The view from corporates 15

Nigeria: Brightening Africas biggest economy 18

Programmes or projects? 20

Uganda: Going Solar 23

Zambia: Relying on the rains 24

Africas bespoke grids, and the innovators driving the market 27

Conclusion30

1 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Glossary of terms

Off-taker Micro-grid
The buyer of power produced by a given power A small-scale power grid that can operate
generation asset. independently of the main electrical grid. It can
be used for both on and off-grid purposes.
Power purchase agreement
A contract between a power supplier and the Feed-in tariffs
purchaser of power. A PPA typically sets the A payment made to energy producers generating
commercial terms between the two parties, electricity from renewable energy sources,
including duration of contract, payment terms, usually proportional to the amount of electricity
transmission issues, timeline for delivery, generated.
penalties for non-compliance, and credit and
insurance terms. Transmission and distribution system
Transmission systems transport high quantities
Renewable procurement programmes of power - usually through overhead lines,
Policy programmes aimed at securing a given underground cables - to substations, and connect
capacity of power production from renewable power generators to the distribution network
energy. which delivers power to users.

Off-grid power
Power produced independently of the power
grid. Examples include solar home systems.

2 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

About this
research

Power Up: Delivering renewable energy in Africa is an l Alex Rugamba, director, energy, environment and climate
Economist Intelligence Unit report on renewable energy change, African Development Bank
infrastructure in Sub-Saharan Africa, with a focus on solar
l Damilola Ogunbiyi, general manager, Lagos State Electricity
and wind. Findings are based on desk research and expert
Board
interviews and the report includes fieldwork in Nigeria, Zambia
and Uganda. The Economist Intelligence Unit would like to l Aubin Kalaidjian, founding partner, Greenwish Partners
thank the following experts for their time and insights: l Batchi Baldeh, head of power, Africa Finance Corporation
l Andrew Johnstone, chief executive officer, Climate Fund l Abayomi Adebisi, Nigerian Federal Ministry of Power
Managers
l Jorge Lopez Galera, Access Power engineer on-site, Soroti,
l Dr. Tobias Bischof-Niemz, head of energy research at the Uganda
Council for Scientific and Industrial Research (CSIR), South
Africa l Dolf Gielen, director of the Innovation and Technology
Center at IRENA
l Alastair Campbell, managing director, Vantage GreenX
l Michael Obale, agriculture graduate, Gulu University,
l Benjamin Warren, global power and utilities corporate Uganda
finance leader, EY
l Nils de Baar, president for central europe, Vestas
l Dario Musso, senior transactor, infrastructure finance, Rand
Merchant Bank, South Africa l Peter Nyeko, renewable energy developer, Mandulis Energy

l Rentia R. Van Tonder, head, Power, Corporate and l Jasandra Nyker, CEO, Biothern
Investment Banking, Standard Bank l Sipho Phiri, executive chairman, Western Power
l Reda El Chaar, executive chairman, Access Power MEA l Owen Silavwe, managing director, Copperbelt Energy
l Nico Tyabji, senior associate, Bloomberg New Energy Finance Corporation

l Christophe Fleurence, vice-President, business l Charles Mate, executive director of corporate affairs, IDC
development, Africa, EREN Renewable Energy
Dr Elie Chachoua was the author of the report. Eleanor
l Timon Herzog, chief operating officer, Global Renewable Whitehead, Will Pearson and Michael OHagan contributed
Independent Power Supplier (GRIPS) reporting and fieldwork. Melanie Noronha developed data
l Georgios Pergamalis, head, business development, Africa visualisations. Adam Green was the editor. This research was
and Middle East, Enel Green Power commissioned by IHS Towers, the largest provider of mobile
towers in Europe, Africa and the Middle East, in support of
l Phylip Leferink, general manager, Lake Turkana Wind Power Africas renewable energy goals.
Ltd.
l James White, senior manager, business development, The Economist Intelligence Unit bears sole responsibility for
SunEdison South Africa the content of this report. The findings and views expressed in
the report do not necessarily reflect the views of the sponsor.
l Henning Wuester, director of knowledge, policy and finance,
International Renewable Energy Agency

3 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Executive
summary

Following high-level declarations at the affordable power to rural regions beyond the
Sustainable Development Goals and the Paris reach of the grid system.
Climate Conference in late 2015, there is a
growing appetite for renewable energy in But to harness renewables at scale, very
Africa. This is much-needed; the continents significant infrastructure is needed: both
energy supplies are not meeting the needs core assets like wind and solar farms1 and
and aspirations of its people. A better system transmission grids, as well as connective
will promote economic diversification, raise infrastructures, like roads to and from sites for
productivity, and improve the health and transporting kit and manpower, or for bringing
wellbeing of citizens. products, like solar-powered mobile phones,
to market. This requires effective regulation,
Africa requires between $60 and $90 billion sufficient financing, appropriate technologies
annually to address its energy shortfall, roughly and smart business models.
quadruple 2014 investment levels. While fossil
fuels, notably coal, oil and gas, continue The ambitions are there. The African Renewable
1
This report focuses Energy Initiative, led by institutions including
to provide a significant quantity of energy -
primarily on solar and the African Union and the United Nations
especially in South Africa - renewables need to
wind energy, the resources
play a greater role. Environment Programme, has set a goal of
most widely available
and technically feasible 300 GW of renewable energy capacity by 2030.
from an infrastructure Africa has plentiful resources, from geothermal But this requires a 680% increase in current
standpoint, given Africas power in Kenya and Ethiopia to hydropower in deployment rates. According to IRENAs latest
grid systems. These are Zambia and the Democratic Republic of Congo. data, the installed renewable power generation
also the renewable sources Solar and wind are especially promising, thanks capacity in Sub-Saharan Africa currently stands
attracting the majority
to falling costs and resource abundance. From slightly below 30 GW, roughly 25-30% of the
of investment globally
and solar, in particular, solar-powered hospitals in Lagos to wind farms in installed power base, but this is dominated by
is set for rapid growth. It Lake Turkana, renewable energy is not just a pipe large hydro, with other renewables collectively
excludes large hydroelectric dream - it is a reality. Renewables can increase accounting for just 4-5% of power generation.
projects, the infrastructure energy security, reduce energy import bills, and
dynamics of which can diversify and de-risk the energy mix. Through Can the investment be achieved? Who are the
be idiosyncratic, and not current players and how is the market evolving?
off-grid technologies, they can provide direct,
necessarily feasible for most
countries.

4 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Which strategies are most successful, and what dynamics in Africa today, focusing on solar
challenges do developers face? This report, and wind and outlines the strategies employed
combining expert interviews with country by developers, corporates, governments and
fieldwork, assesses renewable infrastructure international partners.

Sub-Saharan Africas power generation


(GW)
Renewables Nuclear, 1.9
(excl. Large hydro), 4.1

Oil & Diesel, 6.5 2%


5%

8%

16%
Natural Gas, 12.3 49% Coal, 39.0

20%

Large Hydro, 16.3

Source: Climate Scope 2015. Data for 2014. Tracks 80 GW in Sub-Saharan Africa.

5 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Key findings

The sun is shining on African renewables. investment, power tariffs must reflect costs.
Falling technology costs, ambitious targets, Targeted subsidies to protect the poor can help
resource abundance, a pipeline of high-quality improve access to power without deterring the
projects, and the support of international donor private sector from investment.
partners are driving the rollout of renewable
power in Africa. Countries can look to positive Transparency and harmonisation are essential
experiences in lead markets like South Africa and for investors. Governments should publish key
Kenya for strategies and best practices. planning documents, like Integrated Resource
Plans, and introduce bankable and harmonised
Like mobile communications in the late 2000s, legal documentation including PPAs (power
Africas power sector can leapfrog heavy purchase agreements), Government Support
infrastructure. Africas green power sector Agreements, and Connection Agreements.
resembles mobile communications a decade ago. Africa also needs strong, independent energy
There is a large pool of African consumers able regulators that enforce competitive procurement.
to buy power but simply lacking appropriately
priced and designed options. Leapfrog Improve border customs efficiency. To utilise
strategies are emerging in rural regions, where renewable technologies, landlocked African
electricity is delivered without heavy, clunky nations must improve supply chain efficiency
infrastructures. Innovative pay as you go so developers can quickly move equipment and
contracts, affordable technologies like pico-solar replace parts like panels and turbines. Faster
units, and remote utility management software, customs processes are vital to achieve this.
are smart alternatives to the conventional
Countries should design competitive
grid approach. In rural regions, off-grid power
renewable procurement programmes, rather
generation could create an entirely new type of
than relying on one-off investments. While
bottom-up network as island grids gradually
investors occasionally pursue one-off projects,
become interconnected. As with mobile in Africa,
government-backed renewable procurement
the key will be smart business models, not just a
programmes are more likely to attract long-
reliance on cheapening technology.
term investment. Following South Africas
Governments must implement cost-reflective lead, Uganda and Zambia are emulating the
tariffs based on publicly available cost of programmatic approach: other countries
service studies. To attract infrastructure could do the same. Transparent, standardised,
6 The Economist Intelligence Unit Limited 2016
Power Up: Delivering renewable energy in Africa

