DRAWING SUBMISSION STATUS

OF DETACHED, 26 UNITS OF SEMI-DETACHED & 16 UNITS OF TERRACE) ON 015372915 AT KUALA INANAM, OF JALAN TUARAN BY-
PASS, KOTA KINABALU DISTRICT
Project Name :

Project No. JPB/14-163


:
Local Authority
Description Document/Drawing No. Rev. Remarks
To Our Ref. & Date Status Authority Ref. & Date

DBKK DBKK Richard Kinki


Sewerage Water Roadwork Drainage

JPB/14-163/DBKK-(DR)/003 DR.03/04.2015/(JK)R/962
JPB/14-163/S-AP/CW/DR/01-07(A)
(Phase 1)
19 September 2016 13 October 2016

DBKK JPB/14-163/DBKK-(RD)/001 Pending TIA approval


JPB/14-163/S-AP/CW/RD/01-04
CIVIL

JPB/14-163/S-AP/CW/WT/01&02 JA JPB/14-163/JANS/02 JA James Swana


(Phase 1) 19 September 2016
JPB/14-163/S-AP/CW/SWP1/01, 02, 03, 04 DBKK JPB/14-163/DBKK-(SW)/003 Comments SEW.02/05.2015/R/962 DBKK Jack Lo
& JPB/14-163/S-AP/CW/SW/05A (Phase
1) 19 September 2016 2 Jan 2017