Batching Plant Installation Schedule With Comment Rev 24september2017
Batching Plant Installation Schedule With Comment Rev 24september2017
To make schedule at Site with following key point Start Concrete production shall
be after production test . It
1 Schedule for Foudation of BUMA meens that Production will
2 Schedule of USI to confirming with Project Manager Hendry (He will stay at site 2 weeks from Sep 12) start Dec.4 in eariest case
3 Check Material Availability supplied by USI and setting target receiving schedule(If not yet received)
4 Minimum Requirement for Production concrete:
(F)1Unit of Batching Plant, (G)Loading Ramp, (N)Labolatory, (C)Chiller, (J)Concrete Wash Pond
(H)Sediment Pond 1,(Q)Toilet, (R )Sewage, (T)Genset Shelter 1, Water Supply Line, Electrical Supply Line, Drainage
5 To dedicate water supply tie in point
6 Drainege must be planned at site and incorporating to This Schedule
CARIBLATION USI