and competitive programmes reduce risks for also have the technical capacity to make it
developers, and costs for governments. They happen. Improving the fiscal conditions of
signal long-term policy commitment to green national energy off-takers, and implementing
energy and build local expertise. well-designed, standardised power purchasing
agreements, are of critical importance here.
Ambitious targets are not enough: investors Developers also pay close attention to a countrys
are also looking at whether governments infrastructure track record and the relationship
have the technical capacity to deliver: The between its renewable energy goals and its actual
majority of Sub-Saharan African countries economic needs.
have the ingredients to make renewable energy
infrastructure viable, and over half have explicit
renewables targets. But those moving fastest

7 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

1 Powering African renewables

Last year was bright for the global renewable speed, distance, and altitude) as it flew across
energy industry. Investments in clean energy the Pacific powered by the sun. The same week,
reached their highest level yet ($329bn, SunEdison Inc., a US-based clean energy
excluding large hydropower, according to developer, filed for bankruptcy. Clearly, ramping
Bloomberg New Energy Finance), and net up renewable energy is as much about business
capacity additions in wind (60GW) and solar models as technologies.
photovoltaic (56 GW) surpassed deployments
in new coal (42GW) and gas (40 GW) power Africas place in the sun
generation.2 Sub-Saharan Africa is yet to fully harness
renewables on a continent-wide scale. Its power
This figure is over five times the 2004 investment
supply is failing to keep up with peoples needs.
total, according to BNEF, showing the remarkable
Hospitals and schools go without lights or
distance that renewable power has come in little
equipment, and at home families huddle around
over a decade. Last year was also the first year
polluting, dangerous kerosene lamps. Job-
developing countries out-invested developed
creating services and manufacturing industries
ones, after marked increases in China, Latin
cannot emerge due to intermittent power
America, Africa and India.3 And with developing
supplies. Each year, the average Sub-Saharan
countries as a whole expected to drive future
African manufacturing firm loses 5.5% of annual
energy demand growth and renewable energy
sales due to power outages, over double the
costs on the decline, that trend is expected to
global average (2.6%). Nigeria has nearly 33
continue.
outages a month; the average duration is 8
2
Source: UNEP 2016.
Growth was particularly marked in Mexico hours, according to the World Bank.
3
Source: UNEP 2016. (114%), Chile (157%), South Africa (329%) and
Overall, almost 600 million people in Sub-
Morocco, which saw $2 billion investment from
Saharan Africa lack access to electricity.
4
See Bloomberg Visual zero in 2014 according to BNEF data.4 These
According to McKinsey5, only seven countries
Data, available on bnef.com investment figures are more remarkable given the
Cameroon, Cte dIvoire, Gabon, Ghana, Namibia,
historically low oil and gas prices of late, and the
Senegal and South Africahave access rates
5
Brighter Africa: The sluggish growth in emerging markets. That said,
growth potential of the sub-
above 50%. The rest have an average grid access
this is also an industry in flux. In mid-April, Solar
Saharan electricity sector, rate of 20%. Outside of South Africa, average
Impulse 2 broke several world records (including
McKinsey, February 2016.
8 The Economist Intelligence Unit Limited 2016
Power Up: Delivering renewable energy in Africa

Figure 1: Grid electricity prices by end-use sector in selected countries, 2013


(US cents per kWh)
Residential Services Industry Average cost of generation by region
50

40

30

20

14 cents/kWh
10 11 cents/kWh
9.5 cents/kWh
5.5 cents/kWh
Ethiopia

Kenya

Rwanda
Cote dIvoire
Nigeria

Ghana

Cameroon

DR Congo

Gabon

Zimbabwe

Tanzania

Angola

Mozambique
South Africa
West East Central Southern
Source: IEA 2014

Figure 2: Average cost of wind and solar in South Africa, according to bids submitted
during the first four rounds of the REIPPPP
(Average tariff in US cents)
Solar PV Wind
30.0
28.7
25.0

20.0
17.1
15.0
11.9 9.3 9.2
10.0
Coal/gas new build option 6.9
5.0 6.8
5.4
0.0
Bid Window 1 Bid Bid Window 2 Bid Window 3 Bid Window 4
(4 Nov 2011) submission (5 Mar 2012) (19 Aug 2013) (18 Aug 2014)
dates
Source: CSIR, 2015.

9 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

electricity consumption is about 150 kilowatt- explained: The country has a strong grid, a
hours per capita, a fraction of consumption rates deep and sophisticated financial market in local
in Brazil or India. If such trends continue, in 2030 currency and a credit worthy off-taker. The rest
there will still be 655 million people in Africa of the continent is less advanced. But, as this
(42% of the population) without access to power report argues, South Africa provides a beacon
according to IRENA6. for other countries to look to. Some are already
following its example.
Renewable energy can help: Africa has abundant
solar, wind, and geothermal resources, to name
Renewables: The new mobile
a few. Solar PV alone could provide more than
revolution?
8TW, according to McKinsey data. By way of
Global technology cost trends are proving
comparison, total capacity installed in the Sub-
a helpful tailwind. According to BNEF, the
Saharan African region stood at 97 GW in 2012,
levelised cost of wind power generation is now
including fossil fuel generation.
half what it was in 2009, while the cost of Solar
Governments are engaged, say interviewees PV modules has fallen by 80% since 2008, on
in this report, especially if they are energy- average. On a $/kWh basis, Solar PV and wind
importers. Nearly 40 African countries have power are the cheapest new-build options in
introduced renewable energy targets in the last South Africa today...even cheaper than new
10 years and there are now more than 100 GW of coal, says Dr. Tobias Bischof-Niemz, head of
renewable energy projects in the pipeline says energy research at the Council for Scientific
Dolf Gielen, Director of IRENAs Innovation and and Industrial Research (CSIR) in South Africa,
Technology Center. There is a real openness to referring to the average bids under South Africas
renewable energy in Africa, adds Nils de Baar, Renewable Energy Independent Power Producer
president for Central Europe at Vestas, a global Procurement Program (REIPPP). Africa holds the
market leader, with wind farms in Cape Verde (28 world record of the cheapest bid for electricity
MW), Egypt (79 MW), Kenya (12 MW), Morocco from wind power generation, at $3c/kWh8, and
(50 MW) and South Africa (350 MW). Vestas is has world leading renewable resources. Lake
also constructing the 310 MW Lake Turkana Wind Turkana wind farm, for instance, has one of
Power project in Kenya, which will be the largest the highest load factors in the world due the
wind power plant in Sub-Saharan Africa when powerful wind resources on the site.
completed. We see significant potential for
Falling technology costs reminds some experts
developing wind power in Sub-Saharan Africa,
of the mobile phone sector in previous years.
6
Africas renewable says de Baar. Africa can be the continent that
Benjamin Warren, global power and utilities
energy future: The path achieves the highest contribution of renewable
to sustainable growth,
corporate finance leader at EY, said: For me the
energy.
International Renewable best analogy is the telco market where it seems
Energy Agency. Yet, while Africa has seen a near 60% increase technology was available and affordable.
in renewable energy capacity over the past there is no reason why that cant be the same
7
From 23 GW in 2000 to 36.7 with energy. In fact, the technology is probably
GW in 2015 (including large 15 years7, its relative share of global installed
renewable energy capacity has actually dropped evolving as quickly, if not quicker, than in the
hydro) according to IRENA
2015 from 2.7% to 1.8% over the same period, mobile telephone market.
according to IRENA. In Sub-Saharan Africa,
8
This was the lowest bid A second helpful tailwind is the significant public
in Moroccos latest rounds nearly 60% of the 1.8 GW net capacity additions
support for renewables, from Power Africa (led
of auctions for 850 MW. A in last year (large hydro included) was installed
by USAID) to the African Renewable Energy
bid does not guarantee the in South Africa, as Dario Musso, senior transactor
project will get delivered at
Initiative (AREI), an African-led initiative that
of infrastructure finance at Rand Merchant Bank,
this cost. aims to deploy 10 GW of renewable energy by

