Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Avic-Mixed Development Project

Engineer: Supervision Consultant: Contractor:


Central Engineering Consultancy
AVIC Hotels Lanka Pvt Ltd. CSCEC
Bureau

SITE DIARY
Date: 05/01/2016 Name : Situge S.M.J.M.T

Location
Basement at grid 27-29/E-F Tower crane base vertical plan was chipping
L03-L04 at 5-9/B-C Lift wall f/w was inspected
Basement to Level 01 Cracks inspection was done

Did you notice no


any non approved
Materials used at site /
Material used but don't know the status ?

Defects Noted/
Verbal instruction given to contractor
regarding defects

Studied the transfer floor drawings and shop drawings

Referred Method statements ,Drawings


and Engineer's comments.

Collected information

Plant & Labor Observations

General Comments:
swimming pool plumbing work was inspected. Defects were identified and informed contractor to rectify
* provided drain pipes get through swimming pool base slab and those
were placed without puddle coller * Drain pipe laid top on bottom reinforcement
*Outlet drain pipes in bottom slab were not
line *Some cracks were slowly generating

Signature:.. Date:05.01.2016..

You might also like