Site Diary: Avic-Mixed Development Project Engineer: Supervision Consultant: Contractor
Site Diary: Avic-Mixed Development Project Engineer: Supervision Consultant: Contractor
SITE DIARY
Date: 05/01/2016 Name : Situge S.M.J.M.T
Location
Basement at grid 27-29/E-F Tower crane base vertical plan was chipping
L03-L04 at 5-9/B-C Lift wall f/w was inspected
Basement to Level 01 Cracks inspection was done
Defects Noted/
Verbal instruction given to contractor
regarding defects
Collected information
General Comments:
swimming pool plumbing work was inspected. Defects were identified and informed contractor to rectify
* provided drain pipes get through swimming pool base slab and those
were placed without puddle coller * Drain pipe laid top on bottom reinforcement
*Outlet drain pipes in bottom slab were not
line *Some cracks were slowly generating
Signature:.. Date:05.01.2016..