10 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Top renewable energy markets in


Sub-Saharan Africa by installed capacity
1. South Africa
RE Installed Capacity MW RE Share

1,989 4%

11 3
4% 55% 29% 13% 9
4 2
6
8
2. Kenya 3. Ethiopia
10
RE Installed Capacity MW RE Share RE Installed Capacity MW RE Share 5 12
719 33% 416 18% 7

14% 3% 7% 75% 30% 41% 27% 2% 1

4. Uganda 5. Zambia 6. DR Congo


RE Installed Capacity MW RE Share RE Installed Capacity MW RE Share RE Installed Capacity MW RE Share

154 17% 131 5% 115 4%

43% 57% 70% 30% 92% 8%

7. Zimbabwe 8. Rwanda 9. Sierra Leone


RE Installed Capacity MW RE Share RE Installed Capacity MW RE Share RE Installed Capacity MW RE Share

96 5% 89 63% 89 40%

23% 77% 90% 10% 64% 36%

10. Malawi 11. Nigeria 12. Mozambique


RE Installed Capacity MW RE Share RE Installed Capacity MW RE Share RE Installed Capacity MW RE Share

88 24% 62 <1% 58 2%

78% 1% 21% 100% 100%

KEY
Source: Climatescope 2015
Hydro RE = renewable energy
Solar Wind Bioenergy Geothermal
(<50MW) Blue bars represent installed capacity,
measured relative to South Africa

11 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Renewable energy roadmap to 2030


Breakdown of renewables in total energy mix, by region,
and required forecast to 2030 to meet energy goals
SHARE OF RENEWABLES SHARE OF RENEWABLES SHARE OF RENEWABLES
WEST (excluding hydropower)
CENTRAL (excluding hydropower)
EAST (excluding hydropower)

2013 2030f 2013 2030f 2013 2030f

2% 15% 3% 36% 14% 28%

Cumulative investment in RE Cumulative investment in RE Cumulative investment in RE


required 2015-2030 required 2015-2030 required 2015-2030
Breakdown by type 2030f

Breakdown by type 2030f

Breakdown by type 2030f


59% US$13bn
71% US$36bn 70% US$36bn

10%
1%
9% 9%
US$17bn 14%
3%
3% US$31bn US$21bn
23% 11%
14%
3%

T&D US$52bn T&D US$14bn T&D US$49bn

SHARE OF RENEWABLES
SOUTHERN (excluding hydropower)

2013 2030f

1% 23%

Cumulative investment in RE
required 2015-2030
Breakdown by type 2030f

50% US$18bn

27%

US$94bn
18%

5%

T&D US$74bn

KEY

Hydro Solar PV CSP Wind Geothermal Biomass Transmission Source: IRENA


& Distribution
12 The Economist Intelligence Unit Limited 2016
Power Up: Delivering renewable energy in Africa

2020, reaching 300 GW by 2030. Against the Meeting these targets requires policy and
backdrop of the Sustainable Development Goals investment frameworks reflective of the realities
(SDGs), which aim to provide universal access to of deploying renewable energy infrastructure.
affordable energy by 2030, and the Paris Climate Importantly, these will be unique to the markets
Change Agreement, which aims to achieve a net and contexts, and developers should re-assess
zero carbon global economy by 2050, there is no their pre-conceived notions of what constitutes
shortage of ambition. a necessary environment for renewable energy.
The development of renewable energy in Africa
But, between ambition and reality, there is a will not follow the pure textbook that has been
sizeable gap. Delivering 300 GW of renewable forged by the more entrenched markets of the
energy capacity by 2030 requires a 680% increase developed world, says James White, senior
in current deployment rates. The 300 GW is manager for business development at SunEdison
entirely achievable, but it will require more South Africa.
support from governments and institutions
across Africa says Dolf Gielen, Director of
IRENAs Innovation and Technology Center.

13 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Upcoming renewable energy projects* in Sub-Saharan Africa


*excluding hydropower projects

BURANGA GEOTHERMAL
POWER STATION
Uganda
100MW
US$42m AYSHA WIND FARM
Planned Ethiopia
2020 300MW
US$502m
Planned
N/A

LAKE TURKANA WIND POWER


Kenya
310MW
US$700m
Under construction
2017

NZEMA SOLAR
Ghana KIPETO WIND FARM
155MW Kenya
US$350m 100MW
Planned US$300m
2017 Under construction
2017

KHOBAB WIND FARM SINGIDA WIND FARM


South Africa Tanzania
140MW LOERIESFONTEIN 2 WIND FARM 100MW
Approx US$230m South Africa US$285m
Under construction 140MW Planned
2017 Approx US$230m 2017
Under construction
2017 KEY

Wind

REDSTONE SOLAR THERMAL POWER Solar


South Africa
100MW Geothermal
Approx US$715m
Under construction Expected
launch
2018 date
14 The Economist Intelligence Unit Limited 2016
Power Up: Delivering renewable energy in Africa

2 Greening African power: The view


from corporates

At its core, a renewable energy infrastructure The level of electricity tariffs can also be
project is a capital-intensive endeavour where problematic. In a recent survey of African power
most costs are incurred up-front in the form of utilities by PwC, two-thirds of respondents
capital expenses while operational costs are admitted to not being able to recover the cost of
low, as there is no cost of fuel. Thermal power new power generation via existing tariffs. Only
plants, on the other hand, might have lower a handful of countries have moved towards cost-
capital expenditure but higher operational costs. reflective tariffs.
This changes cash-flow profiles and thus the
Many utilities also face challenges in bill
investment dynamics.
collection. This results in off-takers having weak
For renewable energy, says Dr. Bischof-Niemz, balance sheets, as in Nigeria. Distribution
certainties about the tariff (the price to be paid companies are financially distressed at the
for the power generated) and about the off-taker moment says Andrew Johnstone, CEO of Climate
(certainty that the buyer of the power will take all Fund Managers. Theyre not achieving their
of it) are critical. The market structure doesnt target loss ratios and youve got shareholders
matter; you still need these two certainties. If and financiers who are under pressure due to
you dont have them, you might still deploy the slowing down economies, low oil prices, and no
project but at higher than necessary costs - thats hard currency; the whole market is just in a very
just inefficient and creates windfall profits during difficult place at the moment.
the latter part of the lifetime of the asset.
Given this context, investors and funders
Both factors are challenging in Sub-Saharan want to make sure there is a move towards a
Africa. In many countries, the off-taker (such as cost-reflective tariff-regime says Rentia Van
an industrial user or utility) risk - the risk faced Tonder, head of Power, Corporate and Investment
by the power producer as a result of the buyer banking at Standard Bank. The majority will also
not paying or not taking the power - is high. The look to the public sector for guaranteeing Power
practical reality on the African continent is that Purchasing Agreements (PPAs). Its almost
you cant simply sell the power into the grid or to impossible to bank a long-term PPA in Sub-
a third party buyer if theres a default from your Saharan Africa without a government guarantee
original buyer says Alastair Campbell, Managing says Musso.
Director at Vantage GreenX, a renewable energy
The challenge is that most African countries
fund in South Africa.
are unable to provide the required long-term

15 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Key stakeholders in Africa's renewable energy sector

Equipment
Project developer manufacturers Power off-taker

Multilateral
development banks Foreign donors Banks

investment certainty on their own. This is projects involve importing equipment such as
where development financial institutions (DFIs) turbines or panels from overseas.
come in, says Dr. Bischof-Niemz. They can
help de-risk the PPAs he adds. Recent examples Investors may need to build infrastructure to
include Ugandas GetFit program, and Zambias transport equipment, more so in Africa than
partnership with the IFCs Scaling Solar other regions. The Lake Turkana wind project,
program. led by a consortium including Vestas, Aldwych
International, KP&P and Standard Bank,
Then come financing challenges such as currency required 208 km of road from Laisamis to the
risk - a particular problem recently, in the site. Construction, which took about a year, also
likes of Nigeria - and the costs of debt, as well influenced the choice of equipment. One of
as logistical challenges affecting imports of the reasons we ended up going for smaller wind
products. Inter-border customs can be prone turbines is that they are a lot easier to bring into
to extensive delays, which can create additional the area than some of the newer - but larger -
bottlenecks, says Reda El Chaar, Executive turbines, says Phylip Leferink, general manager
Chairman of Access Power. Many infrastructure of Lake Turkana Wind Power Ltd, Kenya.

16 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

The first turbine to reach the site arrived last These things will kill your project, says James
March, nearly three years after the PPA was White, of SunEdison South Africa. It also means
signed, shipped from Tianjin in China. Such projects might take longer to deliver.
challenges impact the connecting up of assets:
the cost and the challenge of getting utility- Building a 10MW solar project in a landlocked
scale projects connected up is significantly country without a mature local solar supply
greater in Africa than in other parts of the world, chain such as Uganda takes about 6 months.
says Nico Tyabji, senior associate at Bloomberg In developed markets, the same 10MW could
New Energy Finance. probably be delivered in a matter of few weeks,
says Reda El Chaar, executive chairman of Access
For developers, such challenges mean proper Power, an investor in the 10 MW Soroti project in
prior planning is key. You cant go into the Uganda.
middle of Ethiopia and say Today Im going to put
a wind farm up here or a solar farm when there Interestingly, having to invest heavily in projects
are no roads and there is no access to the grid. is leading some companies to act both as

Financial components of Lake Turkana wind power project

Financing structure
Equity Debt

Subordinated Development finance institutions including


debt DEG, AfDB, PTA bank and EADB
IFU, KP&P Aldwych Vestas
Norfund, (co-developer) (co-developer) (turbine
Financiers including AfDB, EIB, export
Finnfund supplier)
Senior credit agencies, commercial banks
debt (Standard Bank, Nedbank) and develop-
Equity financial instrument: European Investment Bank ment finance institutions (Proparco, FMO,
PTA bank)

Lake Turkana
Wind Power Ltd

Revenues Costs

Engineering, procurement
Operation & Maintenance
and construction

20-year purchase power


agreement (PPA) with Kenya Other
Power for 8.42 US cents/kWhr contractors, 15-year service and
Vestas including availability contract with
civil and turbine supplier Vestas
electrical

Source: Lake Turkana wind power project official website.


17 The Economist Intelligence Unit Limited 2016
Power Up: Delivering renewable energy in Africa

developers and vendors: Vestas is one example. risk of delay is passed on to the EPC9 contractor.
The Danish turbine maker does not ordinarily But passing a risk to another entity does not
invest in energy infrastructure, preferring to be necessarily mean that risk no longer exists. It
an equipment vendor, but made an exception just means that a different entity is pricing it,
in Lake Turkana. Investment is not our core and that means we face a contractor premium
business, so we normally do not invest even in in markets that have a challenging execution
wind parks. But, on certain occasions, and this environment.
was a special occasion, co-development, is a way
forward to make sure the project is established, The worry is that these costs offset the benefits
says Nils de Baar at Vestas. of falling technology prices. When you start
looking at capex for individual projects, some can
Taken together, supply chains, borders and be almost double the global benchmark prices.
logistics challenges can impact construction This doesnt seem right, because the whole point
risk. The way to deal with that is very much the is to take advantage of the cost reductions driven
same as any other infrastructure project. In the by other parts of the world, says Tyabji at BNEF.
majority of our projects, notes El Chaar, the

Nigeria: Brightening Africas biggest economy


When the power went out at Ita-Elewa Primary This is a luxury. Nigeria is Africas biggest
Health Centre in times gone by, workers economy and home to one in five of its people,
would occasionally pay to keep the lights on but power blackouts hamper development. The
themselves. Nowadays, they do not worry about countrys total capacity, including fossil fuel
the dark. Two enormous solar panels tower over generation, is over 6,000 MW, of which only
the scruffy single-storey clinic in Ikorodu, a far- 3,500 MW is tapped. South Africa has over 11
flung corner of Lagos. times that. Consequently, just under half of
Nigerians lack access to light.
Under the stifling sun, they produce more
than enough power to keep fans whirring over According to World Bank data, manufacturing
patients heads, and to support nine cooling firms experienced an average of 32.8 power
units, which store vaccines for the hundreds outages a month, resulting in a loss of 10-15%
of children who are carried in for check-ups in annual sales10. Big headquarters in Lagos
daily. We used to have to keep two generators spend enormous amounts on diesel to fuel
running to support those, a doctor says, generators which they rely on for most of their
gesturing to the fridges. Now we dont have to power needs.
pay for anything.
Partly, this is because the Nigerian privatisation
Ita-Elewa is one of 11 primary healthcare process was hit with problems, including
centres and 172 schools which have been lit strikes which prevented several investors from
up since the Lagos Solar Project launched last inspecting their assets before purchasing. When
9
Engineering, year, funded by the Lagos State Government they took over, they found infrastructure in
Procurement and with assistance from the UK Department for disrepair, or poorly mapped customer networks.
Construction International Development. The goal of the
project is to provide vital power to a community Nigerias power plants mostly generate
10
2014 World Bank data, who are mostly rural and riverine, and not electricity using gas - which it has plenty of. But
World Bank Enterprise connected to power lines. Some people simply low prices set by the government encouraged
Surveys, Power outages in could not keep up with their bills. Today, the oil producers to flare it off rather than selling it
firms in a typical month. projects photovoltaic cells produce a total of at a loss, and vandals regularly attack pipelines.
Available at: http://data. almost 5 MW of power, making it the largest off- Even if plants could produce more, the public
worldbank.org/indicator/ grid solar programme in West Africa, according grid cannot carry it. Distribution groups have
IC.ELC.OUTG. to the Lagos State Electricity Board. failed to collect adequate revenue, so the sector

18 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

has fallen into a quagmire. By March 2016, launching its first 20 MW solar plant in Senegal
Egbin, the countrys biggest independent power and hopes to build a 600 MW portfolio in Sub-
producer, was owed 40 billion Naira by the bulk Saharan Africa. EU donors are investing in
trader. micro-grids, and the Lagos Solar Project hopes
to show that the suns energy is reliable.
Developing alternative sources of power is
essential. Yet Nigeria has lagged as other However private investors contend with
African countries diversify their energy mix. doubtful consumers, cheap electricity tariffs
Large hydro projects should contribute about and fuel subsidies which make renewable energy
1,800 MW to the grid, but they underperform. less competitive. On larger projects, industry
A wind farm in the northern state of Katsina experts complain of regulatory uncertainty or
should have been generating 10MW of power lack of enforcement. The challenge is that the
by now, but development has stalled. High government doesnt want to subsidise solar, and
construction costs make solar projects more would rather develop gas if its cheaper, one
expensive than in other African countries. investor argues, on the condition of anonymity.
Excluding large hydro, just 0.1% of the countrys
Some positive signals have come from a new power currently comes from renewable sources.
government which swept to power in Nigerias
first democratic transition last year. New Successive administrations have failed to
regulation, which entered into force in February meet power production targets, so lofty
this year, sets up dollar-denominated Feed-in- ambitions should be treated with caution. The
Tariffs with 20 year PPAs and a 50% renewable government has started (but not yet completed)
energy procurement goal for electricity very important and constructive reforms. Their
distribution companies. Nigeria also has several successful implementation is key to provide an
hydro projects under construction, which are enabling environment for private investment
equivalent to nearly 5 GW. says Henning Wuester, director of knowledge,
policy and finance at the International
Late last year, a 450 MW greenfield power plant Renewable Energy Agency.
called Azura-Edo raised $876 million, providing
a framework for project finance for Independent Nigeria needs a stronger roadmap for renewable
Power Producers (IPPs) in Nigeria. Leaders say energy development, along with robust
they are now negotiating major PPAs which will guarantees. While setting tariffs for large solar
allow the country to generate 10% of its energy projects, the government needs to take into
(a target of 2,000MW) through biomass, small account Nigerias full energy mix, including not
hydro, wind and solar by 2020. Conventional just gas, but the expensive fuel that supplies
base-load power plants are required to anchor most of its electricity needs, states Ms Aubin
utility scale renewable power projects, argues Kalaidjian at GreenWish Partners. Controversial
Batchi Baldeh, head of power at the Africa fuel subsidies, which dried up earlier this year
Finance Corporation. when oil prices bottomed out, must be abolished
to make renewables more competitive.
Off-grid solutions are also increasingly sought Renewable energy is a new concept in oil-rich
after as the costs of technology fall. Companies Nigeria, says Abayomi Adebisi, of the Federal
tired of paying big diesel bills are increasingly Ministry of Power. But with continued attention,
looking to install solar panels, says Charlotte it could provide some light at the end of the
Aubin Kalaidjian, founding partner at GreenWish tunnel for Africas biggest economy.
Partners, a Paris-based group which is

19 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

3 Programmes or projects?

High capital costs, execution delays and risk high returns, but it is not going to give you scale;
mean most of Africa is not attracting sufficient for that you need a clear enabling environment
renewable infrastructure investment, but implemented through transparent procurement
there are innovative approaches afoot. Most programs, says White. As a large scale IPP
notable are government-led renewable energy renewable energy developer you need to be
procurement programmes which provide selective on where you invest your time and
structure, investor certainty and a policy signal money which is especially relevant in Africa due
to the private sector. The landmark was South to the added market entry barriers. A once-off
Africas Renewable Energy Independent Power project opportunity of fifteen megawatts in
Producer Procurement Programme (REIPPP) and Mauritius is 15 MWs in Mauritius, but 50 MW in
other, smaller countries, notably Uganda and Zambia, in a stated programme that will consist
Zambia, are following suit. of 600 MWs backed by the World Bank provides
a medium or short term pipeline that is part of
Greenfield projects are a great way to attract a longer term vision, and thats where you can
private equity investors looking for opportunistic
Average bid price of Solar PV under South Africas REIPPP program - Rounds 1 to 4
(R/MW)

4.0

3.44
3.0

2.0
2.05

1.0
1.10
0.85

0.0
Bid window 1 Bid window 2 Bid window 3 Bid window 4
Source: South Africas Department of Energy, 2015

20 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Average bid price of onshore wind under South Africas REIPPP program - Rounds 1 to 4
(R/MW)

2.0

1.5
1.42

1.0 1.12

0.82
0.71
0.5

0.0
Bid window 1 Bid window 2 Bid window 3 Bid window 4
Source: South Africas Department of Energy, 2015

justify the development time and money, he for renewables, says Reda El Chaar of Access
adds. Power, adding that when you see true political
commitment, things move.
Dr. Tobias Bischof-Niemz at the Council for
Scientific and Industrial Research in South Continuous support from the Kenyan government
Africa, believes programmes are necessary has been key for Lake Turkana, says Phylip
to give investors the scale they need. A 50 Leferink, general manager, Lake Turkana Wind
MW wind farm is a big renewables project in Power Ltd. There were two governments during
Africa, but compared to other infrastructure the development phase and both governments
investments its tiny, with less than $100 million have been very supportive of the project.
investment volume. You dont want to go into
a project-by-project approach, with project- But political willingness is not enough: there
specific negotiations, project-specific PPAs, or must also be technical capacity to deliver.
project-specific connection agreements. When Some tenders have been issued with very short
combined with a competitive bidding procedure, deadlines, says Georgios Pergamalis, head of
a programmatic approach can reduce the costs business development for Africa and the Middle
of procuring renewable energy. In the five years East at Enel Green Power. If you want to get
since South Africas first auction in 2011, for pricing down, people need the time to do their
instance, the costs of power from new solar and homework and optimise their bids he adds. Lack
wind procured through the programme have gone of capacity can lead to projects being delayed,
down by 75% and 50% respectively. or cancelled. Bandwidth is also an issue. James
White recalls a Namibian project that stalled
not because it was not technically feasible but
Committed governments
because the people qualified to validate it simply
To be successful, renewable programmes need
didnt have the time to work on it.
a committed government. When it comes to
renewables, the majority of Sub-Saharan African South Africa boasts the technical capacity to
countries have the ingredients. What were incite investment. The PPP Unit of the [South
missing are the chefs to put these ingredients African] National Treasury was a massive stamp
together. There needs to be a local champion of approval and halo effect from day one, because

21 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

its head and the department had a strong track and its Get Fit programme is another good
record of delivering infrastructure projects example he adds.
notes Johnstone, about South Africas REIPPP.
African developers, global partners
Wide-ranging consultation has also been a
A thriving clean energy sector cannot be
hallmark of South Africas strategy. South
achieved without local expertise. As South Africa
Africas approach was to consult widely with
shows, international developers still play an
experienced advisors, developers and financiers
important role in deploying renewable projects
to develop a bankable suite of projects and
on the ground - but most will partner with local
government documents. Other countries seeking
developers and/or have their own local branches.
to unlock their own renewable energy markets
would do well to follow this example says Musso. The challenge is thus not lack of talent. Africa
has well-educated and capable entrepreneurs
Kenya is also well-positioned, according to El
that can come up with meticulously thought-
Chaar: In markets like Kenya that have been
11
As in AccessPowers out concepts says El Chaar. But there has not
doing IPPs successfully, you have a capable
Co-development Facility, been enough early-stage credible, international
which selects investments
counterparty that understands IPPs so youre
technical capabilities followed with financial
through a prize competition able to easily discuss risk allocation, and they
commitment to really bring those significant
in which donors are part of generally have the capacity. But when you go into
concepts to life. This is the biggest issue today in
the judging panel. The US$7 trickier markets where they have not concluded
million financial support Africa.
IPPs before, the discussion becomes significantly
mechanism fund prize, in
more challenging, just because the institutional One-stop-shops, such as developed by Climate
its second year, is designed
to help local power project
capacity is not there. Fund Managers (Climate Investor One) or Access
developers and originators Power (the Access Co-Development Facility),
with technical experience, Thankfully, interviewees see momentum. I am
is one way the private sector is responding.
expertise and funding very positive on the new federal government of
From the developers point of view, one-stop-
required to bring projects Nigeria says Johnstone. If you look at Lagos
to financial close. The first
shops reduce transaction costs by providing
State over the last five years, thats a jurisdiction
round saw 55 submissions easier access to partners, technical experts and
that has done PPPs and they know how project
from 18 countries across investors11 while investors benefit from lower risk
finance works. Some of these PPPs are good,
Africa, with technologies profiles thanks to the portfolio diversification
including solar, wind, some are bad, but if they can supersize that at
these facilities provide.12 Other facilities include
hydro, hybrid and bio-mass federal level then youve got the same sort of
the $350m IRENA/ADFD Project Facility and the
projects. dynamic that the National Treasury did for the
$10m Project Support Facility of the African
Department of Energy in South Africa.
Renewable Energy Fund. The result, long term:
12
ClimateOne offers five
Zambia, Ethiopia and Tanzania are also a rise in the number of African-led bankable
different risk/return
options across the life of promising. Zambias Scaling Solar programme projects. Doing business with people who
a project, from a $50m and Ethiopias recent expression of interest understand Africa and are using African money is
development fund (donor
are demonstrating that African governments an incredible opportunity for the continent says
invested), to a construction White.
are realising the power of well-structured
equity fund structured in
three tranches ($100m, procurement programmes, says White. Uganda
$200m, $200m) with donor
funding taking the more
risky tranche while the least
risky one is targeted for
commercial lenders, and a
$500m re-financing fund
opened to both public and
private investors.
22 The Economist Intelligence Unit Limited 2016
Power Up: Delivering renewable energy in Africa

Uganda: Going solar


East Africas largest solar power plant, led by by Ugandas Electricity Regulatory Authority
Access Power and EREN RE, shows the rollout and paid for by Ugandan electricity customers.
of programme-led approaches in smaller Donors subsidise each kilowatt hour by 5.37
economies. Currently under construction on the while the national electricity distributor pays a
outskirts of Soroti, a small town 300 kilometres feed-in tariff of 11/kWh. The project is planned
northeast of the capital, Kampala, it will provide for a 20 year lifetime. Uniquely, the donor-
enough electricity for 40,000 homes and funded top-up payments were front-loaded so
businesses. that developers receive all the top-ups in the
first five years of operation.
However, establishing the plant in rural Uganda
has been far from easy. 32,680 photovoltaic Soroti: a helping hand
panels, on one site, are south-facing. To If successful, this project can make a significant
avoid maintenance requirements, they do not difference to the lives of Ugandans. Sitting
contain parts that would allow the panels to in the shade of a tree outside his mud-walled
track the movement of the sun. Ive worked on hut in Opolai village, a 10 minute drive from
renewable energy projects across Europe, USA, the Ugandan town of Soroti, Michael Obale
Mexico, Brazil, Philippines and Pakistan, says discusses the difference that grid-connected
Jorge Lopez Galera, Access Powers Engineer on- electricity would make. As his mobile phone
site in Soroti and this is the most difficult yet. charges from the solar panel lying on the hot,
red earth, Obale, an agriculture graduate from
The challenges are social and technical, explains Gulu University, says the biggest advantage
Galera. We are bringing something completely would be safely storing and transporting his
new..we have to act sensitively. In some ways produce of sweet potatoes, mung beans and
we are like an NGO, making suggestions and sesame to market.
supporting local people. We dont leave them
aside, we make them a part of the project. We need to develop a cold chain for perishable
items once they have been harvested so as
The biggest challenge is sourcing materials to reduce waste. Too much of our food goes
in this landlocked country. The machine hire bad in the heat before we can sell it. We need
companies we approached in Uganda had never regular electricity here. In Opolai village, Obale
heard of some of the heavy equipment that we considers what the solar plant, which he has
wanted. We had to go to Nairobi to buy poles visited, could mean to him. Its simple, with
for the medium voltage line. In Brazil and the electricity I could do agro-processing, grinding
Philippines, they were easy to find. millet before I take it to market - making more
money. Potentially, I could build a permanent
Delays affect goods sent from Asia or Europe, house and have a better life.
adds Galera, If an inverter [a device that
converts direct current to alternating current] For local businessman Emmanuel Okalebo,
breaks in Europe it can be replaced in three reliable long-term power supply allows him to
days. Here you have to send it to Germany to be plan ahead. Surrounded by busy workers in
repaired. That takes time and pushes up costs. his packed electrical repair shop in Soroti town
Even in Pakistan it was easier. Parts can be centre, Okalebo explains that the electricity
imported from India next door. supply regularly shuts off. Last week it was
almost every day. My customers travel here
To entice the private sector, the Ugandan by bus - some from as far as Pallisa. Okalebo
authorities authorised an innovative bidding describes the journey from a town about 100
and financing program, Global Energy kilometres from Soroti,
Transfer Feed-in Tariffs (GET FiT). The German
international development agency, KfW, and The roads are very bad, the buses dont run
four European donors provided top-up payments on time and sometimes break down. Customers
that would be added to the feed-in tariffs set have to pay to transport their appliances, when

23 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

they get here and the power is off I cant test Investors in his Mandulis Energy project hired
and fix their gadget. Theres nowhere they can three World Bank-approved consultancy firms
afford to stay overnight in town so they travel to test the feasibility of the proposal. All
back and return the next day. Only, many of three endorsed the plan. Nyeko says that the
them never come back. Theyve lost money and conservative nature of local bureaucrats stifles
Ive lost business. Its too uncertain. Okalebos development. The technical capacity in the
only concern about the new power plant is energy ministry doesnt exist to understand
that it will not help to reduce prices, which he non-hydro or non-combustible biomass. Theyve
considers too high. gone for the simplest solar solution but its not
the most cost effective.
Peter Nyeko, a renewable energy developer,
says the GET FiT program needs to go further to The Soroti project is straightforward. Complex
deliver its full potential. The former aerospace hybrid energy proposals are riskier but have the
engineer says his proposed hybrid biomass-solar potential to reap bigger rewards. As Ugandan
combined on- and off-grid project could deliver expertise in diverse forms of renewables
electricity at 11/kWh without any subsidy13. I increases, authorities may wish to consider
see what theyre doing at Soroti, good on them. more elaborate systems which push innovative
But we can deliver similar quantities of energy on- and off-grid techniques.
without subsidies leaving money to be spent
elsewhere or allowing end customer costs to be
reduced.

Zambia: Relying on the rains


Zambia is a second African country advancing its peak capacity gobbles up 160 MW of power, or
a programmatic approach, to deal with the about 7% of total installed capacity in Zambia.
countrys over-reliance on hydroelectric power.
Like Uganda, this is a relatively low income, Making matters worse, construction of two
landlocked economy building a renewable new power plants - which were meant to meet
energy industry with little existing experience - this added demand - fell behind schedule.
especially, in Zambias case, outside of hydro. Thankfully, steady rains through the early
months of 2016 helped avert a catastrophic
Since independence in 1964, Zambia relied on escalation of the electricity crisis, replenishing
large hydropower plants in the south of the perilously low water levels that threatened to
country to send electricity along a north-south worsen the rolling blackouts that became a daily
transmission corridor to Lusaka, the capital, affliction beginning in summer 2015.
and on to large copper mines further north.
For decades, electrification remained limited Zambias power deficit will take years to correct,
primarily to end users near the grid, leaving especially at the 1,080MW Kariba North Bank
most of the eastern and western parts of the power plant where power stations on both the
country without electricity. But beginning in the Zambian and Zimbabwean side of the Zambezi
1990s Zambian authorities became aware that River consumed far more than their allotted
new power plants were needed. More recently, water supply over the course of 2015 and into
the risks of hydropower-based energy have early 2016. In February 2016, the reservoir at
become increasingly apparent. Kariba Dam fell to only 1.5 meters above the
level that would necessitate a full shutdown of
Zambia is dependent on hydropower for almost the plant. Although seasonal rains have slightly
all of its supply needs. Last year, Zambias two replenished the reservoir, it remained only 17%
largest hydro power plants drastically reduced full as of late March, compared to 49% last year.
output due primarily to regional drought. At the Refilling the lake will require a series of healthy
same time, major sources of new demand came rainy seasons coupled with a moderation of
13
The Soroti project subsidy online, led by First Quantums giant Sentinel output from the power plantneither of which
is USc 5.37/kWh. copper mine in North-Western Province which at are a certainty. In the meantime, Zambia must

24 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

rely on much more expensive imported power to Corporation (IDC), an investment company
avoid even worse blackouts. wholly owned by the Zambian government, to
plug the gaping supply deficit with up to 600 MW
The power crisis comes at a particularly bad of solar power. The IDC subsequently partnered
time for a copper-dependent economy reeling with the International Finance Corporation to
from tumbling prices. Amid these electricity and roll out its Scaling Solar program offering a
economic challenges, the Zambian government rapid and transparent tendering process along
is searching for long-term solutions. with bankable project documents backed by the
The need for investment in power infrastructure World Bank.
has galvanised interest from international
Under Phase 1 of the program, two 50 MW
donors and private sector players to not
projects will be built on the Lusaka South
only reduce the deficit but also improve
Multi-Facility Economic Zone. From 48 firms
electrification rates in the countryonly 25% of
that submitted applications, the IDC invited
the population has access to electricity, a figure
eleven pre-qualified bidders to submit proposals
that drops to a paltry 5% for rural Zambians,
to build the projects. Among these firms are
according to the Ministry of Energy.
multinationals like EDF Energie Nouvelle of
On top of domestic needs, the most ambitious- France, Chinas Shanghai Electric Power, and
minded investors see Zambia, with its links Enel Green Power of Italy, and large investment
to the Southern and East Africa power pools, funds including the UKs Globaleq and the Old
as a potential exporter to the region. The Mutual-backed Africa Infrastructure Investment
long-delayed 300 MW Maamba Collieries coal Fund 2, based in Mauritius.
project should come online in summer 2016 and
another coal project is in the works, and several Charles Mate, executive director of Corporate
hydropower projects in the wetter north of Affairs at IDC, noted: we were obviously
Zambia are in development. pleased and impressed by the interest in
Scaling Solar. It was more than we expected,
The need to diversify power has brought solar and a revelation of the pent-up demand from
to the fore. A small number of projects were the private sector for investing in the Zambian
initiated before the crisis but now have a power sector. Scaling Solar will name the
renewed impetus. BioTherm, a South African winners of round 1 and launch Phase 2 of the
Independent Power Producer (IPP), is one program for a planned 200 MW in the coming
beneficiary. The company was a preferred months.
bidder in a 2013 solar tender issued by what
was then the Ministry of Mines, Energy and Also this spring, the Ministry of Energy is
Water Development and is currently negotiating expected to introduce Zambias first Renewable
a power purchase agreement (PPA) for four Energy Feed-in Tariff (REFiT) Strategy. The
projects in Eastern Province totaling 10MW. strategy aims to incentivise the construction of
200 MW of renewable energy projects between
According to Jasandra Nyker, CEO of BioTherm, 1-20 MW, half of which is set aside for hydro and
Zambia should be lauded for being the first the other half for other resources, including
Sub-Saharan African country outside of South solar. Zambian stakeholders have partnered
Africa to run a solar tender, adding that while with donors, with the Energy Regulation Board
Zambia is taking longer than South Africa, we (ERB) linking with USAID to set the initial
are accomplishing our objectives and are ready REFiT guidelines and the Department of Energy
for financial close. asking KfW, the German Development agency, to
help implement the REFiT Strategy using KfWs
Two other government-sponsored solar Global Energy Transfer Feed-in Tariff (GET FiT)
initiatives are underway that, if successful, will program. GET FiT was first deployed in Ugandas
drastically increase the profile of solar power inaugural 170 MW REFiT program, where grant
in Zambia while offering more transparency funding closed the gap between the price the
to the procurement process for building new utility could pay and tariff levels acceptable
power plants. Early in 2015, President Edgar to private developers. In Zambia, GET FiT will
Lungu directed the Industrial Development

25 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

similarly address the tariff gap as well as offer a Copperbelt Energy Corporation (CEC), a
grid connection facility, risk mitigation support, Zambian power company listed on the Lusaka
and a technical assistance facility that provides Stock Exchange, said: From an institutional
standardised legal documentation for the REFiT perspective, we need a central coordinating
program. Solar developers have already shown body charged with implementing policy and
interest in REFiT, with several experienced the various programs meant to meet demand.
international companies as well as local firms Charles Mate agrees, noting that the South
busy identifying land sites and initiating the African renewable energy model is a good one
regulatory processes in Zambia as the program for Zambia, as you get very clear price discovery
takes shape. there through a procurement process that is
competitive and transparent.
The exact amount of solar capacity that can
be absorbed by Zambias grid is unknown, but Given near-term counterparty risk for solar
studies are underway to provide clarity. The projects with ZESCO as the offtaker, some
technical limitations of a grid with only about developers are eyeing off-grid or so-called
2,450 MW of installed capacity is one challenge private-to-private solar power solutions. These
facing developers, but another more daunting captive power plants provide a viable option for
one is Zambias extremely low power tariffs. companies seeking to lower dependence on grid
supply and dirty and expensive backup diesel
Electricity has historically been extremely cheap generators. As seen in several East African
in Zambia, due mostly to reliance on large hydro countries ahead of Zambia in promoting off-
projects that have already been paid for, but also grid solar, this avenue also offers a more rapid
because the government keeps tariffs artificially solution to electrifying rural areas.
low. With a weighted tariff of only about $0.04/
kWh, there are concerns that ZESCO will struggle Solar will play a big role in the electrification
to sign off on the solar projects in development of Zambia and in addressing the current supply
that will require over $0.10/kWh (or significantly gap, says Silavwe. CEC is exploring hydro and
higher depending on the project size) to be solar prospects in Zambia and is participating
viable. in tenders run by Scaling Solar and the Ministry
of Energy, and considering private-to-private
Sipho Phiri, executive chairman at Western projects with some of their mining customers in
Power, an IPP developing hydro and solar Copperbelt Province. Silavwe states that tariffs
projects in Zambias Western Province, notes: are the biggest obstacle to investing in solar in
ZESCO understands that they must have a Zambia, but if we can get a 20 MW project online,
viable tariff or else the banks arent coming and we think we can encourage further projects.
power isnt coming. An initial attempt by the Starting small is appropriate in this market.
utility to raise rates late last year was reversed
by President Lungu in January, and no rate Donors are also advancing off-grid power, with
increase is expected until after the August 2016 the US and Swedish governments partnering on
national elections. It is likely, however, that an initiative called Beyond the Grid providing
some level of tariff hike will come before the end funding for a range of off-grid projects. The
of the year. program is targeting private-sector investors,
and aims to assist companies reluctant to deploy
Another obstacle facing investors is the lack of capital in non-core activities like building an
a publicised planning document that specifies on-site solar power plant but might instead
Zambias power sector strategy and prioritises be interested in becoming an off taker for a
power projects for development. Zambian project built by a dedicated IPP. The opportunity
officials are deluged with direct proposals for is vast, extending from the mining, industrial
grandiose plans to transform Zambias energy and commercial sectors to clinics and schools
landscape with massive solar arrays. These in villages. But, noting the various financial,
approaches appeal to a country in crisis, but the technical and political pitfalls that can slow
sheer number of firms seeking this route also projects, Mate warns that there are windows of
muddies the investment landscape. opportunity, and these windows can shut very
quickly.
Owen Silavwe, managing director at the
26 The Economist Intelligence Unit Limited 2016
Power Up: Delivering renewable energy in Africa

4 Africas bespoke grids, and the


innovators driving the market

Energy projects do not exist in a vacuum: the grid with a significant size to accommodate that
African grid will be essential to the smooth power. But if you implement a more distributed
functioning of the overall power system. approach and go for 5-10 MW projects instead,
One strategy is to strengthen regional power you can connect to the existing grid much more
pools. According to McKinsey, this could cut by easily he says.
$40bn the $490bn of capital investment in new
generation capacity needed to meet Africas Off-grid: Game on
energy needs. Increased connectivity between In 2014, $17bn was spent in Sub-Saharan
countries could reduce the average cost of grid- Africa for off-grid energy services, according
connected power by up to 10% in the case of the to BNEF. While nearly two thirds of that (63%)
East African Power Pool. was spent on kerosene, the broader market is
growing quickly. Tanzania, with a 70% rural
Grid extension and power pooling takes time,
population, has been active in off-grid, providing
however; and with 645 million people in Sub-
standardised tariffs and PPAs and simplified
Saharan Africa lacking energy access today,
procedures for mini-grids. Kenya and Rwanda
decentralised solutions will be required, notably
have picked up pace, with the latter recently
in rural areas where stand-alone and mini-grid
partnering with UK firm Ignite Power to deploy
solutions are expected to meet 70% of the
off-grid systems in 250,000 homes by 2018,
demand of newly connected customers over the
as part of the countrys goal to achieve 70%
next 25 years, according to the International
electrification rate by June 2018.
Energy Agency.
The off-grid market is large and its value
Increasingly, developers are seeing the beauty
proposition is clear: the cost of a solar lamp can
of smaller developments. Deploying large-scale
be recouped in a matter of months. Its structure
renewable energy projects in networks with poor
is also very different than what most people
transmission and distribution infrastructure is
imagine. While most off-grid dwellers in the
a challenge, and one solution, says Dr Bischof-
poorest countries live on under $2 a day, in
Niemz, is to deploy smaller capacities across the
larger economies like Ethiopia or Kenya, more
national grid network. If you want to connect
than half live with a disposable income between
relatively large renewables projects in the
$2-$10/day. These are people who would have
hundreds of MW then you need a transmission

27 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

the money to pay for the grid if it was there, says several years - Solar City issued the first solar
Thomas Duveau, head of business development bond in 2013 - and it has strong potential for
at Mobisol, an off-grid energy service provider of the African market. The next 10,000 customers
solar home systems active in Tanzania, Rwanda, become a 1MW project with a stream of cash-
and soon in Kenya. While the scale of each flows associated with it and collateral; its
project is limited, small scale solar off-grid is standard asset-backed finance, says Duveau.
growing fast.14 This year, were on track deploy The first securitisation for small scale off-grid
4 MW. Next year were targeting more than 8 MW. solar in Sub-Saharan Africa took place in January
Deploying a large scale project of similar size this year, by BBOXX, through a $500m issuance
would take longer than that says Duveau. corresponding to 2500 contracts in rural Kenya.

This consumer market is allowing a range of Berkeley-based Powerhive is another microgrid


offerings, from pico-scale products of just a few innovator. Among their technologies is Asali,
Watts that enable lighting lamps and charging a stand-alone distributed metering system
a phone, to more expensive solar home systems which services customer clusters. This creates a
of 100-200 Watts that provide electricity for microgrid that accommodates communities of
lighting, charging and appliances such as a TV, different sizes. Powerhive has also developed a
fan or fridge. remote cut-off system, called Honeycomb, which
helps companies offer flexible payment models
New and innovative business models are while ensuring their revenue is reliable. BBOXX
emerging based on the pay as you go model, has invented the same kind of remote monitoring
in which a customer pays via mobile for the system to reduce payment plan risks.
electricity consumed and access to electricity can
be cut in case of non-payment. One of the market Micro-grids can take longer to deploy but have
leaders is M-KOPA, an award-winning company larger capacity per project. It took Powerhive
which brought solar power to 330,000 homes in two years and four pilot projects in Kenya before
Kenya, Tanzania and Uganda, with its 8W battery- it could acquire the license to sell electricity to
powered systems, which have 3 lights, a mobile the general public, for instance. Now secured,
phone charger and a solar-powered radio. It however, the microgrid company is working
operates through 100 services centres and is a on deploying 1 MW worth of mini-grids across
proof of concept of a ready and willing market of 100 villages in Kenya, delivering electricity to
African energy consumers. 20,000 households and businesses. Kenyas
14
4.5 million pico-solar unit
rural electrification rate, combined with the cost
were sold in 2014 (from
Other Active firms include Germany-based of electricity access and average income made
nearly none in 2009). The Mobisol, which combines solar power with it a great case for investment says Georgios
Pay As You Go model is a mobile-based payments, and plug and play Pergamalis, head of business development in
small but rising part of the solar tech company BBOXX whose products Africa and the Middle East at Enel Green Power,
market (it doubled in size include 50W roof-mounted solar panels with which took an option to acquire a 93% interest in
in the first nine months of
mobile payments. Not only does this create an the 1MW project ($12m).
2015, according to BNEF).
effective incentive for payments, it also reduces
15
Since maintenance can
maintenance costs15 and builds a customer credit To some extent, thesemodels (off-grid solar
be done remotely and profile. and microgrids) are competing for the same
technicians are only sent market (rural electrification), albeit at different
when neither remote Applied to a large customer base, customer speeds and scale. The growth of one may affect
maintenance nor the user information provides the visibility needed to the other. Mini grids, for instance, might not be
(with whom the company package contracts together, opening the door viable in areas where small scale solar is present,
can interact via phone) can
to securitisation. The model has been in play for as the residual unmet demand of customers
fix the issue.

28 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

might not justify the investment. Reciprocally, to build in the old days because you have a lot
off-grid solar might not penetrate a market which of generation sitting right next to the load.
already has a mini-grid, although the focus of
off-grid solar on selling services as opposed to While these Africa-centric innovations will be key
just electricity - might give an entry point. drivers of the renewables market, it is important
not to forget the impact of continued innovations
What shape rural electrification takes in the long in the rest of the world. One crucial area will be
term is unclear. In mini-grids, the business energy storage, a key mechanism for dealing
model is still work in progress says Pergamalis. with demand spikes or variable renewable power
It is clear, however, that the rise of off-grid generation from intermittent sources like solar
power generation could create a new type of and wind. According to research by BNEF and
network altogether in rural regions, where UNEP, in 2015 some 250 MW of utility-scale
power networks are built from the bottom-up electricity storage (excluding pumped hydro and
as opposed to the top-down. It will happen in lead-acid batteries) were installed worldwide, up
a grass-roots way, says Dr. Bischof-Niemz. He from 160MW in 2014.
envisions supply being provided first in island
grids which gradually get interconnected. Last year brought notable global developments,
including the unveiling of Teslas rechargeable
While some economies of scale that would emerge lithium-ion battery for residential use. Forecasts
from this are similar to those of centralised by Deutsche Bank see the cost of lithium-ion
systems (including the portfolio effect of mixing batteries falling by 20 to 30% a year, potentially
different supply and demand sources, which bringing mass adoption over the next decade16.
leads to lower costs and higher security of supply As with the falling costs of solar panels, these
for each participating island grid), the key innovations take time to filter through to the
difference is that the interconnection between African market - but they can filter through in
two island grids is now much smaller in size than time.
the large transmission line that you would have

16
Deutsche Bank
Markets Research, 27
February 2015. https://
www.db.com/cr/en/
docs/solar_report_
full_length.pdf

29 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

Conclusion

The case for renewable energy infrastructure measures to support renewable infrastructure in
in Africa is strong. The price of wind and solar Africa include:
technologies is falling. Political ambition is there
- with nearly 40 countries penning renewables Cost-reflective tariffs based on publicly
targets. And the continent has abundant available cost of service studies: Artificially
resources. low tariffs, due to government subsidies, are
deterring investors and ultimately reducing
But the continent must level up to meet the power supply. To attract infrastructure
ambitious energy access goals it has set itself. investment, power tariffs must better reflect
South Africa, the most developed market, offers costs. Targeted subsidies to protect the poor can
several lessons in procurement programme improve access to power without deterring the
design. Kenya is a front-runner, with the Lake private sector from investment.
Turkana wind farm promising a very high load
factor and showcasing Africas considerable Transparency and harmonisation. Governments
natural assets. And others, including Uganda and should publicly publish key planning documents,
Zambia, are busily advancing their renewable like Integrated Resource Plans, and introduce
infrastructure sectors from a low base. As bankable and harmonised legal documentation
technology costs fall, especially in wind and including PPAs, Government Support
solar, the case for renewables grows stronger Agreements, and Connection Agreements.
still. And support from development finance Africa also needs strong, independent energy
institutions is bringing capital, de-risking regulators that can enforce competitive
investment and providing technical support. procurement.

However, between the renewables targets and Improve border customs efficiency. To utilise
the actual deployment trends, there is a sizeable renewable technologies, landlocked African
gap: the African Renewable Energy initiative nations must improve supply chain efficiency
goal to deploy 300 GW by 2030 requires a 680% so that developers can quickly move equipment
increase in current deployment rates17. This and replace parts like panels and turbines.
17
Defined as the
report, interviewing developers, financiers and Faster customs processes are vital to achieve
total net capacity of
renewables added each energy experts, has identified several enabling this. Capital expenditure on some renewable
year. factors essential to make that vision a reality. Top infrastructures in Africa are far higher than the

30 The Economist Intelligence Unit Limited 2016


Power Up: Delivering renewable energy in Africa

rest of the world, and customs bottlenecks are As these processes play out, developers need
one reason for cost escalation. resilience and patience, since renewable
infrastructure can, outside South Africa, take
Design renewable procurement programmes, considerably longer to deliver. You need to pump
rather than relying on one-off investments. a huge amount of effort into making contacts,
While investors occasionally pursue one-off understanding regulations and understanding
energy infrastructure projects, government- local laws, employment.and even so, things
backed renewable procurement programmes will take much longer than you expect before
are proving more likely to attract greater they really kick-off says James White. But while
investments in the long term. Following South Africa has its challenges, experts in this report
Africas lead, Uganda and Zambia are emulating believe it can offer rewards for those willing
the programmatic approach: other countries to navigate imperfect environments, adjust
could do the same. Transparent, standardised, business models based on context, and take the
and competitive programmes reduce risks for long view.
developers, and costs for governments. They
signal long-term policy commitment to green
energy, and build local expertise.

31 The Economist Intelligence Unit Limited 2016


About IHS Towers

IHS Towers is the largest telecommunications


infrastructure provider in Africa, Europe and
the Middle East, with over 23,300 towers in its
portfolio. IHS currently operates in Nigeria,
Cameroon, Cte dIvoire, Rwanda and Zambia and
is investing in renewable power solutions to both
improve energy and operational efciencies, and
reduce the environmental impact of its operations.

IHS has set itself the target of becoming largely


diesel-neutral through a combination of on and
off-grid solutions. Over the next few years, IHS
plans to become almost diesel neutral across its
Zambian portfolio and the company is assessing
solar farm opportunities in Rwanda that could
potentially supply power to the national grid in the
rst energy swap model to be used in Africa. To
date, IHS has invested over US$500 million in new
green energy power systems across its portfolio.

IHS is achieving its renewable energy goals whilst


integrating newly acquired towers into its network.
At the same time, IHS is maintaining network
uptime of over 99% in all of its ve markets,
with all tower sites connected to IHSs Network
Operating Centres so that they can be monitored
24/7.

www.ihstowers.com
LONDON
20 Cabot Square
London
E14 4QW
United Kingdom
Tel: (44.20) 7576 8000
Fax: (44.20) 7576 8500
E-mail: london@eiu.com

NEW YORK
750 Third Avenue
5th Floor
New York, NY 10017
United States
Tel: (1.212) 554 0600
Fax: (1.212) 586 1181/2
E-mail: americas@eiu.com

HONG KONG
1301 Cityplaza Four
12 Taikoo Wan Road
Taikoo Shing
Hong Kong
Tel: (852) 2585 3888
Fax: (852) 2802 7638
E-mail: asia@eiu.com

GENEVA
Rue de lAthne 32 While every effort has been taken to verify the
1206 Geneva accuracy of this information, The Economist
Switzerland Intelligence Unit Ltd. cannot accept any
Tel: (41) 22 566 2470 responsibility or liability for reliance by any person
Fax: (41) 22 346 93 47 on this report or any of the information, opinions
E-mail: geneva@eiu.com or conclusions set out in this report.

You might also like